Preview

Project Management

Good Essays
Open Document
Open Document
963 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management
SIM335 Managing Project essay
SIM335 Managing Projects - Task 1
Question 1: Network diagram (activity on node)
‘The network diagram is defined as a graphical presentation of the project’s activities shows the planned sequence of work’ Burke (2003, p.131). It is also called as precedence diagramming method (PDM). ‘It is a method of constructing a project schedule network diagram that uses boxes or rectangles, which referred to as nodes, to represent activities and connects them with arrows that show the dependencies’ The Project Management Book of knowledge (PMBOK) (2004, p. 132). The network diagram (Appendix 1.0) has been drawn out accordingly to the table 1 for Jashol Ltd in order to show activities and period it takes to customise luxury cars for its customers.
Question 2: Determine timing of activities and total floats
To determine the timing of activity A to activity R are using forward and backward pass through the network diagram (Appendix 1). A forward pass is begin from the left to the right which is using the earliest start time(EST) and earliest finish time(EFT) of each activity. While, backward pass is using the activity latest start time(LST), latest finish time(LFT) and total float(TF) that are proceed from right to left. Meanwhile, duration is presented in the activity data. The calculation of timing for each activity has been drawn out clearly in a table form (Appendix 1.1).
Question 3: Determine the project duration and critical paths
The duration for the project is 70 days for completion, which is using LST to add up together with the duration of the activity. PMBOK (2004, p.145) defines critical paths have either a zero or negative total float. Therefore, for the critical paths of this project are activity A→B→F→G→J→K→N→O→Q→R (Task 1 - Appendix 1.0 and 1.2). The zero float showed in the activities are indicate as the critical path or critical activities.
Question 4: The earliest date to complete the project
If the project starts on 5th

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    Determine each of the following: Task Earliest Start Latest Start Earliest Finish Latest Finish Slack A 0 6.5 3 9.5 6.5 B 0 0 7 7 0 CRITICAL C 3 9.5 7.5 14 6.5 D 7 7.5 18.5 19 0.5…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Proj586

    • 1206 Words
    • 5 Pages

    The following data were obtained from a project to create a new portable electronic. Activity Duration Predecessors A 5 Days --- B 6 Days --- C 8 Days --- D 4 Days A, B E 3 Days C F 5 Days D G 5 Days E, F H 9 Days D I 12 Days G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project?…

    • 1206 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 5 Days --- B 8 Days --- C 6 Days A D 4 Days C, B E 5 Days A F 4 Days D, E, G G 4 Days B, C H 3 Day G Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Problem 3 The following data were obtained from a project to design a new software package: Activity Duration Predecessors A 3 Days --- B 6 Days --- C 4 Days A D 2 Days C, B E 3 Days A F 2 Days D, E, G G 2 Days B, C H 1 Day G a. Construct a network for the project.…

    • 562 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    4) Refer to the figure. What is the slack time, in days, associated with activity D?…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Satisfactory Essays

    Aib Problem Solution

    • 608 Words
    • 3 Pages

    Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) What is the Scheduled Completion of the Project? (2 points) 32 -> CORRECT b) What is the Critical Path of the Project? (3 points)…

    • 608 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    TPV1 Sample Questions

    • 453 Words
    • 3 Pages

    Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies?…

    • 453 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    Project Management Activities: Planning-Objectives Resources Work Break-down Structure Organization Scheduling- Project Activities, Start & End Times, Activity Network Controlling-Monitor, Compare, Revise, Action Work Breakdown Structure: WBS is a hierarchical decomposition of the project into phases, deliverables and work packages. 1.Project 2. Major Tasks in the project 3. Subtasks in the major tasks 4.Activities (or “work packages”) to be completed Project Controlling: Close monitoring of Resources, Costs, Quality, Budgets. Feedback enables revising the Project Plan and Shift Resources. Computerized tools produce extensive reports Six Steps PERT & CPM: 1. Define the Project and prepare the Work Breakdown Structure 2. Develop relationships among the activities - decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 4. Assign Time and/or Cost Estimates to each activity 5. Compute the longest time path through the network – this is called the Critical Path 6. Use the network to help Plan, Schedule, Monitor, and Control the project Perform a Critical Path Analysis: The Critical Path is the Longest Path Through the Network…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    Individual Project 2

    • 251 Words
    • 2 Pages

    Scheduling is essential to a project’s success. Forming a network activity with a visual depiction helps the team understand the relationships of tasks in a project. Two of the most common charts used in project management are the Gantt and PERT charts. The purpose of these charts is to assist with project scheduling and illustrate task dependencies. Another tool that can be used is the critical path method (CPM).…

    • 251 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Inflation in Srilanka

    • 697 Words
    • 3 Pages

    Given the following network with activity times in months, determine the earliest and latest activity start times and slack for each…

    • 697 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    -Diagram of project activities that shows sequential relationships by the use of arrows and nodes.…

    • 1126 Words
    • 5 Pages
    Powerful Essays
  • Powerful Essays

    Fvbff

    • 2478 Words
    • 10 Pages

    The regional electrical utility company, South West Electrical, needs a network to be designed and implemented. The…

    • 2478 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    Epm Tools&Techniques

    • 3552 Words
    • 15 Pages

    Acitivity Advertising Registration Invitation Crew uniform Referee Sport equip Table/chair Stall for rent Canopy Stage Security/car park Medic F&B Prize Audio Sys P = Primary S=Secondry Haf iz P Ver ra P P P P P P P P P P P P P P Sujat ha Mari na Jam al Seri na Muv en Name Kuma rez Kal ai Fadzl ee Ro sli Badr ul Sa m Ali as Jo e…

    • 3552 Words
    • 15 Pages
    Powerful Essays
  • Powerful Essays

    Network diagrams are schematic displays of project schedule activities and the interdependencies between these activities. When developed properly, this graphical view of a project’s activities conveys critical schedule characteristics required to effectively analyze and adjust schedules – thus resulting in accurate and feasible schedules. This document addresses what should be considered in the development of a network diagram, how network diagrams are created, and how they may be analyzed to identify necessary corrective actions and ensure optimal schedule definition.…

    • 1565 Words
    • 7 Pages
    Powerful Essays