Preview

Project Management Chapter 4 Q7

Satisfactory Essays
Open Document
Open Document
427 Words
Grammar
Grammar
Plagiarism
Plagiarism
Writing
Writing
Score
Score
Project Management Chapter 4 Q7
Question 3 (35 marks) - Words: 2 – 2.5 Pages

The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, time, and sequences required;

Activity
Immediate Predecessor
Time (Weeks)
A
--
3
B
A
2
C
A
4
D
A
4
E
B
6
F
C,D
6
G
D,F
2
H
D
3
I
E,G,H
3

a. Draw the network diagram.
b. What is the critical path?
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B,C,D and G each one week. Which would you shorten?
d. What is the new critical path and earliest completion time?

Question 3a

Question 3b
From the above project network, five possible paths found in that project as below table:
Path number
Path Details
Time required (Per Week)
1
A > B > E > I
3 + 2 + 6 + 3 = 14
2
A > C > F > G > I
3 + 4 + 6 + 2 + 3 = 18
3
A > D > F > G > I
3 + 4 + 6 + 2 + 3 = 18
4
A > D > G > I
3 + 4 + 2 + 3 = 12
5
A > D > H > I
3 + 4 + 3 + 3 = 13

As the duration of path 2(ACFGI) and 3(ADFGI) need 18 weeks to complete the project which is longest time, so the path 2 and 3 are critical path.

Question 3c
As the activity B does not located on critical path, therefore the completion time no change even its shorten one week. For the activity G which is located on both critical path 2(ACFGI) and 3(ADFGI), therefore it is key activity for the project and has to shorten. Due to activity C and D is location on critical path 2(ACFGI) and 3(ADFGI) respectively, if only shorten activity C or D then another one become critical path, therefore both activity C and D have to shorten one week at same time. Conclusion, I would choose activity C, D and G to shorten the completion time as above reasons.

Question 3d
The new critical path is (ACFGI) or (ADFGI) and the earliest completion time is 16 weeks. Although the path 2 and 3 has same result as no need to consider the additional cost for shorten related activity, in realty

You May Also Find These Documents Helpful

  • Good Essays

    -2- 6. The critical path of a project network is the: a. shortest time path through the network. b. path with the fewest activities. c. path with the most activities. d. longest time path throught the network.…

    • 882 Words
    • 8 Pages
    Good Essays
  • Satisfactory Essays

    QAT1 Task 4

    • 501 Words
    • 7 Pages

    E 7.5 14 12.5 19 6.5 F 7 7 17 17 0 CRITICAL G 17 17 23.5 23.5 0 CRITICAL H 18.5 19 29.5 30 0.5 I 23.5 23.5 30 30 0 CRITICAL J 30 30 33.5 33.5 0 CRITICAL a. Duration of project: 33.5 weeks b. Slack for task A: 6.5 weeks c. Slack for task H: 0.5 weeks d. Task F scheduled start: week 7 e. Task I scheduled completion: week 30 4.…

    • 501 Words
    • 7 Pages
    Satisfactory Essays
  • Satisfactory Essays

    CMGT 410 Week 4 Resources

    • 508 Words
    • 3 Pages

    Gantt diagram showing duration estimates for all tasks and their sequencing (including precedence relations) and highlighting any critical path(s) arising from task dependencies ultimately determining the minimal duration of a project…

    • 508 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The following data were obtained from a project to build a pressure vessel: Activity Duration Predecessors A 6 weeks --- B 6 weeks --- C 5 weeks B D 4 weeks A, C E 5 weeks B F 7 weeks D, E, G G 4 weeks B H 8 weeks F I 5 weeks G J 3 week I Step 1: Construct a network diagram for the project. Step 2: Answer the following questions: (15 points total) a) Calculate the scheduled completion time. (5 points) b) Identify the critical path (6 points) c)…

    • 556 Words
    • 3 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Huffman Trucking Benefits

    • 278 Words
    • 2 Pages

    The Critical Path Method will indicate the longest path of planned to the end of the project. It is a very good tool to use because it will give the Project Manager a good idea of what tasks that must be completed on time in order for the project to continue smoothly. This method is commonly used in the development of new…

    • 278 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    Our text book mentioned some of the critical success factors when scheduling. Some of these factors are when attempting to reduce the duration of a path activities that has a negative slack, focus on activities that are near term and activities that have long estimated duration, the person who will be responsible for performing the activity should approximate duration for that activity, the key to effective schedule control is address any paths with negative or deteriorating slack values aggressively as soon as they are identified, and activity estimated duration should be yet realistic (Gido & Clements, 5th Ed, pg 180). Based on the factors above, the schedule should be revised to find activities with negative slack and timing interval. For example, recruiting & training, create building design estimated duration time could be adjusted to shorter period. This will cause the earliest start and earliest finish time of other activities around these tasks to be adjusted and hence it might create some positive slack time. The Gantt chat also reveals that during the…

    • 611 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Huntsville Project

    • 758 Words
    • 4 Pages

    Of the five tasks identified, four of these tasks are along our critical path and attribute to 60 weeks or a little more than a year. If we were able to reduce tasks along the critical path by 30% it would provide us an extra 18 weeks or four-and-a-half months to complete the schedule. According to our current schedule we are exceeding our schedule by two-and-a-half months. I am proposing that we reduce all of the aforementioned items by a total of 10% will save us two-and-a-half months on our schedule and should provide adequate time to complete the project in the specified time.…

    • 758 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    ____ 6. A(n) ________ path for a project is the series of activities that determine the earliest time by which the project…

    • 2493 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Red Zuma Project

    • 402 Words
    • 2 Pages

    5. The total duration to complete the project changed and actually increased after resource leveling and made the completion later than the original…

    • 402 Words
    • 2 Pages
    Good Essays
  • Good Essays

    mis 302

    • 1114 Words
    • 5 Pages

    The Critical Path is the Shortest Time in which the Project Can Be Completed. Any delay in Critical Path activities delays the project. Critical Path Activities have no slack time Variability in Activity Times: CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a Probability Distribution for Activity Times to allow for Variability.…

    • 1114 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    The critical activities are B, C, E, F, H, J and K. The project should be completed (earliest finish) in 43 weeks - therefore R.C. Coleman’s 40 week completion time cannot be achieved. The probability of R.C. Coleman meeting the 40 week deadline is ~10%. This is a low chance, so they should be cautioned if they make 40 weeks their deadline.…

    • 656 Words
    • 3 Pages
    Powerful Essays
  • Good Essays

    A&D High Tech (A)

    • 613 Words
    • 3 Pages

    3. What is (are) the critical path(s) in the project? What is the level of risk in completing tasks on the critical path(s)? Explain.…

    • 613 Words
    • 3 Pages
    Good Essays
  • Good Essays

    Mean, Median, Mode

    • 1046 Words
    • 5 Pages

    (13 + 18 + 13 + 14 + 13 + 16 + 14 + 21 + 13) ÷ 9 = 15…

    • 1046 Words
    • 5 Pages
    Good Essays
  • Good Essays

    The network diagram display logical relationships among the various activities that take place within a project. It also allows the project manager to see how the various activities flow towards to…

    • 576 Words
    • 3 Pages
    Good Essays
  • Satisfactory Essays

    Ch 4 Test Bank Simplex

    • 1908 Words
    • 25 Pages

    We introduce x4, x5, and x6 as slack variables for the respective functional constraints. The augmented form of the problem then is…

    • 1908 Words
    • 25 Pages
    Satisfactory Essays