Preview

Pert

Satisfactory Essays
Open Document
Open Document
292 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Pert
Q2 Planning and control–Critical Path Method (CPM) & Progamme Evaluation and Review Technique (PERT)
Explain what is meant by the Critical Path Method (CPM) and the Programme Evaluation and Review Technique (PERT), as used in project planning and control?
Department A is performing a system upgrade project with the following tasks, duration and task dependency relationships.
Critical Path Method (CPM)
The critical path method (CPM) is a step-by-step technique for process planning that defines critical and non-critical tasks with the goal of avoid time-frame problems and process bottlenecks. The CPM is ideally suited to projects consisting of many activities that interact in a complex method.

Programme evaluation and review technique (PERT)
The programme evaluation and review technique, or PERT as it is universally known, had its origins in planning and controlling major defence projects in the US Navy. PERT had its most spectacular gains in the highly uncertain environment of space and defence projects. The technique know that activity period and costs in project management are not decision and that probability theory can be applied to estimates, as was mentioned earlier. In this type of network each activity period is estimated on an optimistic, a most likely and a pessimistic basis.

CPM and PERT are project planning and control.
5
5
4
4
2
2 2 3
1
1 1
Start
6
6
3
3
2 1 End 1 the project duration is 9 days
Task 1,2,4,5,6 are critical path. Task 3 is not in critical path , If task 3 delayed for 2 days will be no effect in the critical path.
If crash project schedule to 8 days, we have to employ labor and over time to work in the

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    First Cars Ltd

    • 1031 Words
    • 5 Pages

    Critical path analysis is a method that is used to plan out the many activities involved in a project to be able to find the most efficient way of complete it and how to complete it on time.…

    • 1031 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    The project staff analysed with basis in a series of factors like training staff, adequate to legislative requirements, measuring risks, availability of the budget and quality standards to set a timeline. Once every step is scheduled, the whole staff can work with a estimated and real parameter of timeline.…

    • 3773 Words
    • 12 Pages
    Powerful Essays
  • Satisfactory Essays

    LF – EF or LST – EST Activities on the critical path have zero slack/float. b. What is the Scheduled Completion of the Project? 22 Days c. What is the Critical Path of the Project?…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Introduction to Project Scheduling IX. The Critical Path Method (CPM) X. Program Evaluation and Review Technique (PERT) XI. Project “Crashing”…

    • 5350 Words
    • 1 Page
    Satisfactory Essays
  • Good Essays

    Pert Mustang

    • 1016 Words
    • 5 Pages

    1. Using the information provided, prepare the report that Roberts requested, assuming that the project will begin immediately. Assume 45 working days are available to complete the project, including transporting the car to Detroit before the auto show begins. Your report should briefly discuss the aspects of the proposed new business, such as the competitive priorities that Roberts asked about.…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    The Critical Path is the Shortest Time in which the Project Can Be Completed. Any delay in Critical Path activities delays the project. Critical Path Activities have no slack time Variability in Activity Times: CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a Probability Distribution for Activity Times to allow for Variability.…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Pert Mustang

    • 2682 Words
    • 11 Pages

    construct a network diagram for a project determine critical path and expected completion time of a project with deterministic task times (note: some of us also do calculations for probabilistic times, but not required) calculate slack times for a particular task know how to “crash” a project down to a certain completion time at the lowest cost (note: just the concept of crashing needs to be discussed and not the calculations; some of us do the calculations, others do not)…

    • 2682 Words
    • 11 Pages
    Powerful Essays
  • Satisfactory Essays

    Phase 4 DB

    • 379 Words
    • 1 Page

    Critical Path Method (CPM) is yet another tool for the project manager to use to organize, plan, and control the development of a project. It calculates the longest path to get to the end of a project and tells which activities are critical. It ca be used for projects of any size and illustrates the dependencies between scheduled activities. However, it does not tell you anything about the resources or where they fit into the project.…

    • 379 Words
    • 1 Page
    Satisfactory Essays
  • Better Essays

    After the project has been planned it is time to begin executing the project lifecycle. At this point, the project manager integrates two groups of project management processes. Some of these processes are classified as “executing” and some are classified as “monitor and control”. This plan focuses on the “executing” project management processes. It has seven main steps.…

    • 1106 Words
    • 5 Pages
    Better Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Powerful Essays

    Robert C. Martin 5 October 2003 Some time in the late 60's my father brought home a book that he thought I'd be interested in. The title was Introduction to Operations Research by Frederick S. Hillier and Gerald J. Lieberman, Holden-Day, 1967. I was probably 15 or 16 years old. The book languished on my shelves for perhaps ten years. Then, as a young software professional, I pulled the book down and ,thumbing through its pages, I noticed a chapter on PERT. I had heard of PERT as a method of project management, so I started to read and learn. Since those days in the early 80's I have seen dozens of examples of PERT charts, and tools for drawing PERT charts. They always make me cringe. Invariably these charts a tools missed the nd fundamental principle of PERT that made it such a successful technique: the management of probabilities. PERT (Program Evaluation and Review Technique) was developed in 1958 to help measure and control the progress of the Polaris Fleet Ballistic Missile program. The technique earned considerable respect for assisting in the management of thousands of different contractors and agencies, and is credited with helping to advance the completion date of the program by two years.…

    • 1998 Words
    • 8 Pages
    Powerful Essays
  • Good Essays

    What is a critical path, and why is it important to project managers? How do you…

    • 702 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    A&D HIGH TECH

    • 263 Words
    • 2 Pages

    What is the critical path in the project? How would you assess the level of risk in the project?…

    • 263 Words
    • 2 Pages
    Satisfactory Essays