Lean Sample Exam
EIN 4401
Key to Sample Midterm 2
Closed book, Closed notes

1. (20 pts) Consider the following information about a small molding company that subcontracts to major toy manufacturers. A set of jobs, whose numbers indicate the order they arrived at the shop and ready to be processed are given below.

Job | pi | di | 1 | 8 | 26 | 2 | 12 | 28 | 3 | 6 | 32 | 4 | 10 | 35 | 5 | 3 | 38 | 6 | 11 | 48 | 7 | 9 | 50 | 8 | 11 | 51 | 9 | 13 | 53 | 10 | 7 | 64 |

a) Schedule the jobs by using SPT rule. For this rule calculate total tardiness, maximum tardiness, number of tardy jobs, and average tardiness. b) If the company policy dictated that any customer with late delivery will be compensated with a discount proportionate to the amount of days of delay beyond that job's due date, which rule should you use? c) If each tardy job gets $50 + $10*(# of days tardy) discount for each day of tardiness what will be the total loss due to tardiness of some jobs out of the job shop?

2. (30 pts.) An IE is performing job-shop scheduling using TOC method. He has already calculated the following table for making scheduling on the bottleneck machine #4. Job i | 1 | 2 | 3 | 4 | 5 | 6 | ri4 | 0 | 6 | 14 | 23 | 14 | 30 | di4 | 12 | 27 | 19 | 33 | 45 | 60 | pi4 | 10 | 5 | 6 | 12 | 23 | 15 |

a) During solution process he gets a mental block and cannot order the jobs on this machine. Help him complete the following table.

t | S(set of schedulable jobs) | Job selected | [s.4,c.4][Start time of selected job, completion time of selected job] | | | | | | | | | | | | | | | | | | | | | | | | | b) Based on your completed table what is the job sequence on this machine? What is the makespan?

3. (30 pts.) Consider the data below.
Daily demand matrix:

| 40-Day Demand | Daily Demand | Part A | 1200 parts | 30 parts | Part B | 2400 parts | 60 parts | Part C | 3600 parts | 90

You May Also Find These Documents Helpful

  • Satisfactory Essays

    A) The textbook states that 30 percent of customers pay on the 10th, 40 percent pay on the 13th and 30 percent pay on the 40th day after purchase.…

    • 93 Words
    • 1 Page
    Satisfactory Essays
  • Satisfactory Essays

    M1 Week 3

    • 1315 Words
    • 6 Pages

    Step 4: If the smallest processing time is on the second machine, assign that job at the end of the sequence and eliminate the job.…

    • 1315 Words
    • 6 Pages
    Satisfactory Essays
  • Powerful Essays

    PROJ 586 Final Exam

    • 872 Words
    • 4 Pages

    12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.…

    • 872 Words
    • 4 Pages
    Powerful Essays
  • Good Essays

    ACC 497 Final Exam

    • 2281 Words
    • 11 Pages

    17) Which of the following processes would be accounted for using a job order cost…

    • 2281 Words
    • 11 Pages
    Good Essays
  • Better Essays

    1) Prepare the manufacturing staff’s calculations for the three alternatives (please refer to the attachments):…

    • 1278 Words
    • 6 Pages
    Better Essays
  • Powerful Essays

    Shuzworld Analysis

    • 5851 Words
    • 19 Pages

    A. Workflow: Shuzworld produces Rugged Wear Work Boots at its Shanghai production facility using an 8-step process and an assembly line of 8 workstations. Each workstation performs a single task that can range from 3 minutes to 10 minutes to complete, resulting in a total time of 46 minutes to fully assemble one pair of steel-tipped work boots. The facility has a budget to produce 6 work boots an hour, with a 40-hour work week (48 work boots a day). The following table shows the task schedule, along with the time required for each task and predecessor information to complete the 8-step process. The graph shows the current layout of the 8 workstations in the production line:…

    • 5851 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    Tanglewood Case 2

    • 1369 Words
    • 6 Pages

    d. Compute year end totals for each job in Table 1.1 and do a gap analysis to determine where shortages will occur in the next year.…

    • 1369 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    Accounting Sample Exam

    • 2394 Words
    • 14 Pages

    Issued a credit to a customer for the return of a bike. The bike was returned to inventory.…

    • 2394 Words
    • 14 Pages
    Powerful Essays
  • Good Essays

    Southwest Airlines

    • 775 Words
    • 4 Pages

    1. What types of scheduling decisions is management likely to encounter in the following operations? Describe the scheduling decisions in terms of types of resources to be scheduled and the associated customers or jobs scheduled:…

    • 775 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Questions 1, 2, 3, 6, 7, 10, and 12 on page 84.Q1. Classify the following types of processes as continuous, assembly line, batch, job shop, or project:…

    • 1157 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    Microeconomics Wa 3

    • 1924 Words
    • 8 Pages

    In this case, the profit is positive however for perfectly competitive markets in this situation, there will be zero profits in the long-run.…

    • 1924 Words
    • 8 Pages
    Powerful Essays
  • Good Essays

    1. In your own words, describe two main differences between classical and empirical probabilities. The differences between classical and empirical probabilities are that classical assumes that all outcomes are likely to occur, while empirical involves actually physically observing and collecting the information.…

    • 541 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Wescott case study

    • 475 Words
    • 11 Pages

    According to the results, Model A has an overtime work of 2.75 hours if the standard working hours 8 hours. Same goes to Model B & C, both model worked for 2.77 if the standard working hours 8 hours. However, the production in Model D & E are overrun to 2.5 and 3 days which is insufficient.…

    • 475 Words
    • 11 Pages
    Satisfactory Essays
  • Good Essays

    PROJ 586 Final Exam

    • 814 Words
    • 4 Pages

    12. (TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.…

    • 814 Words
    • 4 Pages
    Good Essays
  • Good Essays

    Being a college student in this day in age is never easy. We are always on the move and become stressed very easily. One of the ways students deal with the pressure of ongoing assignments, papers, and various projects is to simply listen to music. Music is very popular to our specific age group, but is consuming different styles of music necessarily a healthy alternate to the stress? How does music affect the heart rate and what different types of music have a greater affect on heart rate? Music most definitely has emotional value. Heart rate can be directly influenced by these emotional changes. Our group decided to test music tempo’s effect on heart rate. This experiment is relevant to one’s health because it is important to understand how to control one’s heart rate. Before we started conducting our experiment, we hypothesized that fast tempo music increases heart rates while slower paced music would keep heart rate at a normal level.…

    • 950 Words
    • 4 Pages
    Good Essays

Related Topics