Preview

Critical Path

Satisfactory Essays
Open Document
Open Document
1605 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Critical Path
Critical Path Procedure 1. Develop a list of the activities that make up the project. 2. Determine the immediate predecessor(s) for each activity in the project. 3. Estimate the completion time for each activity. For example:

Activity Immediate Predecessor Time A - 3 B - 1 C - 2 D A, B, C 4 E C, D 5 F A 3 G D, F 6 H E 4

4. Draw a project network with nodes and arcs depicting the activities and immediate predecessors listed in steps 1 and 2. Please see problem 4, 7, and 8 below for an example of a network with arcs. 5. Prepare the outline of the activity schedule with column and row titles as shown below. 6. Use the project network and the activity times to determine the earliest start and then the earliest finish time for each activity by making a forward pass through the network. 7. The earliest start time for the first activity(s) in a network is zero (0). The earliest finish time for the first activity(s) in a network is the activity time for that activity. 8. The earliest start time for an activity with one predecessor is the earliest finish time for the predecessor. The earliest finish time for this activity is the earliest start time plus the activity time for the activity. 9. The earliest start time for an activity with two or more predecessors is the maximum of the earliest finish times for all of the predecessors for that activity. 10. The earliest finish time for the last activity in the project identifies the project completion time.

Activity Schedule | Activity | Earliest | Earliest | Latest | Latest | | Critical | Activity | Time | Start | Finish | Finish | Start | Slack | Path | A | 4 | 0 | 4 | 4 | 0 | 0 | X | B | 6 | 0 | 6 | 7 | 1 | 1 | | C | 2 | 4 | 6 | 7 | 5 |

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    Create a project schedule using Microsoft Project. Project schedule will built from and contain the following information:…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    6. (TCO C) The _____ time is the latest time by which a particular activity must be finished in order for the entire project to be completed by its required completion time.…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Powerful Essays

    Proj586 Project

    • 2037 Words
    • 9 Pages

    While meeting with your project team, you have worked with them to determine the appropriate sequencing of the activities, and the duration for each activity. The data that you compiled is shown below. Using MS Project, follow the Project Schedule Instructions provided below to build a project schedule for the Huntsville Project by entering the information from the below task list with duration and predecessors.…

    • 2037 Words
    • 9 Pages
    Powerful Essays
  • Satisfactory Essays

    Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (5 points) b) What is the Critical Path of the Project? (5 points) c) What is the ES for Activity D? (1 points) d) What is the LS for Activity G?…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Date constraints –> Date constraints establishes time milestones or benchmarks on a project that the entire construction team works toward…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    LF – EF or LST – EST Activities on the critical path have zero slack/float. b. What is the Scheduled Completion of the Project? 22 Days c. What is the Critical Path of the Project?…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    TPV1 Sample Questions

    • 453 Words
    • 3 Pages

    D. Milestones are indicators that any of the project major events have already taken place…

    • 453 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Operation Management Case

    • 435 Words
    • 2 Pages

    1. The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:…

    • 435 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Supporting Activity

    • 653 Words
    • 3 Pages

    Start-to-Start: this represents a true relationship between two activities and has nothing to do with their predecessors. If I happen to have two tasks that start at the same time because of a predecessor, that is better represented as two finish-to-start relationships (e.g. systems testing & developing documentation can both begin once development is complete, but there is no relationship between systems testing & developing documentation so we wouldn’t want to use a Start-to-Start dependency here). This dependency is often used with a lag to represent the connection between two activities that run in parallel but cannot start at exactly the same time (e.g. apply the first coat of paint & apply the second coat of paint). A true Start-to-Start example is a race between two runners where each runner is represented as a separate activity – while they will likely finish at different times, both must start at exactly the same time.…

    • 653 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Decision Analysis Task

    • 3292 Words
    • 14 Pages

    In this section of the task, as the operations consultant of Shuzworld, I present my recommendations in detail on how to improve current workflow in the plant of Schuzworld’s Shanghai production facility.…

    • 3292 Words
    • 14 Pages
    Good Essays
  • Satisfactory Essays

    Kristen’s Cookie Company Case Study and Analysis Forecasting and Operations Management Saint Mary’s College of California Executive MBA Program Jessica Marie – www.jessicamariemba.com Kristen’s Cookie Company Agenda Introduction and Preliminary Modeling Key Questions and Problems for Further Thought Recommendations for Improvement Q & A Session and Discussion Kristen’s Cookie Company Introduction Kristen’s Cookie Company Mission Statement: Born from a hunger to feed the student body and the craving brain… This presentation will evaluate the preliminary design for the Company’s production process to make policy and pricing decisions, equipment needed, how many orders can be accepted, and whether the business can be profitable. Kristen’s Cookie Company The Service Triangle…

    • 500 Words
    • 2 Pages
    Satisfactory Essays