Preview

Mb0049

Better Essays
Open Document
Open Document
2089 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Mb0049
Q1. Describe the CPM model. Briefly explain.
Ans:
The critical path method (CPM) is an algorithm for scheduling a set of project activities.[1] It is an important tool for effective project management.
The essential technique for using CPM [6] [7] is to construct a model of the project that includes the following: 1. A list of all activities required to complete the project (typically categorized within a work breakdown structure), 2. The time (duration) that each activity will take to completion, and 3. The dependencies between the activities.
Using these values, CPM calculates the longest path of planned activities to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer). In project management, a critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path.
Although the activity-on-arrow diagram ("PERT Chart") is still used in a few places, it has generally been superseded by the activity-on-node diagram, where each activity is shown as a box or node and the arrows represent the logical relationships going from predecessor to successor as shown here in the "Activity-on-node diagram".

Q2. Define risk management. What are the different types of risks that can affect a project?
Ans:
Risk management is the identification, assessment, and

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Good Essays

    Defines all the work required to complete a project successfully, and should ensure that the…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    This project charter shall define the scope, objectives, and overall approach for the work to be completed. It is a critical element for initiating, planning, executing, controlling, and assessing the relocation of Riordan Manufacturing’s China operations from Hangzhou to Shanghai. It should be used as the single point of reference on the relocation for project goals and objectives, scope, organization, estimates, work plan, and budget. In addition, it serves as a contract between the Project Team and the Project Sponsors, stating what will be delivered according to the budget, time constraints, risks, resources, and standards agreed upon for the project.…

    • 695 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project? (3 points)…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    PERT Analysis (CPA) - Helps to plan all tasks that must be completed as part of a project, including scheduling and resource…

    • 4317 Words
    • 18 Pages
    Powerful Essays
  • Satisfactory Essays

    Assignment Preparation

    • 696 Words
    • 4 Pages

    Content: It will breakdown the different task that needs to be done and who will perform the task…

    • 696 Words
    • 4 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    The critical path is added to the appendix of this case report. As shown in Figure 1 and 2, many tasks are correlated so that one critical phase can affect the other. Here, we divided the entire process into three parts: namely by “Detailed Design” part (on the left hand of the network diagram), “Create Functional Requirements (upper side),” and “Development & Unit Test (bottom left side).” Even though, we leveled the resource referring on automated re-allocation methods, except for 7 phases in this project, most of the critical stages remained still critical. These seven stages are “Create data requirements,” “Gather testing requirements,” “Create System Test Plan & Test Cases,”“Write system test scripts,” and on the other part of the network diagram, “Updating and Calculating Shopping Cart,” Submit Order,” “Check Order History & Order Status,” and “Create ERP Interface Requirements.” Considering that most of the leveled tasks are components of “Detailed Design” and “Development & Unit Test,” (tasked that still remained critical, even...…

    • 613 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Mr Mooneys Gay Paper

    • 3412 Words
    • 14 Pages

    This document investigates the features of MS Project 2007 (MSP) using as an example the garage building project from Lock (Lock D. Project Management. 6th edition. Gower 1996).…

    • 3412 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    Before starting this homework assignment, please review the AIB simulation in this week’s Lecture. This simulation will provide you with an understanding of how to create a network diagram, and how to do a forward and backward pass to determine the ES, LS, EF, LF and slack (float). You will also learn how to determine the duration of the project, and the critical path.…

    • 662 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The aim of this report is to present our Project to open a gym in Belas, more specifically in Massamá Norte (for further details see exhibit 1). This new gym, with an area of around 3000 m2 divided in three floors, would offer a broader range of activities when compared to what current competitors offer. Therefore, given the fact that all activities could be found in only one place (e.g. classes, pool, cardio) it would attract customers from the involving area: Massamá, Monte Abraão and Queluz (for further details see exhibit 2).…

    • 325 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    d) What is the cost of competing the project if its duration is what you…

    • 508 Words
    • 3 Pages
    Satisfactory Essays

Related Topics