Preview

Kah Seg Construction Case Study

Better Essays
Open Document
Open Document
3408 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Kah Seg Construction Case Study
According to clause 30.7 in PAM 2006, if the employer do not pay within 14 days after receiving a suspension notice by the contractor, the contractor must further issue a written notice delivered by hand or by registered post to effect his suspension of work and provided that such notice shall not be given “unreasonably or vexatiously”. Case law above has defined “unreasonably”, which means contractor’s notice have brought a disproportionately disadvantage to the employer, and may even contend that the notice to be “vexatiously” given, which means the contractor has the ulterior motive or purpose of oppressing, harassing or annoying. From the cases discussed and analyzed here, when the contractor suspends works, the employer can claim that …show more content…
In Kah Seng Construction Sdn.Bhd. v Selsin Development Sdn.Bhd, it was stated that a Contractor’s response to actual or alleged breaches of contract by the owners by suspending or deliberately going slow are extremely dangerous. In this case, the plaintiff contended that it was entitled to suspend works because of non-payment of one certificate and partial non-payment of another. The defendant argued that even if the Defendant was not entitled to set off sums of monies for delay and defective works against sums due to the Plaintiff in the interim certificates, there was no provision in the rudimentary contract between the parties for non-payment of certified sums and that the Plaintiff’s admitted suspension was wrongful. The judge held …show more content…
The statement also supported by the case of Graymark Investment v Walter Construction Group; the Contractor is entitled to an EOT since he failed to meet the notification requirements as stated in the Contract. Although the arbitrator found that the Contractor was entitled to an EOT since such delay is caused by the Employer but the court refused to uphold the “notice condition precedent” provision, but instead relied on the “prevention principle” that a party cannot take advantages of its own wrong in enforcing a contract. While in the case of City Inn v. Shepherd Construction, the Contractor has failed to send the notice which was a condition precedent to apply an EOT. The court held that the failure on the part of the Contractor to comply with the provision is properly regarded as breach of contract on his part since he said that:
“If the Contractor having formed the opinion, elects not to do what the clause requires of him, he not only deprives himself of any entitlement, he would otherwise have had to an EOT; he also deprives the Architect opportunity of reviewing the instruction in light of the Contractor’s opinion of its consequences, and choosing whether to insist in it, or withdraw it… it therefore seem to

You May Also Find These Documents Helpful

  • Good Essays

    This case is an interesting one because it gets right into the core of the confliction between the proprieties of contractual agreement. This case is focused primarily on Osborne Development Corp. and the multiple defects customers are experiencing with their homes. These upset customers are suing this Corporation in attempts to collect reparations for the discrepancies faced. The homeowners who purchased homes form Osborne Development Corp. (ODC) negligently purchased these homes. According to the Home Buyers Warranty ( HBW), “ Any and all claims disputes and controversies by or between the Homeowner, the Builder, the Warrant Insure and/or HBW…

    • 527 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Huether moved to dismiss based on failure to state cause for action. The court dismissed the case. Holy Cross Parish took this case to the appeals court stating that there was an error in law made. Holy Cross Parish, the appellant, has made it known that the contractors they hired failed to disclose any information pertaining the damages and irregularities. The appellant had the idea that the job would be performed correctly and no issues were brought to their eyes. The contractor also knew of the issues but did not inform anything to the appellant which was misleading. Also the architect and the appellant had a fiduciary relationship but because he remained silent about the final product that the contractor conducted, he has misled and created a breach of fiduciary duty to the appellant. The court of appeals has reverse this case based on the facts…

    • 317 Words
    • 2 Pages
    Good Essays
  • Good Essays

    Mr. Ralph Gough was under a preexisting duty to construct the trusses for the Kinney shoe store. The general contractor, Chuckrow, was never obligated to pay for the re-erection of those trusses no matter who’s fault if they fell according to the original agreement. Mr. Gough 's preexisting duty cannot operate as consideration or change Chuckrow 's offer to pay. Therefore the contract was not modified, and Chuckrow is obligated only for the original contract price. Hence Mr. Gough cannot recover the funds. (Robert Chuckrow Construction Company v. Gough, 1968)…

    • 573 Words
    • 3 Pages
    Good Essays
  • Better Essays

    The contract was awarded to the lowest bid, Sorochan Enterprises Ltd. Issues: Does the statement of privilege allow the owner to choose a bid other than the lowest even if it breaches the terms of the tender? Facts: One of the tender documents was that the lowest bid or tender shall not necessarily be accepted. There were multiple types of materials that could be used for the sub grade for installing the pipe, and the owner wanted to see only a single…

    • 1347 Words
    • 6 Pages
    Better Essays
  • Satisfactory Essays

    For the case of Sopov v Kane Constructions Pty Ltd (No 2) [2009], the appellant engaged the respondent as contractor in a construction project. The appellant repudiated the contract by wrongly calling on the respondent's bank guarantee, in response to which the respondent terminated the contract and claimed damages for quantum meruit. The Court of Appeal applied the NSW Court of Appeal decision in Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR 234 which provided that an innocent party who accepts a defaulting party's repudiation has the option of claiming either damages for breach of contract, or a quantum meruit for the fair value of work done. The initial contract price was held to be only evidentiary for the…

    • 255 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    leg 440 discussion week 2

    • 503 Words
    • 3 Pages

    Selection of sources for Architect-Engineer contracts in accordance with the provisions of 40 U.S.C. 1102…

    • 503 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Case brief

    • 593 Words
    • 2 Pages

    Issues: 1) Whether the district court erred in concluding that hay is not a “product “for purposes of a strict liability in tort cause of action. 2) Whether the District Court erred in concluding that the Rothings negligence claim against Kallestad fails because it was unforeseeable that the hay could cause injury and death to the Rothings’ horses, thus no duty of care existed. 3) Whether the District Court erred in concluding that the Rothings’ breach of contract claim against Kallestad fails because it was unforeseeable that the hay could cause injury and death to the Rothings’ horses. 4) Whether the District Court erred in imposing discovery sanctions against the Rothings. 5) Whether the District Court erred in awarding attorney’s fees to Kallestad and denying the Rothings a hearing in respect to the calculation of attorney’s fees. (₱3-7)…

    • 593 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Wright, we have a situation where implied terms can be involved. What makes this case implied is because we are dealing with a modern contract that allows certain situations of the contract to be somewhat flexible. In this case, Cerdes is suing Wright for breach of contract. Cerdes did not finish the job in enough time that was suitable for Wright. Therefore Wright proceeded to hire other service to complete the job. Due to the fact that time was the purpose of the change in contractors, implied terms can be enforced. The length of time that should be assumed in this case if not stated in the contract should be based on the job and how long it should typically take for a construction of a house. You would be able to determine this by an average number of homes that size being built. If the Cerdes is discovered to have taken too much time, then he should not be awarded the full amount of the…

    • 605 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Contracts I Course Outline

    • 2280 Words
    • 10 Pages

    1. Expectancy (benefit of the bargain) “in as good a position as he would have been had the contract been performed” Restatement § 344(a) and § 347…

    • 2280 Words
    • 10 Pages
    Good Essays
  • Satisfactory Essays

    Interoffice Memo

    • 363 Words
    • 2 Pages

    As you can see in points number one (1) and two (2), we are legally obligated to follow through with notice if the client is potentially…

    • 363 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Facts: The University of Utah was in need of a women’s Gymnastics training facility so they subcontracted Fox Construction, Inc. to complete the project. For the soil and ground work Fox Construction, Inc. subcontracted with Gary Porter Construction. Gary Porter Construction, Inc. performed their work based on specific plans as well as some work outside of the plans. The combined total from the planned project was $146,740. The additional work completed at Fox’s request cost Gary Porter construction additional costs and Fox refused to pay for the additional work done outside the subcontract.…

    • 1331 Words
    • 6 Pages
    Good Essays
  • Good Essays

    However, there are cases in both Canadian and American law that demonstrate that this is not the case [1]. One of the general principles that show this was established by the Belle River Community Arena Inc. v. W.J.C. Kaufmann Co. et al.. Similar to the situation at hand, the Belle River case involved a bid that was much lower than intended. Both parties acknowledged the mistake in the bid and like the City of Waterloo, Belle River did not allow the contractor to revoke the mistaken tender. In this case, the Belle River Community Arena also sued Kaufmann for the difference between their bid and the next lowest bid [3]. The only major difference between this case and the Belle River case is that Belle River did not submit a formal offer while the City of Waterloo did [1]. However, in deciding the case and the support of this decision in the Ontario Court of Appeals, it is found that "In substance the purported offer, because of the mistake, was not the offer the offeror intended to make, and the offeree knew that […] The situation would be quite different, the Court of Appeal noted, if the offeree had not known the offer contained a mistake and had accepted it at face value." [3]. This constitutes a legal principle that ought to be applied to this case. It is best summarized as done in Law for Professional Engineers, "an…

    • 1070 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    law of contract

    • 11627 Words
    • 47 Pages

    Facts: P is suing D for wasted expenditure arising from D’s breach of K to star in their production…

    • 11627 Words
    • 47 Pages
    Powerful Essays
  • Better Essays

    Contract Disputes

    • 1248 Words
    • 5 Pages

    “CONTRACT DISPUTES REACH 15-YEAR HIGH”, was the heading of an article published, December 1, 2010 in the Government Executive. The heading in itself tells us that the government is doing more and more business by contract and as a result contractors who are lobbying for government business have become more aware of their rights to file disputes when it involves a loss of potential business. Because of this increase in disputes, the government must have a method of terminating contracts without suffering the financial liabilities that could result in millions and millions of dollars going to incomplete contracts and rebids to acquire a contractor for completion of unfinished contracts. This method of termination is known as a Default Clause which will be covered later in this paper. First we will look at a case that involves a contract dispute. The GAO file number: B-215789 which involves J.C. Hester Company, Inc who was awarded contract number: F34650-81-C-0158 with the Department of the Air Force. My reason for choosing this dispute case was because it requires that the individual look at all aspects of the case in reference to Disputes. Usually dispute cases depend on more than one aspect of the FAR. This case shows that not only the contractor but the contracting officer should pay strict attention to the reasons for the dispute. In this case knowledge of the Bids Protest Process area of the FAR is also required to determine if the recommendation by the Comptroller General was indeed valid and fair.…

    • 1248 Words
    • 5 Pages
    Better Essays
  • Best Essays

    XYZ Construction Case Study

    • 4054 Words
    • 26 Pages

    Change Management XYZ Construction Case Study Author: Parusha Table of Contents Introduction ................................................................................................................................ 3 1 Extent to which XYZ adopted the Culture – Excellence approach .................................... 4 1.1 The three change approaches .......................................................................................... 4 1.2 Adoption of the Culture – Excellence Approach ............................................................ 7 2 Reasoning for little opposition/resistance from staff ........................................................ 10 3…

    • 4054 Words
    • 26 Pages
    Best Essays