PROJECT CONSTRUCTION PLANNING
PROJECT CONSTRUCTION PLANNING: CONSTRUCTION OF A CONCRETE BRIDGE

Contents TOC \o "1-3" \h \z \u Overview PAGEREF _Toc364683901 \h 3Details PAGEREF _Toc364683902 \h 3Critical path analysis PAGEREF _Toc364683903 \h 5Planning assumptions PAGEREF _Toc364683904 \h 5Analysis PAGEREF _Toc364683905 \h 5Diagram analysis PAGEREF _Toc364683906 \h 5

Overview
The aim of this task is to provide project management services for the construction of a concrete bridge for a motorway project. A list of activities, an elevation and section of the proposed bridge has been provided which must be used for the project plan.
A critical path analysis will be undertaken to produce a network diagram showing the earliest and late times and a total float for each activity. This will help to provide the following criteria:
Critical activities
Completion time of project A second analysis will be undertaken to determine how the project duration can be reduced in order that recommendation can be made to the contractor.
DetailsThe following figure gives general details regarding the proposed scheme and the table 1 show the list of activities. Table1-List of activities and required resources
Activity Duration
Site strip – complete bridge
Pier A
Excavate pier
Blinding to pier
Fix reinforcement & formwork to kicker
Concrete pier foundation
Reinforcement to abutment
Fix formwork
Concrete abutment
Strip Formwork
Deck slab (piers A to B)
Fix precast concrete beams
Fix formwork to deck
Fabricate and fix reinforcement
Concrete deck
Strip formwork to deck
Curing period prior to striking formwork 4 days
3 days
1 day
3 days **
1 day
4 days
5 days
1 day
2 days
**repeat activities on deck between piers B and C
1 day
5 days **
3 days
1 day
2 days
7 days
** repeat activities on deck between piers B and C
The following resources of temporary works and plant are to be allocated for the bridge construction.
One hydraulic excavator
One pier shutter

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) 30 days b) Identify the critical path (6 points) BCDFH = 30 Days c) What is the slack time (float) for activity A? (1 points)…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    bubbaganoosh

    • 515 Words
    • 3 Pages

    Limitations that impact on what a project can produce are project constraints. Scope, time and cost are the three essential constraints that create these limitations. For this subdivision project is has been estimated that the cost will be $128, 596 with a duration of 110 days. This is for the chosen option of retaining and renting the existing house and selling the vacant subdivided land.…

    • 515 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Plan

    • 2003 Words
    • 7 Pages

    Our company Wireless Software Inc. is an innovative Internet-based company with gross revenues of more than $35 million dollars per year. Our company will be merging with a multinational company Skyguard Software Inc. of equal size, as a result of merging it produced Navitech Software Inc and we will be responsible for developing a project plan to strategically integrate all systems, including databases and infrastructure. Navitech Software Inc. global enterprise operations would provide best software products that will benefit to both companies. This report presents recommendations that allow Navitech Software Inc. to remain successful for years to come. The network design must keep pace with the new techniques and applications and let organizations increase revenue reduce operational costs and communicate more effectively with customers.…

    • 2003 Words
    • 7 Pages
    Powerful Essays
  • Better Essays

    Project Planning

    • 1632 Words
    • 7 Pages

    Georgia Lazenby believes a current liability is a debtthat can be expected to be paid in one year. Is Georgiacorrect? Explain.…

    • 1632 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    One way to consider resources is to take them into account when drawing the logical relationships among activities in the network diagram. In addition to showing the technical constraints among activities, the network logic can also take into account resource constraints. The sequence of activities can be drawn to reflect the limited availability of a number of resources. If resources are to be considered in planning, it’s necessary to indicate the amounts and types of resources needed to perform each activity. For this reason, a resource profile is often developed.…

    • 2049 Words
    • 9 Pages
    Powerful Essays
  • Satisfactory Essays

    Individual Project 2

    • 251 Words
    • 2 Pages

    Scheduling is essential to a project’s success. Forming a network activity with a visual depiction helps the team understand the relationships of tasks in a project. Two of the most common charts used in project management are the Gantt and PERT charts. The purpose of these charts is to assist with project scheduling and illustrate task dependencies. Another tool that can be used is the critical path method (CPM).…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Blue Zuma Part 2

    • 310 Words
    • 2 Pages

    By allocating the additional and available resources, we were able to reduce the amount of critical paths to one. In doing so, we increase the slack in non-critical activities, thus reducing or decreasing the sensitivity of the network. One critical path is now identified in…

    • 310 Words
    • 2 Pages
    Good Essays
  • Better Essays

    project planing

    • 970 Words
    • 4 Pages

    predicted. Investors respond to new information by buying and selling such that prices reflect what is known. The speed with which investors act and prices respond reflects the efficiency of the market…

    • 970 Words
    • 4 Pages
    Better Essays
  • Good Essays

    The purpose of accelerated bridge construction is to ensure the project planning, procurement, and logistics approach are modified to ensure tasks with long lead times, traditionally completed onsite, are of highest priority and completed using creative solutions. Multiple scenarios require the need for accelerated bridge construction technologies; where a bridge is being constructed or reconstructed over an existing roadway in use, where a bridge is being reconstructed or replaced for an existing roadway currently in use. Accelerated bridge construction technologies aid in the construction of the required infrastructure while minimizing or limiting the distribution of traffic. Where the impact upon traffic is a concern, relocation of roadway…

    • 400 Words
    • 2 Pages
    Good Essays
  • Good Essays

    D.U Singer Hospital

    • 5200 Words
    • 21 Pages

    Question 1: Construct the nine elements of the plan identified................................................. 4 i. ii. iii. iv. v. Statement of Objectives.................................................................................................. 4 Work Breakdown Structure............................................................................................. 5 An activity on node (PERT) network ........................................................................... 6 A determination of the critical path(s) and the duration along the path. ..................... 7 An activity list, early-start schedule, slack list and master schedule. Assume every…

    • 5200 Words
    • 21 Pages
    Good Essays
  • Satisfactory Essays

    2.4 What type of bond guarantees that if a contractor goes broke on a project the surety will pay the necessary amount to complete the job?…

    • 735 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Steel Structure Construction

    • 5481 Words
    • 22 Pages

    Strength Pre engineered steel buildings are stable, resistant and possess intensely hard material strength. The primary structural component of a steel building is steel, a metal alloy of soft iron and carbon. The carbon content in steel determines its degree of hardness or softness of the alloy. Steel is one of the most extensively used alloys that have found one more usage in the sphere of building and construction. As an alloy its profitable quality can be attributed to its tenacity, structural strength and unparalleled resistance to corrosion, rusting and other general deterioration.…

    • 5481 Words
    • 22 Pages
    Good Essays
  • Powerful Essays

    Statment of Purpose

    • 531 Words
    • 3 Pages

    Specification Clause & Method Statement Galvashield XP Embedded Galvanic Anodes for corrosion prevention in concrete rehabilitation SECTION 03700 – EMBEDDED GALVANIC ANODES PART 1 GENERAL 1.01 Related Documents A. Drawings and general provisions as received from the Consultant drawing: ‘Galcashield XP+’ 1.02 Summary A. This item includes furnishing all labor, tools, materials, equipment and services necessary to properly install embedded galvanic anodes. B.…

    • 531 Words
    • 3 Pages
    Powerful Essays
  • Better Essays

    Prestressed Concrete

    • 2901 Words
    • 12 Pages

    Bonded post-tensioned concrete is the descriptive term for a method of applying compression after pouring concrete and the curing process (in situ). The concrete is cast around a plastic,…

    • 2901 Words
    • 12 Pages
    Better Essays