Preview

Case Study Minnetonka Warehouse

Satisfactory Essays
Open Document
Open Document
445 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Case Study Minnetonka Warehouse
CASE 10-1: MINNETONKA WAREHOUSE

Question 1: For each of the four work team sizes, calculate the expected number of trucks in the queue waiting to be unloaded.

Size of team Number of trucks in queue
2 3.2
3 .5
4 .27
5 .12

Question 2: For each of the four work team sizes, calculate the expected time in the queue—that is, the expected time a truck has to wait in line to be unloaded.

Size of team Expected time in queue
2 .8 hours
3 .125 hours
4 .067 hours
5 .030 hours

Question 3: For each of the four work team sizes, what is the probability that a truck cannot be unloaded immediately?

Size of team Probability that truck must wait upon arrival
2 80%
3 50%
4 40%
5 30%

Question 4: Which of the four work teams has the lowest cost to Wayne?

Size of team Total cost
2 $268.00
3 $102.00
4 $96.00
5 $95.32

Question 5: Wayne is also considering rental of a forklift to use in truck unloading. A team of only two would be needed, but the hourly cost would be $38 per hour ($28 for the workers and $10 for the forklift). They could unload a truck in five minutes. Should Wayne rent the forklift?

A two-person crew and a forklift will cost $38 per hour. Compare this with the answers in question 4; Wayne should adopt a two-man crew and use a forklift.

Question 6: Disregard your answer to question 5. Labor negotiations are coming up and Wayne thinks he can get the union to give way on the work rule that prohibits warehouse workers on the unloading dock from being given other assignments when they are not unloading trucks. How much would Wayne save in unloading dock costs if he could reassign warehouse workers to other tasks when they are not unloading trucks, assuming that he has picked a good team of workers and each worker works 8 hours a day?

From the printouts, we must determine how much “idle time” there is with the present system. This depends in part upon the crew size. For a crew of four, for example, 24 minutes per

You May Also Find These Documents Helpful

  • Good Essays

    Eco 550 Week 4 Paper

    • 565 Words
    • 3 Pages

    For the second approach we decided to assign each job duty to the person that would required the least amount of time for each different job duty, given that preparation was assigned to Tom, since there was no one else that could do the duty for 100 minutes or less and this was the longest job time from the entire process. We also decided to let George manufacture tables on his own and exclude Cathy from the manufacturing process. This approached equated to a total of 270 hours, given than assembly was assigned to Randy( 80), finishing and packaging to Leon(90), and preparation to Tom(100). By utilizing…

    • 565 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Paper cost ( 1,300 copies x .007) 9.10 Other supplies & electricity (1,300 copies x 0.004) 5.20 Total variable cost 14.30 2.) Calculate the total labor cost of these jobs Labor cost ( $ 8 x 4 hrs ) 32.00 3.) Suggest a way to assign labor and indirect costs to the cost of a copy made on that Sunday Direct Labor hours used because it is fixed and can be easily measured. 4.) Determine the full cost of one copy on the last Sunday in June, using the cost method in preceeding question. Paper cost 0.007 Other supplies & electricity Other supplies & electricity 0.004 0.004 Labor Cost (8/ hrx 4 hrs)/1300 copies 0.0246 Monthly operating cost (total cost (($5,000/30 days)/8hrs ) hourly rate ( 20.83/ hr x 4hrs )/1,300 copies 0.064 Total Full Cost per copy 0.0996 5. ) Determine the average annual full cost of one copy No. Of copies made / No. Of copies made 1,300 copies / 4hrs = 325 copies per hour Total no. Of copies made = total direct labor-hours x copies made per hour 7,280 hrs x 325 copies per hour = 2,366,000 copies Variable Cost ( 0.011 x 2,366,000 copies ) Labor cost (.0246 x 2,366,000 copies ) Other monthly cost total cost 5,000 x 12 months Total annual cost 26,026.00 58,203.60 144,000.00…

    • 657 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Spmproject File

    • 667 Words
    • 3 Pages

    5. On average, how long will the trucks have to wait on a busy day? Assume a 7am start of…

    • 667 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Hog Problem

    • 370 Words
    • 2 Pages

    The next recommended step is to turn this data into a specific number of loads, and then assign the loads to trucks, and see how many we would need to complete that particular days required shipping (see appendix- TABLE D).…

    • 370 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Shuzworld Analysis

    • 5851 Words
    • 19 Pages

    A. Workflow: Shuzworld produces Rugged Wear Work Boots at its Shanghai production facility using an 8-step process and an assembly line of 8 workstations. Each workstation performs a single task that can range from 3 minutes to 10 minutes to complete, resulting in a total time of 46 minutes to fully assemble one pair of steel-tipped work boots. The facility has a budget to produce 6 work boots an hour, with a 40-hour work week (48 work boots a day). The following table shows the task schedule, along with the time required for each task and predecessor information to complete the 8-step process. The graph shows the current layout of the 8 workstations in the production line:…

    • 5851 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    BUS 599 Week 1 Quiz

    • 428 Words
    • 2 Pages

    3. The CEO of a transportation company wants to use a large amount of cash for the purchase of additional new trucks and trailers rather than paying bonuses to its employees. The new...…

    • 428 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    14. You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. Which of the following is the correct value for the resulting line's efficiency?…

    • 1392 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Assuming that all activities and paths are independent following is the probability calculation. In addition…

    • 468 Words
    • 8 Pages
    Satisfactory Essays
  • Powerful Essays

    Was the outcome of the Civil War determined by the nature of Northern and Southern societies or by what occurred on the battlefield?…

    • 1655 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Limitations: We suggest that the company pays the additional workers $8 per hour, as they them in the receiving plant and harvesting jobs. We assume that the dryer units need one employee, so the cost for one additional worker would be $32 per…

    • 895 Words
    • 4 Pages
    Satisfactory Essays
  • Satisfactory Essays

    4. On average, how long will the trucks have to wait on a busy day? Assume a 7am start of processing of berries.…

    • 426 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Ncc Case

    • 1281 Words
    • 6 Pages

    4) On average, how long will trucks have to wait on a busy day? Assume at 11a.m. start of processing of berries and a continuous arrival of berries of 1500 bbls/hr?…

    • 1281 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Macroeconomics Study Guide

    • 2232 Words
    • 9 Pages

    Q2) Joe could be at three different jobs that pay $15, $10, and $8 respectively. If he is not working, the opportunity cost is...…

    • 2232 Words
    • 9 Pages
    Good Essays
  • Satisfactory Essays

    Cost Acc

    • 527 Words
    • 3 Pages

    (4) Assign costs to products by multiplying the cost driver rate by the volume of cost driver units consumed by the product.…

    • 527 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Susan’s company has just won an important new contract. She will have to assign a project team of at least 4 of her 11 staff members to this contract in order to complete it on time. If no more than 5 staff members can be spared from other work, how many different project teams could Susan form for the new contract? T-8…

    • 726 Words
    • 4 Pages
    Satisfactory Essays