Preview

Chadwick Construction Case

Powerful Essays
Open Document
Open Document
767 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Chadwick Construction Case
Chadwick Construction Case Analysis
Introduction
Chadwick Construction Company has had a significant increase in demand over recent years and has encountered multiple project management problems during this time. As a result, CCC’s general manager is considering the possibility of hiring a project manager for project scheduling and keeping track of the progress of subcontractors at work sites. CCC management is interested in knowing the expected completion time for a house if a project manager were to be hired. The following analysis will illustrate the need for a project manager and provide a recommendation as to whether one would be beneficial to the company or not.
Analysis
Table 1 shows the most likely, optimistic, pessimistic, and expected activity completion times based on records of the last 40 homes built by each of the subcontractors for CCC. Table 1. Task List for Building a Home
Task Description Predecessor(s) Most optimistic (a) MostLikely (m) Most pessimistic(b) Expected Completion Time
-3683017780
Variance
SD
√σ2
A Excavation - 4 5 6 5 0.111111 0.33
B Concrete A 7 11.5 13 11 1 1
C Sewer & Water A 3.5 5 6.5 5 0.25 0.5
D Rough Plumbing C,E 2.5 5 13.5 6 3.361111 1.83
E Structure B 46 60 68 59 13.44444 3.67
F Roofing & Siding E 14 15.5 20 16 1 1
G Electric E 3.5 5 9.5 5.5 1 1
H Walls & Cabinets D,G 7.5 9.5 11.5 9.5 0.444444 0.67
I Brick Work F 4 7 10 7 1 1
J Outside Finish I 5 6.5 11 7 1 1
K Finish Plumbing H 3.5 5 6.5 5 0.25 0.5
L Inside Finish F,K 5 7.5 13 8 1.777778 1.33
M House Complete A-L 100 107 123.5 111.25 15.34028 3.92
Project Network
Figure 1 illustrates the network of activities for building a house.

Path Analysis
Table 2 shows how long the project will take including the earliest and latest start and finish times and allotted slack times for each activity. Table 3 shows each path of the project in addition to the critical path in which the activities consist of: A) Excavation B) Concrete E)

You May Also Find These Documents Helpful

  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Good Essays

    ACC 497 Final Exam

    • 2281 Words
    • 11 Pages

    15) A simple diagram that shows estimated completion times versus actual completion times for the various activities in a systems implementation project…

    • 2281 Words
    • 11 Pages
    Good Essays
  • Satisfactory Essays

    Managerial Statement: The expected duration of the project is 31 working days. Critical Activities are I, J, K, L, and M.…

    • 678 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Admn232 Assignment 1

    • 993 Words
    • 4 Pages

    The job of project manager, as performed by Ron Barnes of CanDo Construction Ltd., is fundamental in making things happen, as he is responsible for winning and completing projects. To do this successfully, he must gather an accurate assessment of the competition through direct contact, past experience, or second-hand reports. He must also organize available material and human resources, and determine the timeframe necessary to complete all processes of a project.…

    • 993 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    Week 3 Aib Problems

    • 895 Words
    • 4 Pages

    Before starting this homework assignment, please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram, and how to do a forward and backward pass to determine the ES, LS, EF, LF and slack (float). You will also learn how to determine the duration of the project, and the critical path.…

    • 895 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Natural Blends

    • 556 Words
    • 3 Pages

    Project Management Case Assignment - Use Microsoft Project to analyze this case. This is an example of a construction project. The construction for a large corporate building must be started by February 15th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. The details of the project activities are as follows – The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared. The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins. Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 15th, 2010 which is a Monday and that you work five days a week for 8 hours every day. Analyze the following questions based on the estimates of the above activities 1) When do you complete the project?…

    • 556 Words
    • 3 Pages
    Good Essays
  • Good Essays

    References: Last, F. M. (Year Published) Book. City, State: Publisher. Portny, Stanley E. (2008) Project Management: Planning, Scheduling, and Controlling Projects. New Jersey John wWley & Sons No author. (n.d.) Business Dictionary. Retrieved on 01/09/2012. Retrieved from http://www.businessdictionary.com/definition/best-practice.html#ixzz2HuDx20hu No author. (05.10.2012) ITIL. Retrieved on 01/09/2012. Retrieved from http://www.itil-officialsite.com/AboutITIL/WhatisITIL.aspx…

    • 812 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    pinto pm2 tif ch12

    • 5994 Words
    • 82 Pages

    5) A resource loading table is created through identifying the project activities and their resources required to completion and applying this information to the project schedule baseline.…

    • 5994 Words
    • 82 Pages
    Satisfactory Essays
  • Good Essays

    The third and last interview was conducted through a face-to-face in-depth interview with respondent C who is a project manager at CBRE Company in Sacramento, California. He has been living in Sacramento County for more than 20 years with more than 15 years of experience in construction project management. Through the in-depth interview with participant C, he shared his experiences and the factors he perceived as contributing to his project success as follow:…

    • 891 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Orion Shield Project

    • 5525 Words
    • 23 Pages

    Executive Summary The basic concepts of project management calls for proper planning, organization and the management of a variety of resources in order to successfully achieve a certain goal. One of the most important objectives of project management is the ability to deliver a product or service within a certain time constraint or “on time” as well as being fiduciary responsible or “within budget.” Thus, it can be seen that good project management makes efficient use of time, money, personnel, materials and supplies, and methods of communication in order to successfully complete a project. Unfortunately, these basic methods of project management were not…

    • 5525 Words
    • 23 Pages
    Powerful Essays
  • Satisfactory Essays

    A&E Thread size chart

    • 975 Words
    • 4 Pages

    Technical Bulletin A&E THREAD SIZE COMPARISON CHART Thread Construction & A&E Brand Application Perma Core ® Ultimate Ex-Light Weight Shirting & Tailored Clothing Tex Size Old A&E Tkt # Avg. * Avg.*…

    • 975 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Solar Farm

    • 17321 Words
    • 70 Pages

    Sydney & Samuels International Limited FEASIBILITY STUDY FOR SYDNEY & SAMUELS 51MW HYBRID WIND FARM PROJECT, KWANKWASO, MADOBI LGA, KANO STATE A Gideon Goldmann Feasibility Report Gideon Goldmann Feasibility Study on Proposed WTG for Sydney & Samuels by the: Advisory Sydney & Samuels International Limited Table of Contents Section 1: Introduction and Executive Summary 1.0 Report Methodology 1.1 Introduction 1.2 Project Description 1.3 Feasibility of Proposed Project: Key Issues 1.4 Project Financial Feasibility via Renewable Energy Credits 1.5 Rationale for Multiple Wind Turbine Installations 1.6 Wind Turbine Generators (WTGs) in the Global context 1.7 Overview of WTG Economics/Profitability (US & EU Scenario) 1.7.1 Capital Mix and Cost of Capital 1.7.2 Tax Benefit - Production Tax Credit (PTC) 1.7.3 Low Cost Financing Opportunities - REPI and CREBs 1.7.4 Tax Benefit - Accelerated Depreciation 1.7.5 Renewable Energy Credits (REC‟s)…

    • 17321 Words
    • 70 Pages
    Powerful Essays
  • Good Essays

    Great Wall rotary kiln is widely used in the fields of building materials, metallurgy, chemical industry, environmental protection and so on. It can be divided into cement kiln, metallurgy chemical kiln and lime kiln according to the different materials processed. The cement kiln is mainly used calcine cement clinker. In the process of non-ferrous and ferrous metallurgy, such as the iron, aluminum, copper, zinc, stannum, nickel, wolfram, chromium and so on. The rotary kiln can be used to sinter and roast ore, concentrate, intermedium and so on. The lime kiln is mainly used to calcine limestones.…

    • 457 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    Performance Boating Products

    • 3677 Words
    • 15 Pages

    • A brief summary of the three individual projects can be viewed in the table below:…

    • 3677 Words
    • 15 Pages
    Powerful Essays
  • Good Essays

    Emaan

    • 1992 Words
    • 8 Pages

    Rockwool RockShield external wall insulation offers triple value - outstanding thermal and weather protection plus…

    • 1992 Words
    • 8 Pages
    Good Essays