1 when the cone crusher ore must be assigned to work in the middle of the disk , in order to prevent crusher overload, make liner wear unevenly ; allow direct ore into the ore crushing cavity proper conditions are: ore distribution plate . uniformly dispersed in the crushing cavity , can not give into the higher levels of ore rolling acetabular wall.
2 The maximum size of the ore crusher ≤ 85% to the mine mouth size , otherwise it will lead to lower production crusher , cone crusher damage certain components.
3 Do not load starting crusher to avoid accidents.
4 When parking , you must first stop feeder and let the ore has been crushed into the crushing chamber after discharge , so that the crusher parking.
Work pressure and hydraulic station 5 . Crusher work should always check the locking system , identify problems and timely treatment .
6 Replace the rolling acetabular wall , rolling acetabular wall has a U-shaped spiral rock breaking machine manufacturer nail on the adjustment ring , injected between zinc alloy, making it closely, when a new installation or replacement of rolling acetabular wall , in after 6-8 hours , you should check its fastening and tighten the U -shaped bolt again.
7 replace cone crusher wall , cone crusher crushing cone wall is fixed to the body with a conical head , between two zinc alloy casting , after a new installation or a new replacement cone crusher wall 6-8 hours should check the fastening , found loose to tighten immediately.
8 gears , the circular plate wear due to friction , the cement production process changes affecting the gap between the gears, in order to ensure the normal gear must be supplemented in the bottom cover gasket, the gasket should be equal to the thickness of the circular plate wear amount .
9 bearings and seals, bearings when installing bowl , taking care not to damage the wire rope slinger ( material support between the rope with hardwood , etc. ) . When