Project Management-Chapter 8 Review Questions
Project management-Chapter 8 review questions

1. How does resource scheduling tie to project priority?

-resource scheduling is directly tied to the project priority, because of the amount of available resources. The resources available will automatically go towards the project with the highest priority assigned by the organization’s objectives.

2. How does resource scheduling reduce flexibility in managing projects?

-Resource scheduling will reduce the flexibility because the scheduling system will reduce slack in increasing the number of critical and near-critical activities.

3. Present six reasons scheduling resources is an important task. o It allows the project manager check to see if the resource is adequate and to assess the availability of resource. o It allows the PM to consider possible alternatives for limited resources o It allows multiple projects to be worked on at the same time, even if they are utilizing some or all of the same resources needed. o It allows PM’s to see how much flexibility they have with managing certain resources. o Will help see if the project is assigned a realistic time line o It will allow the PM to see which resources have priority

4. How can outsourcing project work alleviate the three most common problems associated with multiproject resource scheduling?

- Outsourcing is a great way to improve the utilization of limited resources and make sure the project is running smoothly and efficiently and reduce bottlenecks.

5. Explain the risks associated with leveling resources, compressing or crashing projects, and imposed durations or “catch-up” as the project is being implemented.

- The risks associated with leveling resources, compressing or crashing projects, and imposed durations are if flexibility is decreased and the risk of project delay is increased.
6. Why is it critical to develop a time- phased baseline?

- It is important to develop a time-phased budget because they are critical

You May Also Find These Documents Helpful

  • Satisfactory Essays

    Unit 421 Unit 7

    • 686 Words
    • 3 Pages

    of such resource loading and develop a more leveled schedule. This forms your Exercise 2 for this week.…

    • 686 Words
    • 3 Pages
    Satisfactory Essays
  • Better Essays

    Mgmt404 Project Plan

    • 1494 Words
    • 6 Pages

    I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen…

    • 1494 Words
    • 6 Pages
    Better Essays
  • Satisfactory Essays

    CMGT 410 week 5

    • 308 Words
    • 2 Pages

    Enables project manager to analyze the findings of the review and improve on certain aspects in the next project that need attention.…

    • 308 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    How do the five major variables of project management-scope, time, cost, quality, and risk – relate to this scenario?…

    • 1016 Words
    • 5 Pages
    Good Essays
  • Satisfactory Essays

    An increased resources and materials can cause issues that will affect the project severely if not monitored and addressed in time. The probability may be low, but can change due to several economic and/or political issues that may arise. If such an event happens, it can easily have a ripple effect throughout the project. It can cause the budget to be derailed, which can cause the project be put on hold until more affordable materials can be acquired, or the project as a whole not come to completion. To address this issue, the budget and the economic situation must be closely monitored.…

    • 362 Words
    • 2 Pages
    Satisfactory Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    Risk Identification I have made a list of all areas that might cause project delays or failure with their respective outcomes (see numerical list below). The five risks I have chosen as key risks are bolded below and appear in the Risk Assessment Table.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    Cost and Schedule are the most important elements of a successful project management. The USAMMA Scheduling & Cost Controls offers methods…

    • 1428 Words
    • 6 Pages
    Powerful Essays
  • Powerful Essays

    Brs Mdm3 Tif Ch07

    • 2550 Words
    • 19 Pages

    7) Refer to the figure. Suppose that additional resources are provided to crash the project completion time below its expected normal completion time. Which activities would be potential…

    • 2550 Words
    • 19 Pages
    Powerful Essays
  • Good Essays

    My partners and I have made a list of areas that might cause the project delays or failure with their respective outcomes. We have listed the risk below that can prevent the project to finish on time.…

    • 1078 Words
    • 5 Pages
    Good Essays
  • Powerful Essays

    Business Case

    • 2402 Words
    • 10 Pages

    Intelligent Imaging Solutions (IIS) is a public corporation that is headquartered in Dallas, TX, that competes in the global market for consumer navigation systems (GPS) and in the military defense industry. Their organization consists of two divisions. The first division produces products for consumers and the second division produces products for the military. For consumer products Intelligent…

    • 2402 Words
    • 10 Pages
    Powerful Essays
  • Powerful Essays

    Tegan Hrad Write Up

    • 3041 Words
    • 13 Pages

    Outsourcing has seemed to acquire a rise in popularity and usage in our modern times. Outsourcing involves entering into a contract in which an in-house company process, or processes, is ultimately handed over and dealt with from a third party’s perspective. I would have to say that there are three primary, helpful factors to outsourcing, especially when it comes to the world of business. To start off, the cost of operations can be trimmed down through outsourcing. This, in turn, would assist a corporation or business in accumulating more lucrativeness. Secondly, every organization out there has the intention of delivering top-of-the-line services and goods. Outsourcing can contribute to more efficient deliveries. Specifically concerning information technology or something that would be considered to be a bit more technical, outsourcing can bolster efficiency within that particular field of a technical nature. Thus, productivity would be improved through outsourcing. Thirdly and lastly, within a set interval of time, an establishment has the ability through outsourcing to complete projects promptly. This is due to the fact that while a third party is handling a certain progression of a certain company, that individual company can now use its human capital and employees – that may originally were going to have to deal with a peculiar development stage of a certain project which has now been outsourced – in other, more beneficial ways. More labor can be put into other areas.…

    • 3041 Words
    • 13 Pages
    Powerful Essays
  • Better Essays

    Working to understand the risks a project may endure along with the cost associated is critical in every project management plan. Understanding potential risks based on the project type, resources needed, timeline and budget still leaves gaps that creates uncertainty for actually predicating the outcome of the project. There is not a true way to predict when and where a project risk will occur but designing a plan to properly address and manage those risks will increase confidence while eliminating the element of surprise.…

    • 1195 Words
    • 5 Pages
    Better Essays
  • Satisfactory Essays

    Pinto Pm2 Ism Ch10 1

    • 3754 Words
    • 21 Pages

    INSTRUCTOR’S RESOURCE MANUAL CHAPTER TEN Project Scheduling: Lagging, Crashing, and Activity Networks To Accompany PROJECT MANAGEMENT: Achieving Competitive Advantage By Jeffrey K. Pinto CHAPTER 10 PROJECT FOCUS – A Crushing Issue: How to Destroy Brand New Cars INTRODUCTION 10.1 LAGS IN PRECEDENCE RELATIONSHIPS…

    • 3754 Words
    • 21 Pages
    Satisfactory Essays
  • Powerful Essays

    Enables employees to work collaboratively to achieve a goal rather than choosing their own technique or method potentially at the expense of the organisation or other employees.…

    • 2431 Words
    • 8 Pages
    Powerful Essays
  • Good Essays

    Discuss the process of defining project scope in more detail as a project progresses, going from information in a project charter to a project scope statement, WBS, and WBS dictionary.…

    • 1086 Words
    • 5 Pages
    Good Essays