Preview

Prepare to Formal

Satisfactory Essays
Open Document
Open Document
264 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Prepare to Formal
DATE: November 9, 200x
TO: Mark Edelstein, President
FROM: Darmisha Pierson, Development Officer
SUBJECT: Progress Report on Construction of Seattle Branch Office

Construction of Vintage Realtys Seattle Branch Office has entered Phase three. Although we are 1 week behind the contractors original schedule the building should be already for occupancie on March 10.

Past Progress

Phaze one involved development of the architects plans, this process was completed onJune 5. Phaze two involved submission of the plan’s for county building department approval. Each of the plans were then given to the following 2 contractors for the purpose of eliciting estimates, David Gray Construction, and Millennium Builders. The lowest bidder was David Gray Construction, consequently this firm began construction on July 15.

Present Status

Phase three includes initial construction processes. We have completed the following steps as of November 9:

• Demolition of existing building at 11485 NW 27 Avenue
• Excavation of foundation footings for the building and for the surrounding wall
• Steel reinforcing rods installed in building pad and wall
• Pouring of concrete foundation

David Gray Construction indicated that he was 1 week behind schedule for these reasons. The building inspectors required more steel reinforcement then was showed on the architects blueprints. In addition excavation of the footings required more time then the contractor anticipated because the 18 inch footings were all below grade.

Future Schedule

In spite of the fact that we lost time in Phase 3 we are substantially on target for the completion of this office building by March 1. Phase 4 include the following activities, framing drywalling and installation of

You May Also Find These Documents Helpful

  • Powerful Essays

    Nt1330 Unit 6 Paper

    • 579 Words
    • 3 Pages

    The Custom woodworking Company has been in the custom furniture business since the early 1950’s. Since their inception they have grown their business and reputation steadily. This growth has demonstrated a need for the company to expand its existing factory floor space. Therefore, the companies stakeholders have agreed to expand the existing property by adding “additional production capacity equivalent to 25% of the existing floor space” (Wideman). Moreover, the floor space would contain “air-conditioning, a dust-free paint and finishing shop, an automatic wood working production train, as well renovated offices for the President and Executive Vice President” (Wideman). The total renovation costs have been outlined not to exceed…

    • 579 Words
    • 3 Pages
    Powerful Essays
  • Satisfactory Essays

    project will start the week of January 16, 2017. Property owners at 1763 Subtropic Drive…

    • 650 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Course Project Charter

    • 567 Words
    • 3 Pages

    2. The architect selection, real estate selection needs to be completed by April 1, 2011…

    • 567 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    construction, but the end of the last phase, the building was 82 meters square and approximately…

    • 1694 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    GB560 Unit 6 PaigeHarward

    • 1135 Words
    • 4 Pages

    The next stage would include project planning. This is the stage in which the team would establish a detailed project plan and would navigate from the existing plan and lead to an end result. This part of the process would include creating a chart indicating what changes are being made and help the team see the flow of the “As-Is” process and the “To-Be” process.…

    • 1135 Words
    • 4 Pages
    Good Essays
  • Best Essays

    In 1987, the trustee of a property trust employed CDG Pty Ltd (the first respondent) to design the foundations of a commercial building. The second respondent was a civil engineer employed by the first respondent and was its project manager in relation to the complex’s design and construction.…

    • 2813 Words
    • 10 Pages
    Best Essays
  • Powerful Essays

    The MW-1 2003 Contract was developed and published by the Royal Australian Institute of Architects (RAIA) and the Master Builders Association (MBA). This contract is the revised edition of the original ABIC MW-1 2001 contract…

    • 2001 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    This project is to provide a build out of a dental office in Los Angeles. It requires as existing building with new interior infrastructure, negotiations with the Southern Central City of Los Angeles, and coordination with various building contractors, electricians, and supply vendors.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Hnc Forms of Construction

    • 3301 Words
    • 14 Pages

    Contents 1.0 Introduction 2.0 Methodology 3.0 Inception 4.0 Feasibility 4.1 Overview of stage 4.2 Assessing the feasibility 4.3 Site investigation 4.4 Effects on design 5.0 Then brief 5.1 Overview of stage 5.2 What the brief should cover 5.3 What the brief should include 5.4 Consultants at this stage 6.0 The concept/outline proposals 6.1 Overview of stage 6.2 Requirements to proceed with concept design 6.3 Developing the brief into concept design 6.4 Planning permission 6.5 Building regulations approval 6.6 Achieved at this point 7.0 The design development 7.1 Overview of stage 7.2 Developing the design 7.3 Finalisation of design 7.4 Planning proposal 7.5 Building regulations 7.6 Sampling and testing 7.7 Health and Safety 7.8 Achieved at this stage 8.0 Technical design 8.1 Overview of stage 8.2 Implications on design 9.0 Production phase 9.1 Overview of stage 9.2 Design implications 10 Other construction projects…

    • 3301 Words
    • 14 Pages
    Powerful Essays
  • Satisfactory Essays

    The phases deination/scope and consultant supplier section were completed by the second week of the project. 5% complete…

    • 606 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Merv investigated the situation and submitted a confidential document, on the First High School this was in February 1999. The performances to date of Meyerhoff, the main contractor and Stewart and Sons, the architectural firm, were critically evaluated. The major findings were that Stewart and Sons failed to control the scheduling properly and that it was making an unusually large profit for its administrative function. Merv was familiar with Stewart & Sons and was able to write about their methods of execution. The school board asked Stewart and Sons to renegotiate because of the findings of the report, but gave them the impression that it was based on the construction delays. The content of the report remained undisclosed. After two months of very difficult negotiation, all groups signed an amended contract on June 30, 1999. All major issues were settled and they were able to proceed to the construction of the second high school.…

    • 561 Words
    • 3 Pages
    Good Essays
  • Better Essays

    | The project is estimated to take approximately five months after groundbreaking. The Czopeks are willing to have the project delayed in order to save costs.…

    • 3547 Words
    • 12 Pages
    Better Essays
  • Satisfactory Essays

    Research Paper

    • 3695 Words
    • 15 Pages

    Part A includes four steps to complete, which will become your main post in Unit 3:…

    • 3695 Words
    • 15 Pages
    Satisfactory Essays
  • Powerful Essays

    information that was gathered during the prior 3 phases. Upon completion, the next sub activity…

    • 1463 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    * Stage 4 – Maintaining Social Order – at this stage the focus is on following…

    • 2611 Words
    • 11 Pages
    Powerful Essays