1) Task 1
1.1 Project Network Diagram
1.2 Determination of Timing of Activities and Total Float
1.3 Project Duration and Critical Path
1.4 Earliest Date Calculation
1.5 Effects of Duration Changes
1.5a) Activity E is delayed by 1 Day
1.5b) Activity M is delayed by 1 Day
1.5c) Activity R is completed early by 1 Day
1.6 Limitations of Network Diagrams
2) Task 2
2.1 Introduction of Project
2.2 Initiation
2.3 Planning
2.4 Execution
2.5 Closure
References
Appendices
TASK 1 (Educare Ltd)
TASK 1
1.1)
Below is the Network Diagram for Educare Ltd project. It shows a breakdown of the activities into small pieces and all activities needed to complete the project. (Field & Keller, …show more content…
2007)
TASK 1
1.2) The timing of activities is important as it helps with the planning of all resources. (Larson & Gray,5th edition).
The Timing of Activities is done by analysing the Forward Pass and Backward Pass throughout the Network Diagram.
The Forward Pass is the process of going through the network (Activity A – Activity R) from time zero. It goes through the network from the earliest start (ES) to the earliest finish (EF) with the minimum total project duration. The ES is the same as the EF of the next activity. For activities done simultaneously, EF comes from the latest finish among them.
The Backward Pass is the opposite. It is done by going through the network from the final activity to the first (Activity R – Activity A) and using the late start (LS) and late finish (LF) for each. It starts with Float as zero, which uses the number of days in the Forward Pass as its starting point. The LS is done by taking away the days from the LF for each single activity. For concurrent activities, the LF is the earliest LS of the previous activities. This is important when it comes to identifying the Critical Path and Total Float. It assumes all activities will start and finish at the latest date and will finish as the earliest of the previous activity starts.
Total Float (TF), also known as Slack, is the number of days where delays or luxuries of time are allowed from that will not affect the project completion date.
This is done by using LF-EF. For example in Activity E, we use the LF (12) to minus the EF (9) thus the TF is 3. TF for this activity will be 3 days. (Field & Keller, 2007)
1.3)
The Project Duration is the time taken to complete the whole project. In this project, it will be 40 days. This is done by adding the number of days from Activity A to R. When there are multiple activities, the latest time is taken.
Next is Critical Path (CP). It identifies the activities which has no room for error, or zero Slack. It is identified by linking all the activities with zero TF. For this project, it is as follows:
A B CGHJKLNOPQR
TASK 1
1.4)
By using the Total Project Duration of 40 days with a 5-days work week (no holidays in between) and starting on Monday 6th January 2014, we are able to compute the below …show more content…
table.
With reference to a 2014 calendar and we going forward 40 days, the end date will be 28 February 2014.
ACTIVITY
DAYS TAKEN
START DATE
END DATE
A
4
06-Jan-14
09-Jan-14
B
2
10-Jan-14
13-Jan-14
C
6
10-Jan-14
21-Jan-14
D
1
E
3
F
2
G
8
22-Jan-14
31-Jan-14
H
2
03-Feb-14
04-Feb-14
I
1
J
2
05-Feb-14
06-Feb-14
K
2
07-Feb-14
10-Feb-14
L
4
11-Feb-14
14-Feb-14
M
2
N
2
17-Feb-14
18-Feb-14
O
4
19-Feb-14
24-Feb-14
P
1
25-Feb-14
25-Feb-14
Q
1
26-Feb-14
26-Feb-14
R
2
27-Feb-14
28-Feb-14
TASK 1
1.5)
1.5a) Activity E is not part of the CP and the TF is 3 days, thus a delay in 1 Day will not affect the project completion date.
1.5b) Activity M is also not part of the CP and with the TF of 2 days, it will not affect the project completion date.
1.5b) Activity R is part of the CP, which will affect the project completion date. The whole project will complete 1 day earlier than planned.
This will benefit the project as it gives additional 1 day TF for fine tuning.
TASK 1
1.6)
The project managers (PM) welcome a bird’s eye view of the project for making time, costs and quality related decisions. The Project Network Diagram (PND) shows the sequence of activities and provides a graphical view of the project. It also allows the PM to plan for activities that can be done concurrently thus saving time.
The project completion date is important as it affects the proposal and agreement the PM sets. PND allows the PM to propose the end date accurately and save penalty costs incurred from delays.
For planning, it is crucial to know each activity’s start and end dates. PND allows the PM to focus their resources to the important areas to reduce errors and unnecessary risk. This prevents rushed work which compromises quality.
However, the activity time taken will have to be a judgement call by the PM. For the less experienced PM, this will be a shot in the dark where PND is of no help.
Another limitation is the underestimation of the project completion time due to alternate paths becoming critical. PND is useful only if all activities go as planned. An oversight or miscalculation will have a butterfly effect on the overall result.
TASK 2 (Murray PLC)
Task 2
Introduction
Every project has its unique Team, Scope and Control. In this report, we will determine the best steps and methods used to complete this latest club project.
The Project Objective is to have this new club up and running within 6 months from the start of the project within the budget of S$1,000,000. The manpower will be planned by our Human Resources while the purchase of the equipment will be done by our Procurement. The renovating of the club is not our expertise thus it will be outsourced. Selection of contractors will be done Procurement but the layout and design will be from Marketing.
Initiation
A Project life-cycle helps to provide the elements and break them down to smaller pieces for easier management. We will start off the current project at the feasibility state. At this stage of the report, we will analyse the financial and working aspects of this project to decide if it is worthwhile for Murray PLC to take on this project. (Burke, 2003)
We will be taking the below steps to forward this new club project.
Plan the project development and implementation activities.
Estimate the time taken, staffing and equipment requirements
Identify all costs and consequences of investing in this project (Harold ,2011).
As the project manager, I will be the project go-to person and the bridge between the planning team (management) and the executing team (hands-on). The success of this project is to meet the projected expectations like budget, punctuality and quality.
Staff Management
As in all projects, motivation and persuasion are two key skills to manage the staff. There will be sparks when people work together everyone wants things done their way. I will find the compromising point so that everyone will be able to work together. A happy workplace will produce quality work on time.
Project Management
I will oversee the project’s budget plans, work schedules and risk assessment. These planning will be empowered to individual teams manager. I will also analyse progress reports to make sure we are on schedule and conduct site audits to ensure quality.
Knowledge of Murray PLC
It will be my duty to know the working style and responsibility of everyone in Murray PLC. This allows me to make better decisions for the smooth sailing of this project when challenges arise and keep the morale of the team high at the same time.
Technical Skills
With my technical background, I will still be able to understand the challenges and constraints that each team faces. Together with the project as the big picture, I will be able to decide on a balanced plan/schedule that will not strain the teams but still adhere to the projected timeline.
Integration Skills
As a Project Manager, I will have to be a “Jack-of-all-trades”. Due to the coordination work with the various teams, understanding their jargons and their trade know-hows is essential as I will usually be the one who in the middle of things.
Responsibility and accountability
Each team will be assigned their roles and responsibilities. But I will still be the one responsible for the end results thus it will be on my shoulders to make sure instructions are understood and things are according to plan.
Accountability will come with each responsibility. Each team will have to be accountable for the quality of their part of the project. This in turn gives me a better idea of the team players and rewards will be fair.
Authority
To prevent myself as the bottleneck of the project, power of authority will be delegated to team managers of each team. In this way, it will be easier for me to manage the project as I will be able to focus on the overall challenges. (Richman,2002)
Feasibility Analysis
As mentioned above, the feasibility analysis is done to advise the management if this project is viable to be carried out. The following are the analysis.
Pay Back Period (Profit and Lost)
All projects are carried so that it will make money for the company. This methodology allows us to estimate the time taken to recover the investment put in. The formula is as follows: The Costs of Project or Investment Injected
Payback Period = --------------------------------------------------- Annual Cash Inflows of Murray PLC (each club)
According to the management, the investment made available for this new club will be S$1,000,000 with an estimate annual inflow of S$470,842 for 1 club. Using the above formula:
PP=1,000,000/470,842= 2.2 (rounded up)
Thus it will take about 2 years and 2 months to breakeven from this new club project.
Project Budgeting
Although there is S$1,000,000 set aside by the Murray PLC’s management for this project, we will still need to come up with a budget for a better idea of our expenditure. To do this, we will need the below information from all teams:
Manpower cost
Direct costs from each activity
Indirect costs from each activity
Total cumulative cost
With the above information, I will be able to work out a budgeting table and allocate funds to each team accordingly with advice from our Finance whom I have empowered as the project budget control.
Item
Amount allocated (S$)
New Building
300,000
Renovation (contractor)
168,000
Equipment and facilities
220,000
Staff acquired
100,000
Staff training
76,000
Miscellaneous
88,000
Grand Total
888,000
Projected Profit/Lost
According to the information from our Finance team, below will be an estimate of the total annual projected profit/lost for all 19 clubs (inclusive of the new club). Note that all figures are estimated.
Projected Cash Flow for all 18 Clubs
Projected items
Inflow (S$)
Outflow (S$)
Total (S$)
Annual Profit from all 18 Clubs
20,916,000
12,440,844
470,842 * 18 =8,475,158
Expenses (Maintenance, Payroll, etc)
0
4,013,000
(4,013,000)
Productivity Savings/Funding from Government
1,667,000
0
1,667,000
Total
6,129,158
Projected Cash Flow for new Club
Projected items
Inflow (S$)
Outflow (S$)
Total (S$)
Annual Profit from new club
1,162,000
691,158
470,842
Annual Profit from new club’s Beauty Spa
712,836
242,836
470,000
Expenses (Maintenance, Payroll, etc)
0
322,944
(322,944)
Productivity Savings/Funding from Government
92,661
0
92,661
Total
710,559
From the above table, we can see that there is an increase of S$ 710,559 in overall profit if we take on this new project which is a 10.4% increase in the annual profit. Given this figure, it will be beneficial for Murray PLC as a whole to take on this new Beauty Spa project. With this new project, it will not only give Murray PLC a bigger market share but also increase confidence to the shareholders that we are always the forerunner of the industry.
Initiation
Work Breakdown Structure (WBS)
WBS helps us analyse and divide the project into smaller work packages, dependencies and other activities which this project encompasses. It also shows their relationships and workflow in a visual form thus making it easier to understand the activities and the processes involved. With this, we will be able to come up with the project schedule, resource requirements and costs involved in this project.
(See Appendix A)
Organisation Breakdown Structure (OBS)
OBS is similar to that of WBS. The difference will be that it provides a clear allocation of responsibilities to each department. This will act as a guide when inter-department or inter-personnel challenges arise.
(See Appendix B)
Activities Identification (Network Information)
Before coming up with the network diagram, we have to identify the activities involved. Below will be the Network Information Table (Field & Keller, 2007)
ACTIVITY
ACTIVITY (TASKS)
DURATION (DAYS)
ACTIVITY PRECECESSOR
A
Approval by Management
7
--
B
Confirm leasing of new club location
14
A
C
Confirm equipment contractors
7
B
D
Confirm renovation contractors
14
B
E
Outfit new club
60
C, D
F
Install Equipment
14
E
G
Acquire Staff
30
F
H
Train Staff
60
F
I
Final Preparation
7
G, H
J
Completion and Handover
4
I
As we will take 6 months to get this new club up and running, a Gantts chart will be able to provide an overview for the company. We can also use this to track our progress of the whole project. (See Appendix C)
Risk Management
No matter how well all bases are covered, risks are still inevitable for all projects. The teams will face risks everyday that test their experience and judgement. A Risk Management team (lead by the Human Resources department) will be formed and consist of at least 1 member from each team so that we can get inputs from all angles. A Risk Management Manager (RM) will be appointed to coordinate all risk matters. Below are the steps taken to minimise and control the risk of this project:
Risks Identification
Risk Analysis
Risk Response Planning
Risk Monitoring and Control (Micheal J Termini, 1999)
Risk Identification is the first step. We will need to consult all the teams so as to identify the hotspots where problems will likely occur. The RM will lead the brainstorming session and gather all inputs.
Risk Analysis is done next. Methods such as Failure Mode and Effect Analysis (FMEA) will be used. With the brainstorming information, the RM will then estimate the severity and likelihood of activity failure.
Next step will be Risk Response planning. This is to ensure that the on-site-staff know what to do if the predicted risk occurs. This will be included in our Standard Operating Procedures.
Last, but not least, Risk Monitoring and Control.
The RM will disseminate to all the teams their area of responsibility to track and monitor risk. This will be done in conjunction with the team’s job function as they are experts in their field and able to deal with it effectively.
Execution
This is an important stage as the wheel will be set in motion and everything on paper will become reality. A lot of coordinating and people management skills will be needed.
There are 3 main areas to focus on: Managing the project teams, Managing inter-organisation relations and Progress evaluation. (Larsson and Gray, 5th edition)
Managing the Project teams
There are five stages to the form a team: Forming, Storming, Norming, Performing and Adjouring.
In this project, all team members are scorned from all the 18 current clubs. These start-up teams will assist the incoming local-teams (who will be newly employed by Human Resources) integrate to the Murray PLC culture and style of doing things. Upon completion of this project, the start-up teams will officially hand-over to the local-team to run the show. (See Appendix D)
Managing Inter-Organisation
Relations
As part of our project is outsourced to contractors due to our limitations in equipment purchases and building construction, inter-organisation relationship management is important. To make sure that we select the best option available, the awarding of this part of the project will be tasked to the Procurement Team in our Finance Team.
There are several advantages in outsourcing:
Due to the competitive nature of the industry, we are able to compare and get the best company for the job. This enables us to get cost reduction with good quality work together with the high level of expertise of the contractor. We will also not be constrained by our resource availability as we are able to tap on the contractors’.
However, there is also the other side of the coin:
As each company has their own culture and way of doing things, coordination breakdowns may occur. This communication breakdown may compromise the project timeline and its quality which in turn leads to conflicts. Trust is a very important here if we were to get things done according to plan.
We may lose our control over the project as we do not have much control over the contractors’ workers. We have to be careful with the selection process else we may not be able to complete the project successfully.
Lastly there are the security issues. The contractors will need information of Murray PLC to get their job done, Should these contractors jump ship to our rivals to earn more, we may have a problem as trade secrets will be shared with them. In order to address this, our Finance will make sure that they sign a non-disclosure clause with us.
Progress and Performance Evaluation
I have delegated to all Team Managers to do the On-Going Reviews of their teams while I will hold the Project and Performance Evaluations meetings (Periodic Inspections) every fortnightly to check on things. A Milestone Evaluation will be done after every stage to make sure of quality before the next stage starts. This is done so that problems will not spill over to the next stage. A Final Project Audit will be done at the last week of the project to before handing over to the Management.
Project Closure
This is the final step of the journey. We will be engaging a Facilitator to work with Human Resource to get a neutral and third person perspective.
A Wrap-Up Closure Checklist will be done to confirm that everything is done and nothing is left out. This is done for both internal and external parties.
A Post Project Evaluation is also done to find out the hits and misses of the project. This is important as we are able to take note of what to improve and where our strength lies. (Larsson and Gray, 5th edition)
Conclusion
The above report shows the recommended steps taken in order to make this New Club Project a success. For this project to work out, team work, dedication and some self-initiation is important from all team members.
----------------END----------------
References
REFERENCES
Burke, R (2003) Project Management-Planning and Control Technique (4th edition)
Field, M., Keller, L. (1998) Project Management. Open University
Richman, L. (2002) Project Management Step-by-Step
Larrson, E., Gray, C. (2011) Project Management, The Managerial Process (5th edition)
Turner, R. (1993) Handbook of Project-Based Management
Mubarak, S. (2005) Construction Project Scheduling and Control
Micheal, J. T (1999) Strategic Project Management: Tools and Techniques for Planning, Decision Making and Implementation
Harold, K. (2011) Project Management Metrics, KPIs and Dashboards: A Guide to Measuring and Monitoring Project Performance
Appendix
Appendix A
Appendix B
Appendix C
Appendix D
Stage 1: Forming Orientation to Project Testing and dependence
Stage 2: Storming Emotional response to the demands of the project Intergroup conflict
Stage 3: Norming Open exchange of relevant information Development of group cohesion
Stage 4: Performing Emergence of a solution Functional roles emerge
Stage 5: Adjouring Dissolution of the group