BACKGROUND:
Read the Green Computing Research Project, Part 1 in Appendix C.
Assume the project budget is $500,000 and will take six months to complete and that you must select the project team as soon as possible.
Use project charter examples from Chapters 3 and 4 as support in your answer.
Prepare a project charter for the Green Computing Research Project.
Write a two to three (2-3) page paper in which you include the following:
Project title and date of authorization
Project manager name and contact information
A summary schedule
Project budget summary
Brief description of the project’s objectives
Project success criteria
Summary of planned approach for managing the project
Roles and responsibilities matrix
Use at least two (2) quality resources in this assignment.
Project Title: GREEN COMPUTING RESEARCH PROJECT
Date of Authorization: January 21, 2013
Project Start Date: February 1, 2013 Projected Finish Date: August 1, 2013
Budget Information: The firm has allocated $0.5 million for this project.
Project Manager: , @wearebig.com
Project Objectives: This is a high priority for our company. This is the initial project charter and the objective is to research possible applications of green computing, which include: Data center overall energy efficiency The disposal of electronic waste and recycling Telecommunicating Virtualization of server resources Thin client solutions Use of open source software Development of new software to address green computing for internal use and potential sale to other organizations
Main Project Success Criteria:
Provide a series of extensive research reports, one for each listed above as well as including detailed financial analysis and recommendations on which green computing technologies to implement.
Approach:
Maintain a group of five full time personnel dedicated to this 6-month project. Additional resources
References: Schwalbe, K. (2011). Information technology project management. (6th revised ed.). Boston: Course Technology-Cengage. CengageBrain.com (2012). Downloadable Microsoft Office 2010 Templates for Information Technology Project Management, Revised 6. Retrieved from http://www.wadsworth.com/cgi-wadsworth/course_products_wp.pl?fid=M20b&product_isbn_issn=9781111221751&token= PMI.org (2012). Evaluation and application of a project charter template to improve the project planning process [ABSTRACT]. Retrieved from http://marketplace.pmi.org/Pages/ProductDetail.aspx?GMProduct=00100195800&iss=1 Erwin Z (2012). Benefits of PMBOK. Retrieved from http://benefitof.net/benefits-of-pmbok/