Kerzner Question 11 46
a. The project manager is brought on board at the beginning of the conceptual phase but acts only as an observer. The project manager neither answers questions nor provides his ideas until the brainstorming session is completed.
The advantage of bringing the project manager on board at the beginning of the conceptual phase, but only as an observer is that the project manager will be able to understand the brainstorming process that was undertaken which will allow him/her to see how the group works together in making decisions. Further, it would provide the project manager with insight into which employee to place in certain areas, based on the task of conceptualizing the project.
The disadvantage of bringing the project manager on that this phase only as an observer is that the project manager does not have the advantage of helping to come up with ideas, at the beginning of the project, that could help make the project successful. Without the project managers input in this phase he/she is unable to resolve any conflicts that occur, or have any input into any potential conflicts that may occur as a result of the concept that was created by others.
b. When brainstorming is completed during the conceptual phase, senior management appoints one of the brainstorming team members to serve as the project manager.
The advantage of having a brainstorming team member to serve as project manager is that this team member was able to provide some input when creating the project concept. This would allow the project manager to have input into the thoughts and ideas that later developed into the project itself. Further, this individual would have firsthand knowledge of the project team members, how well each member works with the group, and where each team members' strengths and weaknesses lie.
The disadvantage of having a brainstorming team member to server as project manager is that it may cause dissension among the project group. Other team members may feel let down and

You May Also Find These Documents Helpful

  • Powerful Essays

    Proj. Man Final Paper

    • 1789 Words
    • 8 Pages

    Using the information the project manager would be in possession of when starting the project right after it was awarded they should first identify the key stakeholders and create a stakeholder register and a communications matrix. Creating the stakeholder register and the communications matrix would help identify the key players and contact information as well as providing a readily available means to reach the said key players at any critical times without having to search for the needed contact information. This information can also be used to help create organizational charts and assist with determining chain of command within the project.…

    • 1789 Words
    • 8 Pages
    Powerful Essays
  • Powerful Essays

    The Project Manager is responsible for balancing the competing objectives of project cost, time and…

    • 1250 Words
    • 5 Pages
    Powerful Essays
  • Good Essays

    CLC Project Guidelines

    • 814 Words
    • 4 Pages

    This will allow us to make sure the project is what we all want and not just what “one of us wants” or even help us our if someone has a better idea or different way of handling a issue…

    • 814 Words
    • 4 Pages
    Good Essays
  • Best Essays

    CIPD - 5DPP

    • 3309 Words
    • 14 Pages

    ‘The project manager’s job is challenging - her success requires a keen ability to identify and resolve sensitive organisational and interpersonal issues.’ (Portny 2012: 21). As one of the principle stakeholders in the project their responsibility is…

    • 3309 Words
    • 14 Pages
    Best Essays
  • Powerful Essays

    Staffing a project team is a vital piece of the project management process. The composition of a successful team includes members with the skills, knowledge, and abilities to perform the work of the project (Project Management Body of Knowledge (PMBOK), 2013, p. 35). This holds true in the assignment of a project manager. The first error in the Orion Shield Project was assigning Gary Allison as the project manager. As quoted in CIO (2012), “inadequately trained and/or inexperienced project manager can doom a project”. Schwalbe (2012), identifies ten knowledge areas a project manager must develop; it includes stakeholder, procurement, risk, communications, human…

    • 1442 Words
    • 5 Pages
    Powerful Essays
  • Satisfactory Essays

    wbs dictionary

    • 524 Words
    • 3 Pages

    Project Manager conducts a formal kick off meeting with the project team, project stakeholders and project sponsor.…

    • 524 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Project managers play the leading role in the project management process: They are accountable for the completion and delivery of projects. They create an atmosphere of teamwork and collaboration in which a defined goal can be achieved in a controlled and structured manner by a group of people. Project managers manage projects on a day-to-day basis, maintain a continuous focus on moving projects toward their defined objective, drive the decision-making process and execute milestones according to plan (Guzman, 2010).…

    • 2266 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    Project Launch or Execution: The project manager will be responsible for the above conceptions, initiations, and planning.…

    • 567 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Project Management has become a very important and popular business tool in recent years. If you want a successful project you should have a person in charge to keep the project organized. A project manager must have strong leadership skills such as:…

    • 687 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Grt Task 1

    • 19334 Words
    • 78 Pages

    B. Monitoring/Controlling C. Initiating D. Planning Correct Answer: D QUESTION 6 Given the circumstances below, which of the following would be the BEST action for the project manager to take? One of the key stakeholders disagrees with the project. Two of the key staff members refuse to work with each other. The budget for the project has been reduced. The scope of the project has changed. A. The staff members who refuse to work together should be terminated so that the project can proceed on schedule. B. The project should be closed because the scope has changed. C. The project manager should work with the stakeholders to resolve the areas of disagreement.…

    • 19334 Words
    • 78 Pages
    Powerful Essays
  • Good Essays

    Groupthink Case Study

    • 547 Words
    • 3 Pages

    The Project Manager needs to give a clear goal to the team members to avoid groupthink from occurring. Every team member also needs to know that the Project Manager is holding them accountable. According to Janis & Mann (1977) “the…

    • 547 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Staff members who are working on the project are also a very important resource. This will help to support the project manger as the project would be completed faster and with a better standard. The project manger ensures that each staff member has the correct set of skills needed, in order to complete to the project. The manger is should also ensure that each member is determined to do their best and give their best in order to make the project successful.…

    • 316 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    Management Structures

    • 310 Words
    • 1 Page

    The advantages of the Project Team structure are that the team members will bring diverse ideas to the table, which will benefit the clients. Each team works independently on their project and there is one team leader who is responsible for making sure the project is running smoothly. The main disadvantage is that conflict often arises, making things difficult to agree on. Often the team leader needs to resolve the conflict.…

    • 310 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    This could be how any project is organised, of course. But the standard itself lays down a lot of bureaucratic detail about the level and structure of the documentation required.…

    • 958 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Project Organization - During the session, the Project Manager can review the project organizational chart and the associated roles and responsibilities to accomplish the project objectives.…

    • 763 Words
    • 3 Pages
    Good Essays