I followed up with Evan at Top Notch regarding the doors, he said that he is hoping they will be done on Monday and Nick M. can bring them up when he comes on Tuesday.
I met with each of the subs today and discussed the areas that need Fire Caulking.
Powers Excavating - Tyler worked today on back filling and compacting the ground around the meters pits next to building B. He also worked grading and leveling out that section, and removing excess dirt.
Mountain
West Mechanical - Justin and his guys continued working on getting building A prepared to for a 4-way inspections.
AgraTec - Harold and his guys continued working on installing the 1st floor windows in building A&B.
Mechanical Inspector - Wyatt came out and inspected the mechanical(ducted work, gas lines, radiant tubing etc.) in building A. Everything passed except the gas inline, We were still getting leaks in that line. Justin is going to work on trying to get it fixed on Monday, then we will call in for another inspection.
Hedgehog - Glen and his guys continued working on doing the rough electrical in building B.
Arrow Leaf - Nick came by, and we discussed elevations of the storm tech system etc. He is going to be getting me some measurements we can pull from, so we can set the treatment Man hole.