Industrialization is very important for the development of country. It is considered as the backbone for the economy of country. Every businessman wants to grow its business by increasing its productivity.
The task which is given to our organization is only the civil works for the Extension of Paint Shop at Indus Motor Company. Our aim to complete this project within the given time and budget in order to follow all the policies and standards of client.
This proposal includes the planning, scheduling and execution of all the construction activities of this project. The proposed budget of this project is 80 million rupees and the completion time of all civil activities is 105 calendar days. The covered area of this extension …show more content…
The covered area of this extension is 10000 sq. yds. The budget of this project is 80 million rupees and the time to complete this project is 105 calendar days.
2.1 INCLUSIONS
• 95 Isolated Foundations with short columns.
• Plinth Beams
• Anchor bolts fixing on each columns for MS Structure
• Slab-on-Grade (SOG) on 10000 sq. yds.
• RCC Control room with covered area of 500 sq. yds.
• To follow the HSE plan provide by client.
2.2 EXCLUSIONS
• All drawing provide by client.
• All approvals taken by clients.
• SST will be pay be client.
• MS structure installation will be done by client.
• Anchor bolts will be provided by client.
2.3 ASSUMPTIONS
• PM Constructors work on Insurance Guarantee.
• Electricity & Water is provided by client free of cost.
• All soil test have been conducted by client.
3. PROJECT AIMS & OBJECTIVES
Extension of Paint Shop (only Civil Works) at Indus Motor Company located in Port Qasim, Karachi. The covered area of this extension is 10000 sq. yds. The budget of this project is 80 million rupees and the time to complete this project is 105 calendar days.
The civil works of this project covers:
• 95 Isolated Foundations with short columns.
• Plinth Beams
• Anchor bolts fixing on each columns for MS …show more content…
RISK ASSESSMENT
S.no Risk Categories Impact Financial Impact Area which may suffer
A. Internal Risk Known internal Risk
1. Cost Risk Mid High Budget, Duration
2. Time Risk Mid High Duration, Budget Unknown internal Risk
1. Quality Risk Low Mid Budget, Quality
2. Scope creep Low High Budget, Quality, Duration
3. Safety risk Mid Mid Duration
B. External Risk Known external Risk
1. Environmental risk High High Budget, Quality, Duration
2. Rainy Weather risk Mid Mid Budget, Quality, Duration Unknown external Risk
1. Political factors High High Duration
2. Material shortage Low Mid Duration, Budget
17. RISK RESPONSE & CONTINGENCY PLAN
S.no Risk Catagories Likelihood Risk Response Mitigation/Contigency plan
A. Internal Risk Known internal Risk
1. Cost Risk Mid Reduce In case of cost risk, we try to cover it with the contingency reserve of project.
2. Time Risk Mid Avoid In such case, overtime will be preferred. Also increase the resources. Unknown internal Risk
1. Quality Risk Low Avoid We try our best to meet the customer