Hextable Dance project is an example application of value management in construction industry. It was moved from being unaffordable to reality, through the effective application of VM techniques. To build upon this, a project was initiated to construct a dance school of great aesthetic impact. Initially, the project was started 10 years ago but stalled because of the design. Even though it was an accepted innovative design, but it was expected to exceed the available construction budget of £2.1m by 20%. It is £420,000 more than the initial budget. To get the project back on track, the project team commissioned a VM study, involving all the key project stakeholders. The project was completed in 2005.

The objective to build this building is
…show more content…
There were a number of major issues facing the project team prior to the VM study. First is the two earlier schemes had failed and the current proposal exceeded the budget by 20% as mentioned above. Because of certain reason, due to the nature of the funding arrangements, finances were fixed and could not be increased. The project cannot proceed and need to investigate further in order to make sure the project will proceed within its original budget

The introducing of Value Management (VM) team recommended re-evaluating the project to focus on function. The project team effectively need to recheck all the function, to achieve maximum benefits by conducting the early stages of a VM study. Each stage normally involves a period of preparation, one or more workshops and a report, which identifies actions to develop and implement. In this case, the project team combined the first two stages to fast-track towards a solution.
…show more content…
Assertion
Decision building
The existing design for Hextable Dance was for a multi-level roof of great aesthetic impact, with a double-height ceiling in the main dance studio. One of the most important new ideas was to lay the building over only one storey. This was radical, but exactly the kind of idea encouraged in the creative stages of VM. The innovative roof structure and double-height studio ceiling could be retained by moving upper level areas to the ground floor, removing stairs and corridor space, so improving the building’s efficiency.
Lessons learned
■ Involving all key stakeholders in the VM study was very important when defining value. It allowed stakeholders to buy into the process and ensured their needs were met.
■ The architects’ full support made the VM process much more effective. They were willing to take suggestions from the project team and quickly put forward relevant options.
■ Willingness by the team to return to the client’s core requirements and to reassess the required functionality opened the project to increased creativity by removing unnecessary constraints – open mindsets really do make a

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Explain the expected impact on the project, and suggest two (2) ways the team could maintain its current goal in both planning and execution.…

    • 268 Words
    • 1 Page
    Satisfactory Essays
  • Best Essays

    Busi 650-ILP Final

    • 3605 Words
    • 15 Pages

    Delgado-Hernandez, D., & Aspinwall, E. (2008). A framework for building quality into construction projects - Part I. Total Quality Management & Business Excellence, 19(10), 1013-1028.…

    • 3605 Words
    • 15 Pages
    Best Essays
  • Satisfactory Essays

    Week 5 TCO F Project Monitoring and Control Project Management for Business, Engineering and Technology Chapter 11: Project Execution and Control (pp. 404-444) Earned Value Project Management Chapter 1: If Earned Value is so hot... (pp. 1-4) Chapter 2: Earned Value Project Management (Introduction) (pp. 5-13) Chapter 3: Earned Value Project Management (Overview) (pp. 15-25) Chapter 5: The Earned Value Body of Knowledge (pp. 35-46)…

    • 390 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Ah531

    • 3543 Words
    • 15 Pages

    Valle, J., & Soares, C. (2005). The use of earned value analysis(eva) in the cost management of construction projects. Federal university fluminense, brazil, Retrieved from http://www.google.com/url?sa=t&rct=j&q=&esrc=s&frm=1&source=web&cd=4&ved=0CEQQFjAD&url=http://www.icoste.org/ICMJ%20Papers/Valle%20-%20EVA.pdf&ei=PkW7UeT0BobY8gS18YCADg&usg=AFQjCNFSA-RUj35ZNIwD-ii15E76nCs9-Q&sig2=Sktqkw1XxvD8CRFJnvkbVg…

    • 3543 Words
    • 15 Pages
    Powerful Essays
  • Best Essays

    We will create long term value by applying project controls oversight, leadership, and partnerships in executing the right projects at the right time and the right cost.”…

    • 3170 Words
    • 13 Pages
    Best Essays
  • Better Essays

    Senior Management

    • 1685 Words
    • 7 Pages

    6) Lack of project ownership from the senior management team – It was only Frank Carau and Ben Walker, who are juniors that are handling the project. It does not have enough clout to direct and influence the project on the senior management levels. However, with the leadership and sponsorship of Phil Faraci, the project came into a turn-around from being a slow-paced to fast-paced project, from being a…

    • 1685 Words
    • 7 Pages
    Better Essays
  • Satisfactory Essays

    Project Management

    • 289 Words
    • 2 Pages

    Apply the project management concepts discussed in Weeks 1–3 to this project. This information will also be used in next week’s individual…

    • 289 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Matrix Template

    • 756 Words
    • 4 Pages

    GenRays Matrix Template Project Management Knowledge Areas|Recommended Tool(s)|Justification for Tool| Project Integration Management | Expert Judgment|-PM Plan is Formal, single document, approved (becomes officially the project plan. It defines how project is executed and controlled. Scope, schedule, and Cost, Change, and Configuration Management plans are created in this process and are part of the PM plan- Scope Management plan is developed here as well.| Project Scope Management | -Interviews -Focus Groups -Facilitated Workshops -Group Creativity Technique -Group decision making techniques -Questionnaires and Surveys -Observation(Job Shadowing) -Prototypes| Facilitated Workshops examples: JAD and Quality Function Deployment Group Creativity Technique examples: -Brainstorming -Nominal Group Technique: enhances brainstorming with voting process -Delphi Technique-Idea and Mind Mapping -Affinity Diagram: large numbers of ideas to be sorted into groups Group Decision making technique -Unanimity: everyone agrees on single course of action -Majority: support from more than 50% of the members of the group -Plurality: the largest block in a group decides even if a majority is not achieved Dictatorship: one individual makes the decision for the group| Project Time Management| -Bottom- up Estimating -Expert Judgment -Alternative Analysis -Published Est. Data -PM Software| Bottom-up estimating: Breaking down complex activities into pieces. -Published Est. Data: Published data as books and journals -Alte. Analysis: means considering several different options for how to assign resources| Project Cost Management | -Analogous Estimating -Bottom-up Estimating -Parametric Estimating -Cost of Quality -Vendor Bid Analysis -Reserve Analysis -Expert Judgment -Three-point estimates -PM estimating software| -Cost of quality: Cost that is incurred to achieve required quality -Rough order of magnitude: As the project moves, estimates should become more accurate -Direct Costs: Costs…

    • 756 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    the solution is deployed. Hence, many of the details of implementation must be planned ahead of…

    • 1463 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    Dance History Review

    • 477 Words
    • 2 Pages

    Prepare answers for all of the questions below. On the exam you will answer 8 questions: 4 that I select and 4 that you select = 8 total. The length of each answer should be one-half page or more.…

    • 477 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    A Professional Failure

    • 358 Words
    • 2 Pages

    The most important thing I learned from this experience is the key role of a project leader, a person who could select the right people in the team, coordinate the relationship between client team and technology team, monitor the progress to ensure not shift to the target. Without such a leader, although we had world-class technology team and emotion, this project finally failed. The particular experience is important to me because I am aware that I am lack of project management skill to maximum my solid technology skills to well sever my clients. This is a major…

    • 358 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    “The Importance of Fine Arts Education” focuses on how fine arts are an essential part of development in every human being and are part of the cultural heritage of every American. It also notes the impact fine arts education has on improving learning throughout all academic areas. The article is published on the Katy Independent School District's website and lists many credible sources. Therefore, the article itself is highly credible.…

    • 1267 Words
    • 6 Pages
    Satisfactory Essays
  • Powerful Essays

    Chunnel Project

    • 9442 Words
    • 38 Pages

    This case study was originally prepared as part of Project Management Applications, the capstone course of the Master of Science in Project Management in the Department of Management Science at The George Washington University, by the graduating students listed above with the supervision of Professor Anbari.…

    • 9442 Words
    • 38 Pages
    Powerful Essays
  • Good Essays

    Dance Critique

    • 1307 Words
    • 4 Pages

    Late last Saturday day night, on April 14,2012, I attended the very first dance concert at John Anthony Theater at Collin College Spring Creek Campus. This concert was performed by Collin Dance Ensemble, which is a vibrant company that performs innovative contemporary modern dance. Their goal is to produce dance works at the highest level of artistic excellence. The dance company attends and performs at the American College Dance Festival annually and has been selected for the Gala Performance at the regional festivals sevens times.…

    • 1307 Words
    • 4 Pages
    Good Essays
  • Good Essays

    In developing this contemporary and iconic building, the design focuses on practical attributes and optimises energy efficiency. The design strategy encapsulates four key aspects:…

    • 907 Words
    • 4 Pages
    Good Essays