A market survey of potential customer to assess the gas demand potential in the region has identified over 40 customers with a combined gas demand of 0.25 MSCMD for captive power. Negotiation for gas supply has also been initiated with them. ABC Gas Ltd has received expression of interest for over 0.075 MSCMD. However, timing of gas supply is the key since alternative fuel option such as solid and liquid fuels and wind energy are available. The expression of interest would fall through if gas is not supplied by mid 2008.
Amit Kumar, an engineer consultant, is hired by Prerna Goyal to identify the most feasible and economical route for laying down the gas pipeline. A preliminary site survey is followed by reconnaissance survey by Amit. After conducting Quantified Risk Assessment and evaluating several pipeline options, the consultant has proposed a 12 inch, 150 class low pressure (19 bar) pipeline for a total length of 30 kms from the ABC’s transmission