|Sr No |KRA |Area of Improvement |Plan/Steps for improvement |
|1 |Achieve Planned target of Tower ‘B’ |) Micro Scheduling |1)If VFC drawings are not received in well in advance then|
| |Completion of RCC work upto Mar 2010 |2) Strict Progress Montoring |the work should be carried as per available design and |
| |upto 19th slab (Subject to obtain CC |3) Fixing Mile Stone to track the |drawings. 2) If Contractor is not performing then the |
| |upto Terrace & Clearance of working |Schedule intermediately |contractor should be penalised or another contractor |
| |drawings well in advance) |4) To get the work done |should be deputed for the work. 3) If the material is |
| | |5) To get the material in time |shortage then we should arrange for the material |
|2 |Civil Finishes :- A) B/W, Plaster & |) Micro Scheduling |1)If VFC drawings are not received in well in advance then|
| |other finishing Items of Typ. Toilet & |2) Strict Progress Montoring |the work should be carried as per available design and |
| |Typ. Lobby (excluding P1 & P6 Lobby) |3) Fixing Mile Stone to track the |drawings. 2) If Contractor is not performing then the |
| |B) Services Co-ordination |Schedule intermediately |contractor should be penalised or another contractor |
| |