Preview

Earned Value Analysis for Chapter 7 Kathy Schwalbe 10 Edition

Satisfactory Essays
Open Document
Open Document
368 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Earned Value Analysis for Chapter 7 Kathy Schwalbe 10 Edition
Running Case
Wellness Intranet Project
Chapter 7 Project Cost Management
Case Task 3: Assume you have completed the three months project. The BAC was $200,000 for this six-month project. Also assume the following:
PV = $ 120,000
EV = $ 100,000
AC = $ 90,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and Schedule performance index (SPI) for the project?
Answer a:
Cost variance (CV) = Earned Value (EV) – Actual Cost (AC)
CV = $100,000 - $ 90,000 = $ 10,000
CV = $10,000

Schedule variance (SC) = Earned Value (EV) – Planned Value (PV)
SC = $100,000 - $120,000
SC = - $20,000
Cost performance index (CPI) = EV – Actual cost (AC)
CPI = $100,000 - $90,000
CPI = 1.11
Schedule performance index (SPI) = EV % PV
SPI = 100,000 % 120,000
SPI = 0.83

b: How is the project doing? Is it ahead of schedule or behind the schedule? Is it under budget or over budget?
Answer b: As the cost variance (CV) is a positive number $10,000 therefore it is under budget and it means that performing the work cost less than planned.
Schedule variance (SV) is is a negative number – $ 200,000 it means that it took longer time than planned to perform work. So the project is behind the schedule.
The project is behind schedule and the budget is costing less than planned till this stage of the project.

c: Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
Answer c: The Budge at completion (BAC) was = $200,000
Estimate to complete (ETC) = (BAC – EV) / CPI
= (200,000 – 100,000) / 1.11
= $ 90,090
EAC = AC + ETC
= 90,000 + 90, 90
= $180,090
As the EAC under budget at $19,910, the project will be completed under the budget.

d: Use the schedule performance index (SPI) to estimate how long it will take to finish this project?
Answer d: Estimated time to complete = Original time estimate / SPI
= 6 months / 0.83 (SPI)
= 7.2 months
It will take 7.2 months

You May Also Find These Documents Helpful

  • Powerful Essays

    PROJ 592

    • 2367 Words
    • 10 Pages

    If the current schedule is maintained, the project will be completed on 12/29/08 and the total cost is$4,644,920.00. Compare to initial budgeted cost the new cost is over budget by 195,000.00. Actual cost so far is $1265, 990.00 and the remaining cost is $3,378,930.00.…

    • 2367 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Nt1330 Unit 4

    • 4542 Words
    • 19 Pages

    The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project.…

    • 4542 Words
    • 19 Pages
    Good Essays
  • Satisfactory Essays

    This means that every machine hour costs the business $2.70. Therefore, during a year that incurs 132,600 hours, we can say that budgeted costs are $358,020, which is a favorable variance from actual costs of $363,036. Remember, when expenses are lower than expected it is favorable, but if revenues are lower than expected it is unfavorable. Many professors often ask you to explain this in your response.…

    • 391 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Nt1310 Unit 4

    • 555 Words
    • 3 Pages

    a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?…

    • 555 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Costing wk4TeamB

    • 1051 Words
    • 6 Pages

    Cost estimates are the one that could have a high risk over the project and it is the one…

    • 1051 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Powerful Essays

    Mcbride Financial Services

    • 4240 Words
    • 17 Pages

    References: APEGBC, (2009). Project Cost Control Basics. Retrieved July 22, 2010 from APGE website at…

    • 4240 Words
    • 17 Pages
    Powerful Essays
  • Good Essays

    Competition Bikes Task 2

    • 1502 Words
    • 7 Pages

    Fourth, the unfavorable revenue and spending variances and unfavorable price variances for manufacturing overhead. The unfavorable variance of $26,426 for revenue and spending and the $24,000 unfavorable price variance was due to the company spending more than the expected amount for the actual amount of output. These are area management should be made aware of so they can pinpoint areas that need…

    • 1502 Words
    • 7 Pages
    Good Essays
  • Good Essays

    Upon reviewing the Arcadia Hospital Income Statement for the year of 2005, I would say that the variance is negative because the actual budget for 2005 $568 million minus the budget of $596 million equals a negative amount of $28 million under budget, which means less revenue. In other word, revenues were $28 million below budget, therefore the variance is negative.…

    • 317 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    2. (TCO F) Process costing would be appropriate for each of the following except: (Points : 5)…

    • 798 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    Whatever the type of project, there are three important elements of cost, schedule and performance project managers must achieve in order to attain a successful project outcome. These elements are interrelated which means a slight change of one of the elements such as prolonging the project time schedule highly affect the element of cost or more…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Communication affects relationships within the setting in a variety of ways. The positive affects are you will have a better relationship with the children as this will help with their learning and development because they will be talking to you about what they like/dislike and their interests. They will feel at ease with you and more trusting and may be more likely to confide in you. They will feel happier and important.…

    • 269 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Satelite Problem

    • 506 Words
    • 3 Pages

    C. Midway through the project your design and production people realize that a 75% improvement curve is more appropriate. What impact does this have on the project?…

    • 506 Words
    • 3 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    1. What is the estimated project completion date? (Assume there are no holidays and ignore the sunk cost of the planning team’s effort)…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    1. When is the project estimated to be completed? How long will the project take?…

    • 576 Words
    • 3 Pages
    Good Essays

Related Topics