IN1 International Accounting Standard 16 Property, Plant and Equipment (IAS 16) replaces IAS 16 Property, Plant and Equipment (revised in 1998), and should be applied for annual periods beginning on or after 1 January 2005. Earlier application is encouraged. The Standard also replaces the following Interpretations:
• SIC-6 Costs of Modifying Existing Software
• SIC-14 Property, Plant and Equipment—Compensation for the Impairment or Loss of Items
• SIC-23 Property, Plant and Equipment—Major Inspection or Overhaul Costs .
Reasons for Revising IAS 16
IN2 The International Accounting Standards Board developed this revised IAS 16 as part of its project on Improvements to International Accounting Standards. The project was undertaken in the light of queries and criticisms raised in relation to the Standards by securities regulators, professional accountants and other interested parties. The objectives of the project were to reduce or eliminate alternatives, redundancies and conflicts within the Standards, to deal with some convergence issues and to make other improvements.
IN3 For IAS 16 the Board’s main objective was a limited revision to provide additional guidance and clarification on selected matters. The Board did not reconsider the fundamental approach to the accounting for property, plant and equipment contained in IAS 16.
The Main Changes
IN4 The main changes from the previous version of IAS 16 are described below.
Scope
IN5 This Standard clarifies that an entity is required to apply the principles of this Standard to items of property, plant and equipment used to develop or maintain (a) biological assets and (b) mineral rights and mineral reserves such as oil, natural gas and similar non-regenerative resources.
Recognition—Subsequent Costs
IN6 An entity evaluates under the general recognition principle all property, plant and equipment costs at the time they are incurred. Those costs include costs incurred