Preview

Project Management

Satisfactory Essays
Open Document
Open Document
1179 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management
|

Project Name: | Concept Coffee Shop | Project Description Summary | This project is to provide an on campus coffee shop to the students of DeVry University. It requires changes in current building interior, negotiations with DeVry University, and coordination with a variety of contractors, vendors and suppliers. | Project Manager: | Date: | August 11, 2013 | Revision Number: | 1 |

a. Risk Identification:
I have made a list of all areas of this project that may cause delays or failure with their outcomes (listed below). The key risks for this project are identified by bolded font below and appear in the Risk Assessment Table in question “b”

1) Inclement weather-- could cause construction and opening day delays.
2) Lack of student interest in hiring process—could delay hiring process and opening day.
3) Delay in building permit and license approvals—could delay construction.
4) Over budgeting—could impact quality of equipment and supplies
5) Delay in delivery of equipment and supplies—could delay first preview
6) Delay in delivery of inventory—could delay second preview
7) Negative feedback during testing phase--could delay advertising.
8) Health and building inspections failure—could delay construction start date
9) General contractor not devoting enough time to project—could delay construction end date
10) Communication issues—could cause deviations from project goals and stakeholders’ vision.

b. Risk Assessment
The following is an assessment of project risks in terms of probability of occurrence and their negative impact on project outcomes. The below risk analysis attempts to quantify the severity of the impact of the previously identified risks, their probability and their sensitivity to change.

RISK SCORING MATRIX

Defined conditions for Risk Management Analysis | ProjectObjective | Relative or Numerical Scale | | Very Low - 1 | Low – 2 | Moderate - 3 | High – 4 | Very High - 5 | Cost | Insignificant

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Is3110 Week2 Assignment

    • 348 Words
    • 2 Pages

    estimate the risks associated with this project. They want you to provide a high level summary of…

    • 348 Words
    • 2 Pages
    Satisfactory Essays
  • Powerful Essays

    Pm595 Course Project

    • 2651 Words
    • 11 Pages

    Cited: Sources of risks in construction projects may be classified as follows (PM Book, 2012):…

    • 2651 Words
    • 11 Pages
    Powerful Essays
  • Better Essays

    Mgmt404 Project Plan

    • 1494 Words
    • 6 Pages

    I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen…

    • 1494 Words
    • 6 Pages
    Better Essays
  • Satisfactory Essays

    We identified several risks and have assessed them in order to determine which of those risks have the highest impact on the project. Below we have listed four of our highest impact risks and have supplied a recommendation for that risk:…

    • 1116 Words
    • 5 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Pm 535 You Decide

    • 585 Words
    • 3 Pages

    * Capture previous projects and study their history of risk matrix and match both to see if you are following the right procedures or decreasing risk factors…

    • 585 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    Risk Identification I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen as key risks are bolded below and appear in the Risk Assessment Table.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Good Essays

    4. Infection control & OSHA – the lack of not being complaint with the State codes and regulations can cause the project on the on halt due to the safety of contractors’ workers. This would prolong the inspection process until up to city code.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Good Essays

    IT 205 final assignment

    • 1253 Words
    • 6 Pages

    • What factors that influence project risk? What strategies would you recommend for minimizing this project’s risks?…

    • 1253 Words
    • 6 Pages
    Good Essays
  • Better Essays

    Proj595 Risk Paper

    • 1690 Words
    • 7 Pages

    Cited: Cooper, D. F., Grey, S., Raymond, G., & Walker, P. (2005). Project Risk Management Guidelines:…

    • 1690 Words
    • 7 Pages
    Better Essays
  • Powerful Essays

    Project Management

    • 1515 Words
    • 7 Pages

    Construct a Cost-Benefit Analysis matrix for an organization that is considering replacing its internal payroll system with a payroll outsourcing service. Include direct and indirect revenue enhancements and direct and indirect cost reductions.…

    • 1515 Words
    • 7 Pages
    Powerful Essays
  • Good Essays

    New Heritage Doll Company

    • 591 Words
    • 3 Pages

    Project poses moderate risk – about the same as the production division’s existing business as a whole.…

    • 591 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Project Management

    • 5162 Words
    • 21 Pages

    This project is needed to build a process of developing and documenting a project management plan by the team .The plan will be capable to lead the team finish up the whole project that satisfy all the requirements by the customers.…

    • 5162 Words
    • 21 Pages
    Good Essays
  • Powerful Essays

    Typically, a project's qualitative risk assessment will recognize some risks whose occurrence is so likely or whose consequences are so serious that further quantitative analysis is warranted. A key purpose of quantitative risk analysis is to combine the effects of the various identified and assessed risk events into an overall project risk estimate. This overall assessment of risks can be used by the transportation agency to make go/no-go decisions about a project. It can help agencies view projects from the contractor's perspective through a better understanding of the contractor's risks. More commonly, the overall risk assessment is used to determine cost and schedule contingency values and to quantify individual impacts of high-risk events. The ultimate purpose of quantitative analysis, however, is not only to compute numerical risk values but also to provide a basis for evaluating the effectiveness of risk management or risk allocation strategies.…

    • 4164 Words
    • 17 Pages
    Powerful Essays
  • Satisfactory Essays

    Homework: choose four classic mistakes for each group: people, process, project, technology, and explain how you can defeat each of them.…

    • 337 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    artificial intelligence

    • 499 Words
    • 2 Pages

    2. Lack of experience and technical skills that leads to low quality of building construction.…

    • 499 Words
    • 2 Pages
    Satisfactory Essays

Related Topics