DESIGN BUILD PROJECT SCOPE

PROJECT INTRODUCTION

Background
Penny Store is a franchise of convenience stores which will be opening their new store in Kitchener, Ontario. Penny Store will be the first 24-hour convenience store that is more like an big dispensing machine than the traditional store.
The store is to be built in space of 3200 sq. feet. The store expects to capture market share by becoming the low-cost leader in the convenience store industry by reducing labour expanses. Because of fully automated shopping experience, customers have the chance of shopping every item at reduced price. The store is opening
…show more content…
Performance scores from previous work: The criteria for determining the performance score would be based on quality of work done by contractor in previous projects and will get following points:
10 or more-year experience: 15 points
5 to 10-year experience: 10 points
1 to 5-year experience: 5 points

2. Bid Price: the contractor’s bid price with respect to client’s price will be evaluated as:
Same as client’s price- 10 points
5% to 10% more than client’s price- 2 points
1% to 5% more than client’s price- 8 points

3. Technical: The contractor must fulfill all the technical requirements required for the project and experienced to perform them for the completion of the project.

4. Qualification: Based on the experience of contractor’s team will be awarded 5 points. This also involve other factors which indicates which team is
…show more content…
The project should not exceed its timeline without the permission of the project manager and client.
3. Construction sites will be limited to the smallest feasible area. Ground disturbance and site management Should be carefully controlled to prevent undue damage to community and prevent noise pollution. Staging is limited in or near the construction area for a construction office or trailer. If used (provided by the contractor), all temporary water, sewer, sanitary facilities and electric utilities, shall be completely removed upon project completion.
4. Submission must be limited to an executive summary, not more than 25 pages of text.
5. Construction zones shall be fenced to avoid any damage to the community.
6. Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area.
7. Proponents may be required to make a presentation and to be interviewed by selection team.
8. Documents can be prepared in either metric or imperial measure.
9. The information submitted by proponents will be used to evaluate capabilities and qualifications of the team.
10. The working hours for the project will be 7 am to 6 pm, Monday to Saturday. Some occasional work on Sundays will be

You May Also Find These Documents Helpful

  • Better Essays

    Jc Penny

    • 1009 Words
    • 5 Pages

    J.C. Penny is creating a new interface for retail, offering new boutiques in the store. Today there are 17 shops. In the future there will be a 100 shops. This should aid in appealing to a diverse set of customers by essentially creating a “mall within a mall”. (JCP Online, 2013)…

    • 1009 Words
    • 5 Pages
    Better Essays
  • Good Essays

    Planning effective messages may not be as difficult when the managers opened their first four stores. Hence working in the stores each day, the managers personally trained the employees and assisted the customers in finding the right tools and supplies for their projects and deal directly with every suppliers. The company uses…

    • 567 Words
    • 2 Pages
    Good Essays
  • Satisfactory Essays

    Proj586 Course Project

    • 735 Words
    • 3 Pages

    Grading Rubrics Week Week 1 Deliverables a. Review course project b. Review MS Project tutorials a. Create Project Charter (15 points) b. Create Scope Statement (15 points) c. WBS (15 points) a. Create project schedule and align resources in MS Project (35 points) Total % Points Alignment 0 points 0% (not Graded) 45 points 75 points 18%…

    • 735 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    bubbaganoosh

    • 515 Words
    • 3 Pages

    Urban Constructions has several policies, procedures and practices in place to protect the client, suppliers, our staff and our contractors. Limitations placed upon our team can restrict the project to what it will produce. To make this subdivision successful, we must follow these procedures.…

    • 515 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Request for Proposals

    • 26335 Words
    • 106 Pages

    SECTION 1 2 3 4 5 INTRODUCTION RFP SCHEDULE OF EVENTS PROPOSAL REQUIREMENTS GENERAL REQUIREMENTS & CONTRACTING INFORMATION PROPOSAL EVALUATION & CONTRACT AWARD…

    • 26335 Words
    • 106 Pages
    Powerful Essays
  • Powerful Essays

    Hnc Forms of Construction

    • 3301 Words
    • 14 Pages

    Contents 1.0 Introduction 2.0 Methodology 3.0 Inception 4.0 Feasibility 4.1 Overview of stage 4.2 Assessing the feasibility 4.3 Site investigation 4.4 Effects on design 5.0 Then brief 5.1 Overview of stage 5.2 What the brief should cover 5.3 What the brief should include 5.4 Consultants at this stage 6.0 The concept/outline proposals 6.1 Overview of stage 6.2 Requirements to proceed with concept design 6.3 Developing the brief into concept design 6.4 Planning permission 6.5 Building regulations approval 6.6 Achieved at this point 7.0 The design development 7.1 Overview of stage 7.2 Developing the design 7.3 Finalisation of design 7.4 Planning proposal 7.5 Building regulations 7.6 Sampling and testing 7.7 Health and Safety 7.8 Achieved at this stage 8.0 Technical design 8.1 Overview of stage 8.2 Implications on design 9.0 Production phase 9.1 Overview of stage 9.2 Design implications 10 Other construction projects…

    • 3301 Words
    • 14 Pages
    Powerful Essays
  • Better Essays

    To weigh each criteria group, the team members assigned each group a score. More important groups were given a score of 10, less important groups a score of 6 to 9, the least important groups a score of 5 or less. Criteria that were scored at 6 or higher were used to assess each project and criteria of 5 or lower were reserved for further ranking later in the process. Criteria are weighted in order to help place the projects in order of importance as they are aligned with the goals of the company (Kloppenborg, 2009, p. 36).…

    • 1019 Words
    • 5 Pages
    Better Essays
  • Good Essays

    The Applicant, JBCC Development, LLC is the contract purchaser of a development site (the “Site”) consisting of 1.82 acres at 2295, 2277, 2257, 2247, and 2237 Fruitville Road and 2268, 2260, 2252, and 2234 2nd Street and a 15’ Alley Vacated Per O.R. Book 2034, PG 1979. The site is zoned Downtown Core (DTC) and is located north of Fruitville Road between North Lime Street and 3rd Street. The proposed development will consist of 5,636 sq.ft. of retail space (convenience store) and Quick Vehicle Serving (Full Service Gas Station) with six (6) gas pumps covered by a 4,582 sq.ft canopy. As there will be three (3) access points, where two (2) will be from 2nd Street, which is a local road. Additionally, there will be a right-in and right-out access point involves Fruitville Road, which is a major arterial. Currently, the site consists of vacant land, single-family unit, variety of commercial uses such as automotive sales, auto repair shop, and retail. However, in redeveloping the subject site, the existing buildings will be demolished. In concert with improving the subject…

    • 1035 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    In my adventure to find the right store for this assignment, I solicited the assistance of my neighbor. My neighbor, Edith Yarbor and her husband Larry own a convenience store in Agua Prieta, located in the northern region of Sonota, Mexico so this was the venue of choice for me to observe for a few hours.…

    • 413 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Project management

    • 1280 Words
    • 7 Pages

    This task provides evidence for grading criterion P3. (discuss the resources required to complete a construction project)…

    • 1280 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    Task 1 P7: Explain the implications of environmental issues and legislative constraints on this type of construction development.…

    • 1227 Words
    • 5 Pages
    Good Essays
  • Best Essays

    Final Strategic Plan

    • 2391 Words
    • 10 Pages

    To provide the lowest prices along with giving customers a retail shopping experience in convenient size stores for ease of shopping. Obtain financial growth with community involvement. Maintain high quality customer service and employee interaction.…

    • 2391 Words
    • 10 Pages
    Best Essays
  • Good Essays

    The company's relationship with contractors is predominately transactional in nature where construction work is tendered and bid on a competitive basis. Work is primarily awarded based on lowest cost with some consideration for…

    • 612 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    • temporary structure erected on proposed locations to identify the actual site of construction must be respected;…

    • 419 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    A convenience store can be more responsive by doing exactly what Seven-Eleven Japan is doing; many locations, rapid replenishment, appropriate technology deployment, and an equally responsive supplier (vertical integration for many of their SKUs). The risks associated with this system are the costs coupled with demand uncertainty. If demand patterns change dramatically, or the customer base changes, then Seven-Eleven is left with an operation that is not needed. Offering variety of services in the case of this case study Seven Eleven offered attractive services to customers such as ski lift voucher pass, payment of mail order purchases, internet shopping, a meal service delivery, automatic teller machines installation in each store, pick up online services, electronic money service that allow customers to prepay and use a card or cell phone to make payments etc. on the other hand, a short coming might result due to the failure of one or more information system due to failure or break down.…

    • 2117 Words
    • 9 Pages
    Powerful Essays