Preview

Case Flashy Flashers

Satisfactory Essays
Open Document
Open Document
739 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Case Flashy Flashers
Inhoud
1 Recommendations 3
2 Planned order releases 3
3 MRP Explosion 4

1 Probable sources
Based on the case we have come up with the following list of probable sources
Long setup times
For a company that is using ATO it is weird that Wescot has such long setup times. This would mean that switching production is quite a long work, while you switch your setups a lot thanks to ATO.
Big lot sizes
This also goes for the lot sizes. However taking in consideration the long setup times the bigger lot sizes are understandable, still this is weird for an ATO environment.
Quite big difference in orders and forecast
Despite the fact that the difference is not so big when measured overall the question is how big is the range, is this process statistically controlled? The average difference is not so high but this only means that in the end is was all fine, but looking at some models in this data the differences are quite big.
Difficulty regarding staff flexibility
The fact that staff on this workstation is so difficult to replace makes it vulnerable to problems. Risk like sickness or busy periods will hit this workstation the hardest. Since this most looks like the Bottleneck facility it will also affect the whole process.
Short term planning
The planning is very short term and this is very weird for the master schedule. Its made once a week for the next week. This means that operations don’t have the complete picture and will have difficulty adapting to changing situations.

2 MPS
Based on reducing the inventory of finished goods to a minimum we made an MPS on basis of the minimum lot size. This was done based on the fact that this is an ATO environment so you want no stock in finished goods. Furthermore the case mentioned complains by the controller about the high stock levels in the company.
The forecast used is shown below.

Afterwards this forecast was translated into an MPS per model.

Now that its was done on the model basis this resulted in the following MPS for

You May Also Find These Documents Helpful

  • Better Essays

    MGT 330 WEEK 5

    • 1661 Words
    • 7 Pages

    “Planning is a systematic process in which managers make decisions about future activities and the key goals that the organization will pursue. The necessity of careful environmental scanning has an immediate impact on planning processes” (Reilly, Minnick, and Baack, 2011, sec. 7.2). Making plans for future activities is one of the Army’s key functions; without planning its subordinate commands would deteriorate and lose focus on mission objectives and the quality of work. In the Army, we use the Eight-Step Training Model; for which planning always starts out backwards by starting with the objective and working its way back to day zero. The planning is then broken down into three phases; long term, short-term and near term depending on the size of the organization or unit. I find the planning phase in the Army to be very effective because it is important for employees or soldiers to know what needs to happen in the days ahead. “The design methodology provides a means of approximating complex problems that allows for meaningful action” (Grigsby, 2011, p. 30). Proper use of planning in the Army keeps the employees motivated and goal oriented. When planning in the Army goes wrong, you have Soldiers sitting around waiting on orders, people go unaccounted for, and will eventually negatively affect the other four management functions.…

    • 1661 Words
    • 7 Pages
    Better Essays
  • Satisfactory Essays

    OPS/571 week 4

    • 402 Words
    • 2 Pages

    After MPS is created, it is now possible to determine the amount of inventory that is uncommitted, and hence available to promise. A "look-ahead" procedure sums booked orders week by week until (but not including) a week in which there is an MPS amount. For the first week, this procedure results in summing customer orders of 33 (week 1) and 20 (week 2) to obtain 53. Then, the amount is subtracted from the beginning inventory of 64 pumps plus the MPS in the two week 1 to obtain the amount that is available to promise, i.e., 64 + 0 - (33+20) = 11. For weeks other than the first week, the beginning inventory drops out of the computation, and ATP is the look-ahead quantity subtracted from the MPS quantity.…

    • 402 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    A master production schedule is used by business organizations as a metric to ascertain whether or not their production (outputs) meets their supply demands (inputs). There are times when a business wants to have a surplus and at others letting inventory dwindle to smaller numbers is optimal. The idea is to ensure that customers get their orders in a timely manner to retain loyalty, maximize profits, and reduce overhead and direct costs. The Realco Breadmaster Company has a new bread maker in the hopes of increasing their revenue. In question is the cost and efficiency of the new bread maker. The owner of Realco, Johnny Chang, wants a Master Production Schedule (MPS) designed.…

    • 2134 Words
    • 9 Pages
    Better Essays
  • Powerful Essays

    Bsbm504b Review Report

    • 3822 Words
    • 16 Pages

    It is a big problem Staff at the lack of recognition or understanding of the new system because they do not know how to use it correctly. It makes the task that was not great quality.…

    • 3822 Words
    • 16 Pages
    Powerful Essays
  • Good Essays

    Weco Paper

    • 838 Words
    • 4 Pages

    (a) From the data presented in Appendix 1, we conclude that idle Time, planned downtime and setup time are responsible for about 50% of the losses. Therefore, the Management at WECO needs to resolve these three key issues to reduce the lead time from 16-22 weeks to 10-12 weeks which in…

    • 838 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Littlefield Technologies

    • 328 Words
    • 2 Pages

    From days 51 to 97, we noticed the bottleneck occurred at all stations, depending on how many new kits were coming in. As a team,…

    • 328 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    To decrease the current inventory level and set up a more efficient inventory management system, two main alternatives should be considered. Firstly, related policies could be revised to alleviate this inventory problem; secondly, the warehouses could be rearranged and restructured to address the inventory issue. However, the first proposal of revising polices were found to be undesirable among sales managers as they believed it would undermine their influences on the…

    • 1251 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    Flextronics Case

    • 1236 Words
    • 5 Pages

    Flextronics prides in a work culture that values fast and very decisive actions. Jim McCusker is at the epicenter of a task conflict. This group decision making process of choosing a shop floor system has to be completed and fast. Time is running out and the geographical distance between the locations is a challenge. Bringing all parties together through teleconferencing offers him a great way forward. Datasweep Software shop floor system is the best alternative.…

    • 1236 Words
    • 5 Pages
    Good Essays
  • Better Essays

    Incident Response Plan

    • 930 Words
    • 4 Pages

    With that being said, the plan needs to be practiced and tested regularly in order to detect flaws or just simply to improve timeliness. Technology evolves so quickly that these plans must stay up to date as well.…

    • 930 Words
    • 4 Pages
    Better Essays
  • Satisfactory Essays

    Master production scheduling plays an important role in the balancing of demand with the supply i.e. satisfying customers according to the limits of the factory and the supplier’s base. MPS is used to know the number of the items that are to be produced, the planned inventories of raw materials, finished products and parts etc. MPS tells the company what is to be made or produced and also refers to the time in which this production of the products is to be completed. It must be kept in mind that MPS does not act as a sales forecast or as a manufacturing schedule or a wish list or a final assembly schedule. MPS can be linked only with the final products and not with the planning involving the production of parts or the components, as these listings require very detailed planning – so these are left to the other plans that will follow this schedule.…

    • 577 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Despite I did not stay here for this one and a half month to monitor the whole process of running the new system and had very limited information relating the failure, I figured out the main failure may be disconnection of the four components of information system. Besides technology itself, dropping any one of people, process and structure would harm…

    • 711 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    How did you derive your forecast? Why did you choose the “base case” assumptions that you did?…

    • 1657 Words
    • 7 Pages
    Powerful Essays
  • Better Essays

    Trends in the Workplace

    • 1135 Words
    • 5 Pages

    Material Requirements Planning (MRP) is a production planning and inventory control system used to manage the manufacturing process. Most MRP systems are software-based. However, it is possible to conduct MRP by hand as well. The intent of a MRP system is to simultaneously meet three objectives; (1) Ensure materials are available for production and products are available for delivery to customers; (2) Maintain the lowest possible level of inventory; and (3) Plan manufacturing activities, delivery schedules, and purchasing activities.…

    • 1135 Words
    • 5 Pages
    Better Essays
  • Good Essays

    The Morrison Company

    • 1011 Words
    • 5 Pages

    o Availability of machines has decreased, there are concerns that some of the assembly machines do not work correctly…

    • 1011 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Top 1 Cause for Project Failure

    • 65038 Words
    • 261 Pages

    #7. Scope Creep/Unrealistic Expectations ( scope creep: Frequent and uncontrolled changes in the scope or requirements of a project)…

    • 65038 Words
    • 261 Pages
    Powerful Essays