Critical Path Method and Pert
Imus Institute
College Department

Case Problem 9.1

The Bloodless Coup Concert

Nheslyn E. Yupo
Mr. Eulogio T. Catalan
September 22, 2014

Most students enjoy watching live performance such as concert specifically musical events. Just like the Programs and Arts Committee of the student Government Association, they really want the band so they will do anything to get the Bloodless Coup.
To solve this problem, they need to accomplish all of these in 18 days or shorter. Using PERT or Project Evaluation and Review Technique method, we are required to show the solution regarding this case.
Program evaluation and review technique (PERT) is a technique adopted by organizations to analyze and represent the activity in a project, and to illustrate the flow of events in a project. PERT is a method to evaluate and estimate the time required to complete a task within deadlines.

PERT serves as an management tool to analyze, define and integrate events. PERT also illustrates the activities and interdependencies in a project. The main goal of PERT is to reduce the cost and time needed to complete a project.
ERT was developed in 1950 by the U.S. Navy during the Cold War and is intended for large projects, which are:
Complex
Require a series of sequential tasks
Performed in parallel with other projects
PERT planning usually involves the following steps:
1. Identifying Tasks and Milestones: Every project involves a series of required tasks. These tasks are listed in a table allowing additional information on sequence and timing to be added later.
2. Placing the Tasks in a Proper Sequence: The tasks are analyzed and placed in a sequence to get the desired results.
3. Network Diagramming: A network diagram is drawn using the activity sequence data showing the sequence of serial and parallel activities.
4. Time Estimating: This is the time required to carry out each activity, in three parts:
1.

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Step 1: Construct a network diagram for the project. (NOTE: EF for activity H should be 19)…

    • 552 Words
    • 5 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    9. (TCO C) In addition to showing the technical constraints among activities, how does the network diagram logic also take into account resource constraints?…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project?…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The scope of the project will need an outline so the work which needs to be performed is available. Prioritizing, budgets and timelines are in this phase as well.…

    • 447 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 5 Days --- B 8 Days --- C 6 Days A D 4 Days C, B E 5 Days A F 4 Days D, E, G G 4 Days B, C H 3 Day G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Best Essays

    Is3350 Unit 1 Assignment

    • 3307 Words
    • 14 Pages

    In order to calculate the timing of an activity ‘Duration’ of the activity needs to be summed up with the ‘Earliest Finish…

    • 3307 Words
    • 14 Pages
    Best Essays
  • Satisfactory Essays

    TPV1 Sample Questions

    • 453 Words
    • 3 Pages

    Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies?…

    • 453 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    PERT Analysis (CPA) - Helps to plan all tasks that must be completed as part of a project, including scheduling and resource…

    • 4317 Words
    • 18 Pages
    Powerful Essays
  • Satisfactory Essays

    Work Package

    • 351 Words
    • 2 Pages

    By identifying the details, we should try to take the details that build up the structure and work for the project. It should be a blueprint for the project manager to identify the activities clearly. So we should just keep the main steps on the list and try to avoid the unnecessary activities.…

    • 351 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    9. (TCO C) Why are activities drawn in a serial relationship on a network diagram?…

    • 814 Words
    • 4 Pages
    Good Essays
  • Good Essays

    The last couple of years I have had the task making sure my children are dressed and on time for school. This task is a process performed weekdays during the school year. This task can be time-consuming if the appropriate processes are not performed. Using a flowchart design, I will be able to analyze daily task of making sure my children are dressed and on time for school. By creating a flowchart for this process, it will increase the awareness and reveal issues that can improve the time spent performing the task. This analysis will reveal what needs to be overcome or changed to improve the performance of the task. According to Wiesenfelder (2009) “A standard activity flowchart will provide information about potential bottlenecks, delays, and other common sources of inefficiency and error” (para. 5). This flowchart design will help make this process more efficient where time can be saved.…

    • 558 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    The following table presents the requirements that the project’s product, service or result must meet in order for the project objectives to be satisfied. See Table 1.…

    • 656 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Program Evaluation and Review Technique (PERT) Scheduling with Resource Constraints Using Qualitative Simulation Graphs (QSG)…

    • 775 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Human Performance Technology

    • 2822 Words
    • 12 Pages

    HPT stresses a rigorous analysis of the requirements of organization, process and human performance for new design and/or identifying the causes for performance gaps, and attempts to provide new designs and/or solutions to improve and sustain performance, and finally - to evaluate the results against the requirements.…

    • 2822 Words
    • 12 Pages
    Powerful Essays
  • Good Essays

    The information that provided in part 1 alone is not enough to allow the project team in defining any milestones of the project. Actually the hierarchical breakdown of the activity can be designed out of this information but for defining milestones; the project team may well require the following:…

    • 576 Words
    • 3 Pages
    Good Essays