Overview
The aim of this task is to provide project management services for the construction of a concrete bridge for a motorway project. A list of activities, an elevation and section of the proposed bridge has been provided which must be used for the project plan.
A critical path analysis will be undertaken to produce a network diagram showing the earliest and late times and a total float for each activity. This will help to provide the following criteria:
Critical activities
Completion time of project A second analysis will be undertaken to determine how the project duration can be reduced in order that recommendation can be made to the contractor.
DetailsThe following figure gives general details regarding the proposed scheme and the table 1 show the list of activities. Table1-List of activities and required resources
Activity Duration
Site strip – complete bridge
Pier A
Excavate pier
Blinding to pier
Fix reinforcement & formwork to kicker
Concrete pier foundation
Reinforcement to abutment
Fix formwork
Concrete abutment
Strip Formwork
Deck slab (piers A to B)
Fix precast concrete beams
Fix formwork to deck
Fabricate and fix reinforcement
Concrete deck
Strip formwork to deck
Curing period prior to striking formwork 4 days
3 days
1 day
3 days **
1 day
4 days
5 days
1 day
2 days
**repeat activities on deck between piers B and C
1 day
5 days **
3 days
1 day
2 days
7 days
** repeat activities on deck between piers B and C
The following resources of temporary works and plant are to be allocated for the bridge construction.
One hydraulic excavator
One pier shutter