In order to make the system, the programmers should have the knowledge on Java and MS SQL. A knowledge in connecting JDBC to MS SQL to have a database for the data needed to input. A Computer in which only the manager will only have the access. We also need to have Java Software and MS SQL. Internet connection is a must to get aid from some hard coding.
Schedule Feasibility As we planned for our work breakdown structure, we’ve noticed that time is very limited for us thus making all the activities in the critical path. Days we’re spread evenly for us to do every activity effectively. Some of the activities which weigh less have less time some of them are even done with other activity at the same time, again in order to complete the project in the limited amount of time.
Work Breakdown Structure
By Sequential Timeline
Pert CPM Task Name | Duration | Start | Finish | Coming up with the proposal | 7 days | Wednesday, Nov 7, 2012 | Wednesday, Nov 14, 2012 | Choosing a Company | 7 days | Wednesday, Nov 7, 2012 | Wednesday, Nov 14, 2012 | Approval for service | 7 days | Thursday, Nov 15, 2012 | Thursday, Nov 22, 2012 | Data Gathering | 14 days | Friday, Nov 23, 2012 | Friday, Dec 7, 2012 | Analysis for Service | 14 days | Saturday, Dec 1, 2012 | Saturday, Dec 15, 2012 | Solution and Alternatives | 14 days | Saturday, Dec 1, 2012 | Saturday, Dec 15, 2012 | System Benefit Analysis | 7 days | Saturday, Dec 8, 2012 | Saturday, Dec 15, 2012 | Estimate Resources | 7 days | Monday, Dec 17, 2012 | Monday, Dec 24, 2012 | Program Coding | 28 days | Tuesday, Dec 25, 2012 | Tuesday, Jan 22, 2013 | Program Debugging | 14 days | Wednesday, Jan 23, 2013 | Wednesday, February 6, 2013 | Program Implementation | 14 days | Thursday, February 7,2013 | Thursday, Feb 28, 2013 | Final Revision | 14 days | Friday, March 1, 2013 | Tuesday, March 15, 2013