EXECUTIVE SHIRT COMPANY CASE
PGP1 – Section A
Group 13
Manohar Vankadara
Darshan Karkera
Sukvinder Singh
Sunil Kumar
A Touseefullah Siddiqui
Q.1) Compute the following quantities for the current production process as well as for Mike’s and Ike’s plans, assuming the plans are implemented as described in the case.
Solution:
Current batch processing
Sales for the Executive Shirt Company are constituted of only a few basic styles and colours. Hence the company has a limited number of varieties to produce. So, it has large batches of each kind of shirt (size and color).
It has only one cutting machine, which is computer-controlled and can cut up to 60 layers of cloth at the same time. Also up to 8 patterns can be cut simultaneously. The cutting process by the machine takes 30 minutes irrespective of the number of patterns and number of layers. But, the set up time is quite significant. It takes 1.5 minutes to roll out a layer of cloth and so for 60 layers; it takes 90 minutes setup time. The machine is being operated by 4 operators and the company is using its maximum capacity, i.e. 60 layers and 8 patterns at a time. So,
Total number of shirts cut in one run = 60*8 = 480
Total time taken by one run = setup time + runtime = 90 + 30 = 120 minutes
Regular shirts labor content (minutes per shirt) for cutting = 120 / 480 = 0.25 min per shirt
Number of workers = 4
|Operation |Regular Shirts Labor Content (minutes |Number of |Time taken per |Time taken per |
| |per shirt) |workers |shirt (minutes) |batch (minutes) |
|1. Cutting |0.25 |4 |0.06 |3.75 |
|2. Make collar |3.9 |8 |0.49 |29.25 |