Preview

Donner Case

Good Essays
Open Document
Open Document
973 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Donner Case
Order Size for drilling: * The Manual press needs 15 min for set up, in addition to 0.08 min for every hole. Knowing that the typical circuit board has 500 drilled holes, then run time will be 0.08*500 = 40 min / board. Therefore, time taken to drill N boards manually will be equal to : 15 + 40(N) * On the other hand the CNC drill needs 240 min for set up, in addition to 0.004 min for every hole. So run time will be 0.004*500 = 2 min / board. Then the time taken to drill N boards by CNC drill will be equivalent to : 240 + 2(N) * It is then logic to conclude that we will use CNC drill only in order sizes that will provide timing benefit over manual press. i.e. when 240 + 2N < 15 + 40N which means N 6 * However the shop floor policy dictates that only orders for more than 100 boards be drilled by CNC drill !!!!! Surely this must be changed * This means that they used the CNC drill in only 12 orders of the 60 orders received in September, while actually they should have used it in 35 orders ( all orders 6) !!
Order Size for Profiling: * Set up time for Punch press is 50 min, while run time is 1 min / board. So Time taken to profile N orders will be 50 + N * While set up time for CNC routers reaches 150 min, in addition to 0.5 min / board run time. So the time needed to complete profiling of N boards equals 150 + 0.5(N) * Thus CNC reuters will produce time benefit if used only in orders more than 200 boards
Capacity of Dry Film Photo Resist area: * Assuming order size equals 8 boards
Then the panel preparation will take 5 + 0.2 = 5.2 min
Lamination & Exposure will take 20 + 2 = 22 min
Development will take 20 + 0.2 = 20.2 min * This means that Lamination and exposure are the bottle neck of the process, and the cycle time for this step will be 22 min / panel. Which means that the capacity will be 2.7 panels / hour * If we increased order size to 2 panels (16 boards)
Panel preparation will take 5 + 0.4 =

You May Also Find These Documents Helpful

  • Good Essays

    Schonberger Case

    • 757 Words
    • 4 Pages

    The flow-time data is described at "as short as about five days for a few lots, but we are quoting six weeks to markings." A rough average was achieved "by putting pieces of colored tape on a few molded bases from several lots over the space of three weeks. The average flow time, found by noting how long it took for the taped units to get to final prep, was seven weeks. One week of that was the flow time from the start of the drill-and-tap to assembly.…

    • 757 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Pm3110 Unit 4

    • 854 Words
    • 4 Pages

    It takes 5 + 100*0.2 + 10 + 100*0.1 = 45 minutes to make 100 products.…

    • 854 Words
    • 4 Pages
    Good Essays
  • Better Essays

    Hilcrest Auto Case

    • 973 Words
    • 3 Pages

    machine takes 0.06 seconds per tube (60 seconds per 1000 tubes). Each of these processes runs…

    • 973 Words
    • 3 Pages
    Better Essays
  • Powerful Essays

    Shuzworld Analysis

    • 5851 Words
    • 19 Pages

    A. Workflow: Shuzworld produces Rugged Wear Work Boots at its Shanghai production facility using an 8-step process and an assembly line of 8 workstations. Each workstation performs a single task that can range from 3 minutes to 10 minutes to complete, resulting in a total time of 46 minutes to fully assemble one pair of steel-tipped work boots. The facility has a budget to produce 6 work boots an hour, with a 40-hour work week (48 work boots a day). The following table shows the task schedule, along with the time required for each task and predecessor information to complete the 8-step process. The graph shows the current layout of the 8 workstations in the production line:…

    • 5851 Words
    • 19 Pages
    Powerful Essays
  • Better Essays

    Decision Analysis Task 1

    • 1008 Words
    • 5 Pages

    The total task time for the work boot assembly is 46 minutes. The actual number of work stations is currently 8 and the largest cycle time is 10 minutes. Based on these numbers the assembly line is operating at 57.5% efficiency. To determine how to better improve the assembly line efficiency, it is important to first determine the minimum of work stations needed. This can be done by using the following formula:…

    • 1008 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Beck Manufacturing

    • 303 Words
    • 2 Pages

    Since the boring department seems to be the bottleneck, capacity should be increased by an additional piece per minute. Currently there is a slack in the milling department of 1, in the grinding department of 2, 0 in the boring department and 1.5 in the drilling department, an increase of 1 would cut back on the slack in each department.…

    • 303 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Space Age Furniture

    • 1300 Words
    • 6 Pages

    Both of the jobs are requiring one thousand furniture pieces. SAF has the capabilities to produce the units that are being requested from both companies with the current production facility. However, the machine requires the operation of a special lathe by a skilled worker. The lathe is basically a machine tool that rotates the product on its axis to perform different operations such as cutting, sanding, knurling, drilling, or deformation, facing, turning, with tools that are put onto the work piece to facilitate an object with balance. This lathe is used to create a specific piece that will complete a part for the…

    • 1300 Words
    • 6 Pages
    Good Essays
  • Satisfactory Essays

    Earthbuddy Case Study

    • 554 Words
    • 3 Pages

    1. Anton Rabie and Ronnen Harary created a product that allowed customers to express their own creativity through styling grass hair that sprouted from a small humanlike head. They called this product Earth Buddy and the popularity soon spread like wildfire. Product sales started through Toronto-area flower shops and gift stores but as demand increased they were able to start distributing Earth Buddy at K-Mart, Toys R Us, Wal-Mart and stores alike. However, the production of Earth Buddies were time consuming and very dependent on the weather. The production process had a total of seven steps. The first step was filling which included six machines that filled the basic round heads with nylon stocking, sawdust and grass seed. The next step operators shaped the product’s eye-glasses. The rest of the process included moulding the face, placing the glasses on the nose, and gluing the buddies eyes in. Next the buddies were sent to the painter who finished off the buddy with a fabric paint mouth. The last step was to place the product on shelving to dry. In the right conditions, this step took about five hours, however, if humidity levels were higher, drying time increased to seven hours.…

    • 554 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Kristen S Cookie Case

    • 537 Words
    • 3 Pages

    bottleneck operation is baking the cookies in the oven, which can process 60min/(1+9) min = 6…

    • 537 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Bayonne Case

    • 3035 Words
    • 13 Pages

    First of all we started to answer the guideline questions. We computed the current capacity utilization in the work centres, and then we found the capacity in pieces of the die-cut work centres, in the different ganging choices (no gangins, ganging pairs of orders or ganging all of the orders). After this we had to focus on the differences between partialed and non-partialed orders of the Royal/Queen work centres so we could analyze the changes in capacity. Concerning the Fold&Glue department, Bayonne Inc. can choose between Royal/Queen and Staude machines, we computed the optimum batch quantity, according to orders’ volume. To conclude about the efficiency of some work centres we…

    • 3035 Words
    • 13 Pages
    Powerful Essays
  • Good Essays

    Donner Compnay Case

    • 1288 Words
    • 6 Pages

    Thus, for the board size greater than 200, using CNC Router would have less production time than punch press.…

    • 1288 Words
    • 6 Pages
    Good Essays
  • Good Essays

    Ergogenic Aids

    • 1296 Words
    • 6 Pages

    John saw an ad for tomato soup at 24¢ per can. At the price 1.…

    • 1296 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    Donner Company Case

    • 1308 Words
    • 6 Pages

    The Donner Company is a manufacturer of printed circuit boards. They need to address several issues in their supply chain operations to improve their service level because net income in the month of September has drastically decreased. Before September, growth was steadily increasing every month. They found that the major problems include unpredictable bottlenecks in manufacturing, lower than expected productivity and lower than expected quality and delivery. After addressing these major issues, I find that investing in more CNC’s and phasing manual drilling out of the manufacturing process can go a long way to improve the service level of the company.…

    • 1308 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    The Big O Company

    • 839 Words
    • 4 Pages

    Executive Summary. The Big “O” Company is undergoing some change since founder and president passed away. The company produced hydraulic cylinders, and has decided to cease all foundry operations and source this operation. The company has gone out to find a supplier whom can take care of the order to the correct specifications needed. A supplier from Indiana, Barry Foundry, has been selected due to low cost and good reputation. After the supplier was able to show that they could make 100 units to spec, Big “O” kicked hem off to do a full order of 4,000 units. There were problems that occurred with some of the castings, and Big “O” needed to change their specifications of the current casting. When Big “O” approached Barry, they understand that the entire order of 4,000 castings has already been made.…

    • 839 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Case Study

    • 530 Words
    • 3 Pages

    The Big “O” Company manufactures large hydraulic units. One of the most difficult items to manufacture is the hydraulic cylinder. The cylinder housing is fabricated from a malleable iron casting. The housing is machined to close tolerances, and the slightest discrepancy in either material or machining means a total loss. Machine cycle time on a typical housing is approximately sixteen hours. For several years, castings had been purchased from the Macon Foundries in Georgia. Macon had been a Big “O” supplier for many years, and during that time it produced thousands of castings at acceptable quality levels. Eight months ago, however, when its founder and president, George Chapel, died, Macon announced that it was discontinuing foundry operations. The supply department at Big “O” undertook a search for new sources. At first, few suppliers could be found who were either capable or willing to meet the exacting specifications and tolerances required. Ultimately, however, three foundries were selected and invited to submit bids on 4,000 castings. The low bidder, at $76.17 a unit, was the Barry Foundry of Muncie, Indiana. Barry was a small concern with a good reputation for doing quality work and fulfilling every delivery promise. Barry was given a purchase order for the full 4,000 units, with the stipulation that Big “O” approve the first 100 units. Within two weeks the first 100 castings were received. They were subjected to initial inspection and then dispatched to the floor for machining. In the words of the shop foreman, “They machined like butter.” Barry was told to proceed with the entire order and a four-month delivery schedule. It was about this time that problems began to develop in the shop. Some hard castings had damaged both grinding wheels and cutting tools. Also, cracks from casting porosity appeared on newly machined surfaces and slots. Although these conditions were not present in all castings, they occurred in a sufficient number to…

    • 530 Words
    • 3 Pages
    Good Essays