2. Which of the following is not a potential advantage of using good project management? a) b) c) d) Shorter development times Higher worker morale Lower cost of capital Higher profit margins
3. Which of the following is not an attribute of a project? a) b) c) d) Projects are unique Projects are developed using progressive elaboration Projects have a primary customer or sponsor Projects involve little uncertainty
4. Which of the following is not part of the triple constraint of project management? a) b) c) d) Meeting scope goals Meeting time goals Meeting communications goals Meeting cost goals
5. The first stage of any project is a) b) c) d) Proposal Conceptualization Implementation Management 1 IIBM Institute of Business Management
Examination Paper – Project Management
6. __________________ is the application of knowledge, skills, tools and techniques to project activities to meet project requirements. a) b) c) d) Project management Program management Project portfolio management Requirements management
7. Project portfolio management addresses ____________________ goals of an organization, while project management addresses _________________ goals. a) b) c) d) Strategic, tactical Tactical, strategic Internal, external External, internal
8. Several application development projects done for the same functional group might best be managed as part of a a) b) c) d) Portfolio Program Investment Collaborative
9. Which of the following is not one of the top ten skills or competencies of an effective project manager? a) b) c) d) People skills Leadership Integrity Technical skills
10. What is the certification program called that the Project Management Institute provides? a) b) c) d) Microsoft Certified Project Manager (MCPM) Project Manager Professional (PMP) Project Management Expert (PME) Project Management