Preview

Arena Simulation Report

Satisfactory Essays
Open Document
Open Document
608 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Arena Simulation Report
Assignemnt 2
Problem 3-3
Model 3-1 was has been run for 8 hours (480 minutes) instead of 20 minutes. The plots on queue length and the number of times the drill press is busy or idle for the 8-hour run is given figure 1.
Figure 1 (Simple Processing System with 8 hours of time)

The primary performance related results are compared in table 1.
Table 1: Performance Measures | 20 minutes run | 480 minutes run (8 hours) | Total Production | 5 | 89 | Avg. Wait Time | 2.52 | 3.33 | Avg. System Total Time | 6.43 | 6.86 | Time-Avg. number of parts in queue | 0.78 | 0.62 | Drill press utilization | 0.91 | 0.65 |

Note: For comparison purposes only average and not aggregate figures have been considered (except total production) * Total production as anticipated has increased in the longer run. However the drill press utilization has declined from 91 per cent to 65 per cent which indicates drill press under-utilization in the 8 hour run. * The average wait time has increased by 3/4th of a minute and the average system total time has also jumped by almost same margin. On an average parts arrive every 4 minutes in the 20 minutes case where as they arrive every 5.3 minutes on the 8 hour run. Hence the increase in wait time and total system time is most probably due to larger processing time per part at the drill press.

These results must be considered with caution because the system has been replicated only once. In order to have a meaningful estimate on system performance we have to consider multiple trials.

Problem 3-4

In the model 3-1, the set-up time at the drill press was assumed to be zero. Now consider a constant 3 minutes set-up times at the drill press for every part entering the process. The performance measures are expected to change and can be analyzed from table 2.

Table 2 Performance Measures | Zero set-up time (20 minutes) | Constant set-up time of 3 minutes (20 minutes) | Constant set-up time of 3 minutes (2880

You May Also Find These Documents Helpful

  • Good Essays

    WGU JGT Task #1

    • 1134 Words
    • 5 Pages

    Catherine Pang provided the assembly schedule which denotes cycle time which is the maximum amount of time the boot is allowed to spend at each workstation. Upon initial inspection of the workflow, it is noted that a “bottleneck” is noted due to a variance between stations B and C (with a three minute difference) and stations E and F (with one minute difference). Both variances in sequential steps cause…

    • 1134 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Schonberger Case

    • 757 Words
    • 4 Pages

    The ratio of actual production lead time (or flow time) to work content time from the start of the drill-and-tap to final prep is as follows:…

    • 757 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    M1 Week 3

    • 1315 Words
    • 6 Pages

    In order to find the minimum makespan for the two macines we can apply Johnson’sRule:…

    • 1315 Words
    • 6 Pages
    Satisfactory Essays
  • Satisfactory Essays

    5. Exhibit 6 shows the tool utilization based on demand loading, using the process times from Exhibit 5. If you wanted to add capacity to either N90 or N65, what do you think is the least expensive way to do it? Use the Excel spreadsheet (“LC’s Model”) that is provided to experiment…

    • 2096 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    The simulation provides a baseline of wait times that average 11 minutes. These lie far above the upper tolerance level for this simulation, as well as, for those in Figures 1 and 2 research.…

    • 920 Words
    • 4 Pages
    Good Essays
  • Better Essays

    1) Prepare the manufacturing staff’s calculations for the three alternatives (please refer to the attachments):…

    • 1278 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Shuzworld Analysis

    • 5851 Words
    • 19 Pages

    A. Workflow: Shuzworld produces Rugged Wear Work Boots at its Shanghai production facility using an 8-step process and an assembly line of 8 workstations. Each workstation performs a single task that can range from 3 minutes to 10 minutes to complete, resulting in a total time of 46 minutes to fully assemble one pair of steel-tipped work boots. The facility has a budget to produce 6 work boots an hour, with a 40-hour work week (48 work boots a day). The following table shows the task schedule, along with the time required for each task and predecessor information to complete the 8-step process. The graph shows the current layout of the 8 workstations in the production line:…

    • 5851 Words
    • 19 Pages
    Powerful Essays
  • Good Essays

    Pinto Fires

    • 687 Words
    • 3 Pages

    c. Under normal conditions chassis design, styling, product planning, advance engineering, component testing, and so on were all either completed or nearly completed prior to tooling of the production factories. Because tooling had a fixed time frame of about 18 months; some of these other processes were done more or less concurrently.…

    • 687 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Littlefield Labs Report

    • 548 Words
    • 3 Pages

    1. Step 1 is the bottleneck because it has the largest average queue size compare to step 2, 3 or 4. Even though we purchased 5 machines for Step 1, the utilization rate were around 80% or 90% when demand was high. Although Step 2 and 4 do their jobs in the station, they only take 2.1 hours which is still low compare to 5.3 hours in Step 1.…

    • 548 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    One of the main things that we could improve was getting an average of our results. As we only got one set of results this meant that our results were not very reliable, as we had not repeated the experiment. In our main experiment we had to make sure that we repeated our experiment at least 3 times so that we could calculate the average for the results.…

    • 1097 Words
    • 5 Pages
    Good Essays
  • Good Essays

    Littlefield Case Study

    • 875 Words
    • 4 Pages

    At this point, our team should have reevaluated our decisions, and purchased a new machine for Station 1, in order to get production moving faster to Station 2. As our utilization was remaining at a constant 100%, our lead times were also increasing. With full utilization, we were unable to produce enough product to meet our order demands, further increasing the queues at each station and increasing our lead times (as shown).…

    • 875 Words
    • 4 Pages
    Good Essays
  • Good Essays

    1. Act-consequentialists believe that the moral rightness of an act depends entirely on whether the act’s consequences are at least as good as that of any alternative act.…

    • 441 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Wescott case study

    • 475 Words
    • 11 Pages

    According to the results, Model A has an overtime work of 2.75 hours if the standard working hours 8 hours. Same goes to Model B & C, both model worked for 2.77 if the standard working hours 8 hours. However, the production in Model D & E are overrun to 2.5 and 3 days which is insufficient.…

    • 475 Words
    • 11 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Industry Average

    • 315 Words
    • 2 Pages

    *The above table contains data extracted from RMA Industry Averages and is used with permission.…

    • 315 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Abc Costing System

    • 2288 Words
    • 10 Pages

    5-48 Cycle time efficiency and JIT Walker Brothers Company is considering installing a JIT manufacturing system in the hope that it will improve its overall processing cycle efficiency. Data from the traditional system and estimates for the JIT system are presented here for their Nosun Product:…

    • 2288 Words
    • 10 Pages
    Good Essays

Related Topics