MEPL SITE 2X350 MW
THAMMINAPATNAP (A.P)
METHOD STATEMENT FOR UNLOADING THE BOILER DRUM FROM TRAILER BY CRAWLER CRANES
Data Protection Statement
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in whole or in part for any purpose whatsoever without the prior written permission from CETHAR LIMITED.
Staff Information Sheet
The following method statement has been developed to provide a safe system of work and must be adhered to at all times, any significant deviation from this system must first be authorised by SITE INCHARGE or SAFETY INCHARGE. Please read the entire sheet before beginning the procedure, if you have any questions please contact SITE INCHARGE or SAFETY INCHARGE
The main hazards to your safety and health are;
a) Failure of cranes
b) Topple of Cranes
c) Failure of tools & tackles
d) Over Load
e) Injury from incorrect Manual handling.
f) Injury from slips/trips and falls.
g) Injury from the incorrect actions of other contractors on site.
h) Injury to members of the public during operations.
Preventative Measures
a) PTW will be issued
b) Unloading Incharge will be made and he will be having all control over unloading activity.
c) TBT will be conducted.
d) Area will be barricaded.
e) Trained Crew shall be engaged for unloading the drum. The unloading plan will be shared with working crew.
f) Proper Tag lines will be tied.
g) Proper padding will be done to all WRS from sharp edges.
h) Only authorised person will be allowed
i) Proper compactness & level of the ground will be done
j) Signal will be given by the competent person with flags.
Personal Protective Equipment
a) Safety Goggles
b) Safety Helmet
c) High Visibility Vest
d) Safety Shoe
e) Hand gloves
Task Description of Boiler Drum Unloading.
a) Drum lay down area will beis already leveled, and compacted and checked as per requirement. MEPL & CETHAR