Piping Tecnnology in Shipbuilding
A REPORT ON

PIPING TECHNOLOGY IN SHIPBUILDING
BY

Ravi Gupta

2009A4PS229P

AT Chowgule & Company Ltd. “Shipbuilding Division” A Practice School-I Station of BIRLA INSTITUTE OF TECHNOLOGY & SCIENCE, PILANI (11th July, 2011)

A REPORT ON

PIPING TECHNOLOGY IN SHIPBUILDING
BY Ravi Gupta B.E.(Hons)Mechanical 2009A4PS229P

Prepared in partial fulfillment of the Practice School-I Course: BITS C221 AT CHOWGULE AND CO. LIMITED (SHIPBUILDING DIVISION) GOA A Practice School-I Station of BIRLA INSTITUTE OF TECHNOLOGY & SCIENCE, PILANI (11th July, 2011)

BIRLA INSTITUTE OF TECHNOLOGY & SCIENCE PILANI (RAJASTHAN) Practice School Division

BIRLA INSTITUTE OF TECHNOLOGY & SCIENCE PILANI (RAJASTHAN) Practice School Division

Station: Chowgule & Company Ltd. “Shipbuilding Division” Centre: GOA Duration: 53 Days Date of Start: 23rd May, 2011

Date of Submission: 11th July 2011 Title of the Project: Use of Piping Systems & Technology in Shipbuilding Name and Designation of the experts: Mr. Hemant Kadkake (Head Production Division) Mr. Vishwanath Hanagi (Sr. Officer Production Division) Mr. M.S. Motankar (General Manager) Name of the PS Faculty: Dr. N.N.Ghosh

Signature of Student Date:

Signature of PS Faculty Date:

ACKNOWLEDGEMENTS

Preparation of this report on the technical aspects of Chowgule Industries saw the combined efforts of the three of us (Sauvik Dutta 2009B4A4552P, Ravi Gupta 2009A4PS229P and Emdo Gain 2009A2PS491P) coupled with all the help and support we received from all the people we would like to thank. First of all we would like to thank The Dean, Practice School Division, Dr. P. Srinivasan for the course Practice School 1 which is the primary reason that we got exposure to industrial working environment.

We express deep gratitude towards our instructor- in-charge Dr. Narendra Nath Ghosh for his constant help and guidance at Chowgule and Co. Limited. We would also like to thank Manager, HR department, Mr. Sachin Malvankar

You May Also Find These Documents Helpful

  • Powerful Essays

    Industrial Engineering Department, Faculty of Engineering, University of Indonesia, Depok 16424, Indonesia E-mail: surjandari.2@osu.edu, a_citra_s@yahoo.com…

    • 2113 Words
    • 9 Pages
    Powerful Essays
  • Powerful Essays

    Career Episode

    • 4424 Words
    • 18 Pages

    CAREER EPISODE No.1 PIRANHA HANGAR BASE CONSTRUCTION PROJECT Place in Colombia INTRODUCTION 1. This first episode is based on my experience as Project and Quality control Manager for the project related to th construction of two piranha hangar base. This project was executed by XXX, the Company which I worked for, and the Contractor was the ZZZ. This construction project took place from August 2004 to August 2005. BACKGROUND 2. The main scope of this project was to build two hangar bases for “piranha” motor boats. These hangar bases provided different facilities to military personnel that need some support during their military operations and each one had fuel storage and supply facilities, warehouse, dinning and temporary housing facilities .Thus, it was necessary to build a potable water system, sanitary system, fuel storage and distribution system, air conditioning system, bilge and ballast system, electrical network, including generator set. Hull, deck and roof structure were built on steel structure with different specs and coating schema. Each piranha hangar base weighted 209 tons and had two storeys. 3. The Hull was composed by five pontoons each one of 8 meters length x 1.20 meters width x1.5 meters depth and a main section of 24 meters length x 3.5 meters width x 1.5 meters depth. Each pontoon had a specific function, pontoon number 3 was designed for sewage system, pontoon five was used for ballast system and included sea box. Inside other pontoons there were installed pipe lines for fuel, sanitary, electrical, bilge and ballast system. Hull main section was designed to fuel and…

    • 4424 Words
    • 18 Pages
    Powerful Essays
  • Powerful Essays

    VLCC

    • 14368 Words
    • 53 Pages

    First of all, we would like to express our deepest appreciation and thanks to all those who involve in completing this report. A special gratitude we give to our Ship and Offshore Production Technology lecture, Dr. Jaswar Koto for his contribution in stimulating suggestions, comments and encouragement to help us to coordinate this research study especially in writing this report. Without his help, this report entitled Production Process of Very Large Crude Carrier (VLCC) cannot be completed. Furthermore, we would also like to acknowledge with much appreciation to the staff of Perpustakaan Sultanah Zanariah, who gave fully assistant and necessary materials to complete this task. Special thanks go to our team mate members who give their fully commitment and efforts in achieving the goal in this research. Last but not least, many thanks go to friends who give an excellent cooperation and supported us to complete this research study.…

    • 14368 Words
    • 53 Pages
    Powerful Essays
  • Powerful Essays

    6.2 Operational and implementation information for successful and unsuccessful inspection can be of significant benefit for re-inspections.…

    • 6383 Words
    • 26 Pages
    Powerful Essays
  • Powerful Essays

    Business at Tuticorin Port

    • 1723 Words
    • 7 Pages

    The Port is equipped with 7 along side berths and two coal jetty and one oil jetty. Out of this one along side berth is licensed to M/s PSA Corporation during the year 1998. The port also having a shallow draught berth to facilitate small vessels with 6 m draft. All other berths are having a draft of 8.24 m to 10.7 m.…

    • 1723 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Electrosteel ITO

    • 862 Words
    • 5 Pages

    Well planned manufacturing, production and finishing line: Setting up a plant in Kardah, near Kolkata offer them infrastructure support of the existing CIP and the services of the existing staff. It also provides simplified Management control and engineering support.…

    • 862 Words
    • 5 Pages
    Satisfactory Essays
  • Powerful Essays

    Due to this historic prosperous background and also a natural geo-graphical advantage, there are presently more than 200 shipbuilding and repairing yards in Bangladesh. Among them, I visited two ship yards, ASSL and WMS, which are the most modern and largest shipyards in Bangladesh. My first impression was that both of them are well organized in terms of production and assembly flow lines, and that the facilities (welding, steel cutting and design office software etc) and their size (up to about 10,000 ton) were better than I had expected.…

    • 1805 Words
    • 8 Pages
    Powerful Essays
  • Powerful Essays

    / 文件号/Doc. No.: 2301-01-0-02 2301-01-0-02 01-0-0 : 船 厂/ Shipyard: DAI DUONG JOINT STOCK COMPANY, YIETNAM…

    • 1376 Words
    • 6 Pages
    Powerful Essays
  • Good Essays

    Institution of Naval Architects, Proceedings of the Symposium on the Design, Construction and Operation of…

    • 5765 Words
    • 24 Pages
    Good Essays
  • Powerful Essays

    Assignment Financial

    • 2316 Words
    • 13 Pages

    Sapura Kencana provides a full range of construction and engineering services required for the O&G industry, from detailed engineering design to construction. They also focused on the fabrication, building and upgrading of uniforms, vessels, jackets, topsides and other O&G facilities. Engineering works include initial conceptualizations, process simulations, studies, development and analysis to enhance solutions, computer run-throughs and 3-dimensional modelling, as well as multi-discipline detailed engineering designs. With the attainment of Clough Limited’s marine construction division, they are also have the capability to provide extensive engineering services encompassing conceptual, front end engineering design and detailed design for projects in deep-water and difficult environments. There are four asset of Sapura Kencana which is fabrication and HUC,…

    • 2316 Words
    • 13 Pages
    Powerful Essays
  • Powerful Essays

    bsi standards

    • 5885 Words
    • 24 Pages

    BS 3551:1962 BRITISH STANDARD Incorporating amendment issued August 1963 (PD 4964) Specification for Alloy steel shackles --`,,``,,````````,,,``,,,`,``,``-`-`,,`,,`,`,,`--- [UDC 621.885.7:669.15]…

    • 5885 Words
    • 24 Pages
    Powerful Essays
  • Satisfactory Essays

    Ched

    • 433 Words
    • 2 Pages

    SUBJECT: IMPLEMENTING RULES AND REGULATIONS FOR THE IMPLEMENTATION OF THE BRIDGING PROGRAM FOR THE BS MECHANICAL ENGINEERING (BSME) AND THE BS ELECTRICAL ENGINEERING (BSEE) TO BS MARINE ENGINEERING (BSMARE) PROGRAM…

    • 433 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Furkaan

    • 3837 Words
    • 16 Pages

    26th IEEEP Students’ Seminar 2011 Pakistan Navy Engineering College National University of Sciences & Technology…

    • 3837 Words
    • 16 Pages
    Powerful Essays
  • Good Essays

    Requirements

    • 1157 Words
    • 5 Pages

    Requirement engineering is the first and crucial phase in the development of software. The main aim of the requirements engineering process is gathering of requirements. It involves set of activities like system feasibility study, analysis, validation and management of the requirements. There are many methods already exist to perform the requirements gathering process and the software developers apply…

    • 1157 Words
    • 5 Pages
    Good Essays
  • Good Essays

    theses

    • 743 Words
    • 3 Pages

    LEVEL OF SATISFACTION OF 1st BSMT STUDENTS IN THE ENROLLMENT PROCESS FOR THE SCHOOL YEAR 2014-2015…

    • 743 Words
    • 3 Pages
    Good Essays