Preview

Blue Spider Project Case Studies

Better Essays
Open Document
Open Document
1776 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Blue Spider Project Case Studies
Report of the lessons learnt in the Blue Spider Project Case studies.
The Blue Spider Project that Gary Anderson managed for Parks Corporation was a good example of an unsuccessful project. There were many aspects that increased project risk and contributed to the problems encountered. Some of those problems could have been prevented or resolved if Gary Anderson applied proper project management methodology.
In any project, one of the most important success factor is the project manager being able to communicate effectively. Gary Anderson failed to communicate effectively both internally and externally. Internally, Gary had been consistently not updating the status of the project or any decision made to other functional managers. For example, when Gary started testing the new material JXB-3, he didn’t notify the testing manager and as a result, work that was no longer required were done which not only increased the cost of the project but also made the testing manger being upset as he needed to play catch-up and reallocate his resource. Gary Anderson repeated the mistake of having poor communication with internal staff when he didn’t notify the production manager of the rescheduling of the verification mix and forced the production of the mix to be performed during overtime which again increased the cost of project and caused the production staff making a mistake in the mix. More importantly Gary failed to maintain a strong external communication with the customer right from the start of the project. In the beginning of the project when Gary was ‘living’ in the research lab, it was basically impossible for the customer to contact Gary if they wanted an update of the project or had any questions. The customer didn’t have a clue of whether Park had started doing any work yet and they would be very concerned as Lord’s contract worth much more. Gary had broken the trust from Lord at the start of the project and as a result, Lord decided to demand more



References: Dyer, R. (1984), ‘Planning and execution of a major R & D project’, International Journal of Project Management, 2(1), Pages 6-9

You May Also Find These Documents Helpful

  • Powerful Essays

    Burke, R. (2006). Project Management - Planning and Control Techniques (5th ed.). www.burkepublsihing.com: Burke Publishing.…

    • 13536 Words
    • 144 Pages
    Powerful Essays
  • Better Essays

    Pontrelli Recycling

    • 1790 Words
    • 8 Pages

    Eichenberger, J. (1998). Project management, part III budgets for projects. AAOHN Journal, 46(5), 268-70. Retrieved from http://search.proquest.com/docview/1013462577?accountid=35812…

    • 1790 Words
    • 8 Pages
    Better Essays
  • Powerful Essays

    David, O. (April 2006). Understanding and solving the causes of project failure. The CBS interactive business network .…

    • 3251 Words
    • 14 Pages
    Powerful Essays
  • Better Essays

    Executive Summary Project management is the science of planning, organizing, executing, and managing the resources needed to achieve a specific goal. Effective project managers (PM) strategically facilitate the entire project management process to ensure the project’s success. To do this the PM must adequately meet the specific requirements (i.e., time, scope, quality, and cost) set forth by the project and its stakeholders. It is theorized that PM must possess a set of core competencies in order to successfully manage a project. Those competencies are development of project management knowledge areas, application of appropriate project management tools and techniques, understanding of the project environment, possession of leadership skills, and general managerial and human relations skills. This paper will critically analyze the performance of a newly appointed project manager, Gary Allison, through his response to various issues that arose during the management of The Orion Shield Project. In my analysis, I will thoroughly discuss the technical, ethical, legal, contractual, and change issues and Gary’s response to each. I will conclude my analysis with a reasoned deduction of what competencies Gary lacks that prohibit him from being an effective project manager.…

    • 1613 Words
    • 7 Pages
    Better Essays
  • Good Essays

    Answer – Given that the project was strategic in nature for the company, the loss of key personnel to other projects is a very big risk that could impact delivery and quality of the project. Also, Jerry and his team had really worked very hard to ensure that they make up the management reserve that will keep them on the project, an action that they for ensuring project success. However, Frank’s action of booking the management reserve as profit would greatly undermine the planning that had been done by Jerry and also was not in the best interests of the project as it poses a key risk of losing talented personnel if the program was closed. Based on this, and given that as a project manager Jerry was responsible for doing everything to ensure project success, and achieving the goals of the project charter, he should tae action if there are any forces that risk or hamper project success. Moreover was Frank wanted to do was not very ethical and correct as he was trying to gain money by misrepresenting facts. Therefore Jerry should go to the General Manager to present his case and ensure that there is action taen to ensure project success.…

    • 1055 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Throughout the Orion Shield project, Gary faced numerous technical, ethical, legal, contractual and other project management issues. Gary’s lack of project management experience was apparent throughout the project and several time he failed understand that the ultimate responsibility has to be with him, the program manager. As Saran Wilson complained, he spent way too much time doing and not enough time managing. The fact that his memo authorized the vice-president and general manager to book 75 percent of $200,000 profit of the program for corporate profit spending for stockholders was an amateur but costly mistake that eventually cost Gary his job.…

    • 1168 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    References: Larson, E., & Gray, C. (2010). Project management, the managerial process. (5th ed., p. 158).…

    • 1575 Words
    • 5 Pages
    Powerful Essays
  • Better Essays

    | The project is estimated to take approximately five months after groundbreaking. The Czopeks are willing to have the project delayed in order to save costs.…

    • 3547 Words
    • 12 Pages
    Better Essays
  • Better Essays

    Senior Management

    • 1685 Words
    • 7 Pages

    6) Lack of project ownership from the senior management team – It was only Frank Carau and Ben Walker, who are juniors that are handling the project. It does not have enough clout to direct and influence the project on the senior management levels. However, with the leadership and sponsorship of Phil Faraci, the project came into a turn-around from being a slow-paced to fast-paced project, from being a…

    • 1685 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    Shenhar, A. J & Dvir, D (2007) Project management research – the challenge and opportunity. Project Management Journal Pg 94 -99…

    • 4544 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    *What Went Worng*??............. The reality is that if project sponsors do not start out with an understanding of project management and its processes, the probability of such things happening are surprisingly high. Miles Faster jumped at the opportunity to get involved and decided to change the production train specification to increase capacity. Because of this, the software program had to be mostly rewritten, severely limiting Leadbetter's time for managing the project. It also resulted in errors requiring increased debugging at startup. Neither Moneysworth nor Leadbetter was conscious of the need for any review and approval procedures for specifications and shop drawings submitted…

    • 495 Words
    • 2 Pages
    Satisfactory Essays
  • Better Essays

    Amex Hungary

    • 1921 Words
    • 8 Pages

    References: Larson, E.W., & Gray, C. F. (2011). Project management: The Managerial Process (5th ed.). New York: McGraw Hill.…

    • 1921 Words
    • 8 Pages
    Better Essays
  • Better Essays

    I certify that the attached paper is my original work. I am familiar with, and acknowledge my responsibilities which are part of, the University Of Phoenix Student Code Of Academic Integrity. I affirm that any section of the paper which has been submitted previously is attributed and cited as such, and that this paper has not been submitted by anyone else. I have identified the sources of all information whether quoted verbatim or paraphrased, all images, and all quotations with citations and reference listings. Along with citations and reference listings, I have used quotation marks to identify quotations of fewer than 40 words and have used block indentation for quotations of 40 or more words. Nothing in this assignment violates copyright, trademark, or other intellectual property laws. I further agree that my name typed on the line below is intended to have, and shall have, the same validity as my handwritten signature.…

    • 1332 Words
    • 6 Pages
    Better Essays
  • Best Essays

    Harold Kerzner (2003) Project Management – A systems approach to planning, scheduling and controlling Wiley & Sons Inc.…

    • 3083 Words
    • 13 Pages
    Best Essays
  • Powerful Essays

    Trophy Project

    • 6347 Words
    • 26 Pages

    Project Management – A systems approach to planning scheduling and controlling, 7th Edition, Harold Kerzner, PhD…

    • 6347 Words
    • 26 Pages
    Powerful Essays

Related Topics