In this part we can add our project information. We can add our start date of the project and also shows the current date of the project. We can set it at start of our project and then proceed further. We can also change dates here. As we can see the start date of the project is Mon. 12th Oct. 2015.
This below figure shows the options of the schedule of the project and general information. It also shows the calendar we have used that is 40 hours in a week. We have working 8 hours a day and 5 day in a week with Saturday and Sunday off days.
2.1. General Information
This below figure shows the options of the schedule of the project and general information. It also shows the calendar we have used that is 40 hours …show more content…
Place wall insulation - 2nd floor 52 FS
54. Place ceiling insulation - 2nd floor 60,53 FS, FS
55. Conduct insulation inspection 54 FS
56. Drywall
57. Install drywall - 1st floor walls 52 FS
58. Install drywall - 1st floor overhead 57 FS
59. Install drywall 2nd floor walls 58,53 FS, FS
60. Install drywall 2nd floor overhead 59 FS
61. Tape and float 1st floor drywall 58 FS
62. Tape and float 2nd floor drywall 60,61 FS, FS
63. Paint and Wallpaper
64. Texture all except entry and kitchen - 1st floor 61 FS
65. Paint all except entry and kitchen - 1st floor 64 FS
66. Hang wallpaper entry and kitchen - 1st floor 65 FS
67. Texture all - 2nd floor 64 FS
68. Paint all - 2nd floor 67 FS
69. Paint exterior siding & trim work 40 FS
70. Cabinets
71. Install 1st floor - kitchen cabinets 66 FS
72. Install 1st floor - master bath and guest cabinets 71 FS
73. Install 2nd floor - hall bath and private bath cabinets 72 FS
74. Install chair rails, crown moldings, trim 73 FS
75. Finish Plumbing
76. Complete 1st floor - kitchen plumbing 71,43 FS, FS
77. Complete 1st floor - master bath and guest plumbing 76,72 FS, FS
78. Complete 2nd floor - hall bath and private bath plumbing 77,73 FS, FS
79. Conduct finish plumbing inspection 78