Fauquier Gas Company, is one of the nation’s 440 gas companies, served an area where land use was changing from agricultural to residential and commercial. The company is beginning a new project that consist of having 3 ½ miles of lines ready to be hooked up by September. This is another one of the demands that Fauquier have on their hands not including the additional 10 lines that they plan on starting for next project. It takes great deal of engineers and contractors and constructions workers to meet this deadline, not to include precise planning. Mr. Clive Byers is the construction project manager, Mr. Charlie Buck is the design superintendent, Pat Wilson is design engineer, Sam Law is project engineer, and Mr. Bill Murphy is the manager of supply management. All of these individuals are under management of the vice president of operations for the company. These individuals play a huge role in meeting all requirements and specifications for this project. In order to meet all the deadlines into building this project all parties involved have to communicate effectively. Mr. Murphy is responsible for ensuring all the supplies that goes into ordering is placed and delivered in a timely manner.
Mr. Murphy has ran into a road block, he is unable to retrieve the purchase request for the pipeline. Pat Wilson, the design engineer who is in charge of going through all the specifications has change the diameter of the pipe to 24 inches. Mr. Murphy asked why they change in the wall thickness and length. Wilson informed him that the operation of the line would be governed by less stringent specifications, making the wall thickness ¾ inches and the length would be 57 feet. Pat was considering cost as a role in the project based on her design and that lead to the change in the specifications.
As the specifications is getting sorted out by Pat Wilson, Mr. Murphy was getting concerned about the economic consequences and the schedule impact of the