2 out of 2 points | | | Which of the following questions does the organization's mission statement answer?Answer | | | | | Correct Answer: | What do we want to become? | Response Feedback: | The mission identifies "what we want to become," or the raison d'être. Mission statements identify the scope of the organization in terms of its product or service. | | | | | * Question 2
2 out of 2 points | | | From among the following activities, which is the best example of a project?Answer | | | | | Correct Answer: | Writing a term paper | Response Feedback: | See table 1.1 on Page 6. | | | | | * Question 3
2 out of 2 points | | | Which of the following choices is not one of the stages of a project life cycle?Answer | | | | | Correct Answer: | Conceptualizing | Response Feedback: | See List on Page 7. | | | | | * Question 4
2 out of 2 points | | | Multi-weighted scoring models include only quantitative criteria, not qualitative.Answer | | | | | | Correct Answer: | False | Response Feedback: | Weighted scoring models will generally include qualitative and/or quantitative criteria. | | | | | * Question 5
2 out of 2 points | | | From 1994 to 2009 the trend for projects late or over budget was:Answer | | | | | Correct Answer: | Slightly better | Response Feedback: | Failed projects also declined from 31 percent in 1994 to 18 percent in 2004. However, the CHAOS Summary 2009 report shows a small decrease in the numbers. | | | | | * Question 6
2 out of 2 points | | | Project management is usually restricted to specialists.Answer | | | | | | Correct Answer: | False | Response Feedback: | Unlike their functional counterparts, project managers generally possess only rudimentary technical knowledge. | | | | | * Question 7
2 out of 2 points | | | In the current trends, Project managers are