CASE: MAKING NORWICH TOOLS LATHE
INVESTMENT DECISIONS
PAR T A:
PAYBACK PERIOD
years
cash flows 0
1
2
3
4
5
(660,000)
128,000
182,000
166,000
168,000
450,000
PBPA
LATHE A cumulative cash flows cash flows LATHE B cumulative cash flows 128,000
310,000
476,000
644,000
1,094,000
(360,000)
88,000
120,000
96,000
86,000
207,000
88,000
208,000
304,000
390,000
597,000
4.04
PBPB
3.65
ACCEPTABILTY OF EACH PROJECT:
Lathe A will be rejected because it¶s payback period is longer than 4 years maximum expected payback period
4.04years > 4years
Lathe B project is accepted because it payback period is less than the 4 year maximum payback period 3.65years < 4 years
----------------------------------------
PART B:
NPV &IRR
LATHE A NPV & IRR years 0
1
2
3
4
5
cash flow
(660,000)
128,000
182,000
166,000
168,000
450,000
cash flows
(360,000)
88,000
120,000
96,000
86,000
207,000
LATHE B NPV & IRR
PV Factor
@13%
1
0.885
0.783
0.693
0.613
0.543
PV Factor @13%
1
0.885
0.783
0.693
0.613
0.543
PV
(660,000)
113,274
142,533
115,046
103,038
244,242
PV
(360,000)
77,876
93,978
66,533
52,745
112,351
NPVA
58,133
NPVB
43,483
IRRA
16%
IRRB
17%
ACCEPTABILTY OF EACH PROJECT:
Under the NPV calculations both projects are acceptable because NPV of both project is positive or we can say greater than zero. y y
NPV LATHE A:
NPV LATHE B:
58,133 >
43,483 >
0
0
Lathe A has a larger NPV than B so it is preferable.
IRRs of both projects are greater than the 13% cost of capital so both project are acceptable.
However, 17% IRR for B is greater than the 16% IRR for lathe A so it is B is preferable.
---------------------------------------
PART 3:
SUMMARY:
LATHE A
LATHE B
PBP
4.04 years
3.65 years
NPV
58,133
43,483
IRR
16%
17%
Both projects have positive NPVs and IRRs above