Preview

Ms Project Lesson 7

Good Essays
Open Document
Open Document
3323 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Ms Project Lesson 7
Objectives - MS Project 2010

* Track the actual progress of tasks * Updating a Project * Compare baseline data to actual and scheduled data * Viewing a Network Diagram * Earned Value Overview

Once the project starts, it's time to begin tracking the actual progress of tasks and resources. Tracking is the process of gathering and entering task information into the schedule. You can track progress by entering all or some of the actual information.

In the previous lesson, we complete our scheduling and resource assignments. For this lesson, we will assume our project is underway and that several tasks have either finished or are partially finished. We will then determine if our project is behind or ahead of schedule.

Tracking Progress

Before we can begin tracking progress, the project schedule should be fully developed and a baseline plan should be set. Once work begins, progress should be tracked throughout the project. The more often we update the information, the easier it is to identify problems and take corrective action.

When actual information is entered, the project is automatically recalculated. For this reason, task progress should be entered starting at the top of the task list and continuing down the list.

There are three types of dates stored for each task:

Scheduled: Tasks that haven't started yet or are in progress.
Actual: Tasks that are in progress or are completed.
Baseline: Originally planned dates. These dates are used to compare the original plan with the actual dates and scheduled dates. Baseline dates do not change.

There are five types of actual data that can be entered in MS Project:

Actual start and finish dates
Percentage completion
Actual duration and remaining duration
Actual and remaining work
Actual and remaining costs

Our project was scheduled to begin on October 9 2013 and end on November 26, 2013. For the purposes of this lesson, we will assume that it is

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Earned Value Analysis

    • 511 Words
    • 3 Pages

    As for the actual project expenditure know as the actual cost of the present time. This can be obtained through the business financial cost accounting systems. This includes all the costs that go along with all the work that has been completed on the project up to the present instant time. For the actual project progress also known as earned value which is what's planned at the beginning for the expenditures to the work that is completed up to the present time.…

    • 511 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Critical Path Method

    • 894 Words
    • 4 Pages

    From the work breakdown structure, a listing can be made of all the activities in the project. This listing can be used as the basis for adding sequence and duration information in later steps.…

    • 894 Words
    • 4 Pages
    Good Essays
  • Good Essays

    A) According to Valacich, George and Hoffer (2009), project management is an important aspect of the design of information systems and a crucial skill for a system analyst. The purpose of project management is to make sure that system development projects achieve consumer demands and are distributed within budget and also time constraints.FastTrack is software that helps projects managers to plan and manage project more effectively. It illustrates in a colorful way progress, assignments and progress goals. One of the most important features to project development is that this software allows entering activities with specific dates (start date, finish date); the activities can be…

    • 962 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Woody2000 Case Study

    • 740 Words
    • 3 Pages

    Identify and describe a set of project schedule milestones from project concept to project completion.…

    • 740 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Please check on your calendar that Project one is due beginning from October 30, 2010…

    • 396 Words
    • 2 Pages
    Good Essays
  • Powerful Essays

    For instance, at the initial level, there will not be any clarity for managers about the project as there are no proper tracking and estimates done in the project. In the next level, the basic project management activities are taken care and the requirements from the customers and the work progress are captured in a systematic manner. As the level the project increases, there will be more clarity in the project; both the managers and the engineers will understand their roles and responsibilities. The accurate status and the work progress of the project can be obtained very easily. As the project grows to the next level, the accuracy and the success rates become high as the visibility into the project becomes high. The risk areas are identified in prior and appropriate measures are taken to rectify…

    • 1461 Words
    • 6 Pages
    Powerful Essays
  • Satisfactory Essays

    REVIEW PROBLEMS

    • 729 Words
    • 10 Pages

    COMM 225: POM REVIEW PROBLEMS – TUTORIAL QUESTIONS Week Q1 (Ref: Q. 9-23, p413 of (Operation management: creating value along the Supply Chain)): The following table provides the information necessary to construct a project network and project crash data: Activity a b c d e f g h Predecessor a a b b c d, e Normal Times (Weeks) 16 14 8 5 4 6 10 15…

    • 729 Words
    • 10 Pages
    Satisfactory Essays
  • Powerful Essays

    Every projects aim to reach their goals on schedule without any delays. As a project manager, one main responsibility is to ensure keeping the project as scheduled. This becomes a reason that time management takes an important part as one of the nine areas in the Project Management. Failed to manage it properly, it would not be able to carry on as planned. There are many aspects to be concerned in the time management, such as; define activities, add sequences in all activities, estimate activity resources, estimate activity duration, develop schedule and control schedule. All of these sections run an important role to accomplish the time management. However, every part of development plans and actions will be futile without controlled, especially when there is a changing occurs in the on-going project. Upon that schedule control is necessary to determine the time management within a project.…

    • 2173 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Report on Communication

    • 3537 Words
    • 15 Pages

    Once the project plan gets approved the manager should save it as a baseline plan. For a project there can be saved multiple baselines depending on the project size and how often the project plan changes. Ideally, once the project baseline is created it should not be changed anymore. However, it is sometimes inevitable to adjust it due to a new requirement that implies a major change to scope or cost. Also in rare cases the project was not well scheduled in the initial phase. In these cases the best solution is to keep the initial baseline and to save the adjusted schedule as a new baseline. This way there will be several interim baselines that can be used to remember the potentially bad project management or the team members that did not deliver as promised.…

    • 3537 Words
    • 15 Pages
    Powerful Essays
  • Satisfactory Essays

    Our second task is to complete our Summary of Proposal. And we completed this task within 10 days. We started doing this January 13, 2014 and finished it January 23, 2014. Under our Summary of Proposal are 6 specific tasks. First is our System Title, and we completed this task for 1 day (Jan-13). Next is Proponent/s of the System, and we completed this task for 2 days (Jan-14 – Jan-15). Next is Description of the System, and we completed this task for 2 days (Jan-16 – Jan-17). Next is Project Scope and Limitation, and we completed this task for 2 days (Jan-18 – Jan-19). Next is System Cost, and we completed this task for 2 days (Jan-20 – Jan-21). And lastly is Timeframe, and we completed this task for 2 days…

    • 952 Words
    • 4 Pages
    Satisfactory Essays
  • Powerful Essays

    7CPM1 071130199 TMA2 Marked

    • 6848 Words
    • 20 Pages

    In order to meet the goal in the stage 2, Project Manager has to create a system to measure the progress. In this case, I will name it as Planning or Work Programme to measure the progress. With this system either using Microsoft Project, Primavera and others suitable system, Project Manager will being able to measured, monitoring and know what’s the status of the project right now.…

    • 6848 Words
    • 20 Pages
    Powerful Essays
  • Powerful Essays

    This should contain a brief summary of the thesis project. It is composed of a single paragraph of 200 to 300 words and should include the overview of the problem, the project design and the results of the thesis project.…

    • 760 Words
    • 4 Pages
    Powerful Essays
  • Powerful Essays

    On the other entity of our course completion, hence are finalized with our Project Report…

    • 4619 Words
    • 19 Pages
    Powerful Essays
  • Powerful Essays

    Project management

    • 10285 Words
    • 42 Pages

    Each project is composed of a series of jobs or tasks that must all be completed before we can say, “We finished the project.” These tasks are referred to as the “activities” of a project.…

    • 10285 Words
    • 42 Pages
    Powerful Essays
  • Good Essays

    Insightly: An Analysis

    • 1107 Words
    • 5 Pages

    Project management features include task, pipeline and email tracking; detailed project reporting (such as daily progress reports); automatic deadline reminders via email; and the ability to create and measure milestones. It is also possible to link projects to contacts and team members for fast, easy reference.…

    • 1107 Words
    • 5 Pages
    Good Essays