IGC 3 Management Report IGC 3 Sample
INTERNATIONAL GENERAL
CERTIFICATE
(2010 specification)

Candidate report template

UNIT IGC3 – THE HEALTH AND
SAFETY PRACTICAL APPLICAITON

Student number:
Location: Head Race Tunnel of under construction XYZ* Hydro Electric Power Plant
Date of review: 25 / February / 2012
* - Name of the power plant is confidential and may infringe with my employment contract conditions and hence has not been revealed herewith in this report.

Introduction: th This Health & Safety inspection was carried out by me on 25 February 2012 between 1230 hrs and
1330 hrs at the Head Race Tunnel (HRT) area of the under-construction XYZ* Hydroelectric power plant. The project is a run-of-river type 100 MW hydro electric power plant designed with a 4 Meter diameter and 1.2 KM long Head race Tunnel. During the time of this inspection, construction of the
HRT was in progress, with approximately 300 meters out of the 1.2 KM length being completed. The selected contractor had deployed 30 workers inside the head race tunnel for this job.
Following activities were in progress inside the HRT during the time of inspection: Concreting on the inner tunnel surfaces using the Hydraulic Gantry, removal of muck, transportation of concrete, Use of winches to support the Gantry, Constant De-watering and part-assembly of the Gantry parts using hot work. Executive Summary th A Health & Safety inspection was carried out on 25 February 2012 at the Head Race Tunnel (HRT) area of the under-construction XYZ* Hydroelectric power plant. The main objective of this inspection was to identify prevalent HSE hazards which may cause ill-health and or Human Injury. At the time of inspection, following jobs were being undertaken: Concreting on the inner tunnel surfaces using the
Hydraulic Gantry, removal of muck, transportation of concrete, Use of winches to support the Gantry,
Constant De-watering and part-assembly of the Gantry parts using hot work.
This inspection clearly reveals that there are very serious hazards