Denver International Airport Failure
|Program and Project Management |

[pic]

Table of Contents
Overview of the project 2 Specifications: 2 Chronology of Events 3
Stake Holder Analysis 4 Indentifying Stakeholders 4 Power/Grid Analysis 5 Effect of Stakeholders on the Project 6
Analysis for the outcome of the project 7 Key Factors of Failure 8 Change in strategy 8 The decision to proceed 9 Physical building structure design 9 Late decision to search for a different path 10 Scope, schedule and Budget commitments 10 Other Failure Points 10 Bad Risk Management 11 Leadership Change 11 Architectural and Design Issues 11
Conclusion 11
References 14

Overview of the project

Denver automated baggage system aimed at developing the world’s largest automated airport baggage system due to requirement of bigger airport capacity in land area of 140 Km2, it was supposed to be the largest airport to handle the capacity of over 50m passengers on annual basis. The initial budget at the start of the project was $ 5 billion which includes $685 million from the federal government and over $ 400 from the airlines themselves. The below are the technical specifications of the project.

Specifications:

1. 88 airport gates in 3 concourses 2. 17 miles of track and 5 miles of conveyor belts 3. 3,100 standard carts + 450 oversized carts 4. 14 million feet of wiring 5. Network of more than 100 PC’s to control flow of carts 6. 5,000 electric motors 7. 2,700 photo cells, 400 radio receivers and 59 laser arrays

We can see from the specifications it was a massive project in terms of scale of construction involved and also the cost, with automation involved in every stages of the system it was set up for the world’s best, largest and efficient automated baggage system. As per the Project management triangle one of the main parts of the project management



References: 1. De Neufville, R. (1995) “Designing Airport Passenger Buildings for the 21st. Century,"Transport Journal, UK Institution of Civil Engineers, in press. 2. Calleam. (2008). Denver Airport Baggage System Case Study. Retrieved July 2, 2012, from Calleam Consulting: http://calleam.com/WTPF/?page_id=2086 3 4. PMI. (2004). A Guide To The Project Management Body Of Knowledge . PMBOK Guide , 24-27. 7. Mar 6, 1996, New York Times, < http://www.nytimes.com/1996/03/06/us/denver-airport-nestles-into-its-lair.html?pagewanted=all&src=pm>, Denver Airport Nestles Into Its Lair, [Accesses at 1 June 2012] 8 9. Johnson, Kirk (2005-08-27), < http://www.nytimes.com/2005/08/26/world/americas/26iht-denver.html?_r=1 >, Denver airport to mangle last bag. New York Times, via International Herald Tribune.[Accessed at 21 June 2012] -----------------------

You May Also Find These Documents Helpful

  • Powerful Essays

    References: Project Management Institute. (2008). A guide to the project management body of knowledge: PMBOK guide (4th ed.). Newton Square, PA: Author. ISBN: 9781933890517.…

    • 13779 Words
    • 56 Pages
    Powerful Essays
  • Powerful Essays

    On November 12, 1995, an American Airlines McDonnell Douglas MD-83 type passenger aircraft, which was operating as Flight 1572, departed from Chicago O’Hare International (ORD); however, the aircraft got substantially damaged due to impact to the top of oak trees on Peak Mountain Ridge in East Granby, Connecticut. The aircraft also hit the Instrument Landing System (ILS) localizer antenna, which was on its way to Runway 15 of Bradley International Airport (BDL). The aircraft, lastly, crashed while on approach to Runway 15 of BDL at 00:55 Eastern Time. Fortunately, there were no fatalities and all 73 passengers and crew of 5 survived the impact.…

    • 2974 Words
    • 12 Pages
    Powerful Essays
  • Powerful Essays

    Back Yard Deck Project

    • 8397 Words
    • 34 Pages

    Project Management Institute. (2008). A guide to the project management body of knowledge (PMBOK guide) (4th ed.). Newtown Square, PA: Project Management Institute, Inc.…

    • 8397 Words
    • 34 Pages
    Powerful Essays
  • Better Essays

    It301 Unit 5

    • 1300 Words
    • 6 Pages

    Project Management Institute. A Guide to the Project Management Body of Knowledge(PMBOK-Guide)– Fourth Edition (2008).…

    • 1300 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Assessment Task 1 2

    • 2844 Words
    • 13 Pages

    -To be the major retailer in our sector across the city and state in three years.…

    • 2844 Words
    • 13 Pages
    Powerful Essays
  • Good Essays

    In November 1989, ground was broken on the construction of the Denver International Airport (DIA). A typical master plan approach was taken by the City of Denver during the initial conception of the DIA project, and eventually a consulting team was awarded a contract to help due to their expertise in the fields of transportation and construction. A final master plan was created and presented to the City of Denver that called for the construction of the world’s most efficient airport. The new airport was to be built from the ground up with no limitations. The plan was to allow for growth and expansion without compromising efficiency. The high costs associated in building this new airport were understated…

    • 1695 Words
    • 7 Pages
    Good Essays
  • Better Essays

    Southwest Culture

    • 1122 Words
    • 5 Pages

    Kurtz, David L. (2012) Southwest Airlines: “We Love Your Bags”. Contemporary Business 14th Edition (pp. 78) New Jersey: John Wiley and Sons.…

    • 1122 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Denver International Airport was experiencing such a rapid growth that Denver’s Regional Council of Governments concluded that Stapleton would not be able to handle the necessary traffic expected by the end of the year 2000. Modernization of Stapleton could have extended the inevitable problem to 2005, but were the headaches with Stapleton better cured through modernization or by building a new airport? There was no question that insufficient airport capacity would cause Denver to lose valuable business. Being 500 miles from other major cities placed enormous pressure upon the need for air travel in and out of Denver.…

    • 837 Words
    • 4 Pages
    Good Essays
  • Satisfactory Essays

    With the ongoing list of tasks that are provided with the operations of an airport as listed in the Case 1 Studies, being able to deliver the efficient outcome of all of these resources is beyond the skills of any person, and unfortunately, to leave to a human manager leaves more room for human error. One could not successfully be obligated to do all of the following without sufficient flaws: Gates…

    • 312 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Smith, Carol. "Rising, Erratic Air Fares Make company Policy Vital." Los Angeles Times 2 Nov. 1999: D4.…

    • 4702 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    Faa Airport Palnning

    • 39253 Words
    • 158 Pages

    1. Introduction.. ........................................................................................................................................... 2. Airport Master Plans .............................................................................................................................. 3. Factors Influencing Terminal Configuration and Size.. ...................................................................... 4. Terminal Siting Considerations ............................................................................................................. 5. Project Coordination .............................................................................................................................. 6.-19. Reserved…

    • 39253 Words
    • 158 Pages
    Powerful Essays
  • Powerful Essays

    Schipol Case Study

    • 911 Words
    • 4 Pages

    a 2009 lATACATSsurvey. Moreover, mishandled baggage is a $2.5 billion problem for industry every year.…

    • 911 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    14 Gug Sastry At Rgi 1

    • 1972 Words
    • 27 Pages

    12/03/2014 Sustainability Initiatives – A case study of RGI Airport, Hyderabad 1 GMR Hyderabad International Airport Ltd. • GMR Hyderabad International Airport Ltd (GHIAL) is a Public Private Partnership (PPP) Enterprise for building and operating Rajiv Gandhi International Airport, Hyderabad. • Total area of land : hectares •…

    • 1972 Words
    • 27 Pages
    Good Essays
  • Satisfactory Essays

    |baggage |baggages |If you need help with your baggage we have a cart you can use.|…

    • 905 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    Financial planning

    • 7872 Words
    • 32 Pages

    Forsyth, P., Gillen, D., Muller, J. and Niemeier, Hans-Martin. (2010). Airport Competition- The European Cometition. Surrey: Ashgate ublishing Limited.…

    • 7872 Words
    • 32 Pages
    Good Essays

Related Topics