6. You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who desperately needs 1 of your backhoes. You tell Brooker you would be willing to let him have the backhoe if you are still able to complete your project in 11 months.
Develop a resource schedule in the loading chart that follows to see if it is possible to complete the project in 11 months with only 2 backhoes. Be sure to record the order in which you schedule the activities using scheduling heuristics. Activities 5 and 6 require 2 backhoes, while activities 1, 2, 3 and 4 require 1 backhoe. No splitting of activities is possible. Can you say yes to Brooker’s request?
Legend
|ES |ID |EF |
|SL |RES |SL |
|LS |DUR |LF |
RESOURCE
| |
|Schedule the resources load chart with ES and Slack updates |
0 1 2 3 4 5 6 7 8 9 10 11 12 13
ID |RES |DUR |ES |LF |SL | | | | | | | | | | | | | | | | | | | | | | |1 | | | | | | | | | | | |1 |1 |1 |0 |5 |4 | | | | | | | | | | | | | | |2 |1 |2 |0 |3 |1 |1 |1 | | | | | | | | | | | | |3 |1 |3 |0 |3 |0 |1 |1 |1 | | | | | | | | | | | |4 |1 |2 |2 |7 |3 | | | | | | | |1 |1 | | | | | |5 |2 |4 |3 |7 |0 | | | |2 |2 |2 | | | | | | | | |6 |2 |2 |7 |9 |0 | | | | | | | | | |2 |2 | | | |
RESOURCES SCHEDULES |2 |2 |2 |2 |2 |2 |2 |1 |1 |2 |2 | | | |RESOURCES AVAILABLE |2 |2 |2 |2 |2 |2 |2 |2 |2 |2 |2 |2 |2 | |
Yes,