Learning Tasks: |
SECTION A: Short Answer Questions | 1. What major information would you expect to find in a project review? * Classification of the project—e.g., large/small, platform/incremental, complex/ typical * Analysis of information gathered * Recommendations * Lessons learned * An appendix with backup information to support recommendations. 2. Why is it difficult to perform a truly independent, objective review?In most cases those performing the review have some previous knowledge of the project, which presents opportunities for bias. Sometimes the review team, or facilitator, is perceived as a jury, but even jury members come with built-in biases. For example, internal politics have been known to enter into decisions concerning closure of a project. The simple point is that every attempt should be made to keep the review independent and objective. If the review of projects is a regular procedure for all projects, the negative stigma of audits is minimized. 3. Why should you separate performance