Fax :0172-2583724
To: Chief Engineer(MM) Haryana Vidyut Prasaran Nigam Ltd, Panchkula
From: Raj Kumar Gupta General Manager (NT), TCIL, New Delhi
Subject : Your Memo No: Ch-23/HDP-1869/Xen/S/STN./P Dtd. 12.02.2013
Reference: Third Party Quality Surveillance Services on behalf of HVPNL- Contract
Agreement between HVPNL and TCIL.
Dear Sir,
We are in receipt of your above referred letter regarding Final inspection of Power Transformer as per the following detail.
1. Manufacturer : M/s Technical Associates Ltd. Sitarganj Uttarakhand
2.TCIL Inspection Date : 21st Feb 2013 & 22nd Feb 2013
An inspection of Final of Power Transformer at the work premises of M/s Technical Associates Ltd B-7, Eldeco Sidcul Industrial Park, Sitarganj, Dist. Udham Singh, Uttarakhand was conducted for the following Designation and Quantity :
|Transformer Rating |Unit nos. |Qty |
|20/25 MVA 132/33 KV |7th Unit |1 |
We are enclosing a copy of the following documents for your kind information please:
1. Inspection Test Report in Original (Signed by Manufacturer and TCIL)
2. Copy of Calibration Status of test equipments, which are well within validity period.
3. Copy of Test Certificate of Bought out items.
4. Copy of inspection call letter from HVPNL.
5. Letter from the manufacturer regarding Final inspection of Power Transformer.
Contd……
-2-
The test result