Project Management Plan
Project Management Plan

Project Title: Shed Construction at Lot 90 38-42 Wharf Road
Project Description: Development of single storey shed workshop.
Project Manager’s: A Person
Project Agency: Fred’s Sheds

Prepared For
Audience
Project/Organization Role
Mr Jones
Owner Occupier
Prepared By
Document Owner(s)
Project/Organization Role
A Person
C & A Constructions / Project Manager
Project Version Control
Version
Date
Author
Change Description
1.0.0
12/05/2011
A Person
Document created

A References & Definitions

References
AS 2000
AS 3000
AS 4000
Design blueprints for the construction of the shed
Design blueprints for the services (Power, water and access)

Definitions
DA Development Approver
PMO Project Management Office
OHS Occupation health and safety
AS 2000 Australian standards wiring
AS 3000 Australian standards building code
AS 4000 Australian standards plumbing.
GPO General Purpose Outlets
BOM Bill of materials

B Project Points of Contact Position
Title/Name/Organization
Phone
E-mail
Project Sponsor

Mr Fred’s Smith
Fred’s Sheds

Project Manager

Mr A Person
C & A Consulting

Council

Mr Ken Mathie
Ryde Council D.A

Project Team Member
Mr Jack Black
PMO Site Leader

Stakeholder
Ms Karen Dunn
Fred’s shed’s

Stakeholder

Mrs Mitchell
Neighbour

C Project Plan Summary

.1 Business Problem
Mr Jones is requesting the construction of a new shed, so he may be able to store his vehicle, tractor, fertilizer, and tools inside. On the Jones’s property there are existing sheds, some of which have been damaged over the last 10 years with costly repairs.

The construction of the shed must start no later than 6 weeks and take no longer than 3 weeks to complete as there are concerns that the bad seasonal weather may damage the vehicles, tools and fertilisers if not stored correctly.

Due to the severe local weather trends the shed must be constructed of quality materials such that the overall construction is low maintenance.

You May Also Find These Documents Helpful

  • Powerful Essays

    Early in January Fred Smith, the founder and chief executive of Fred’s Sheds, received a phone call from Mr Jones, requesting a quote to design and build a workshop on his property. Fred asked Mr Jones what size and type of shed he would like, when he wanted work to commence, and when he wanted it completed. Mr Jones told him that he required a large shed, big enough to conduct his furniture making business.…

    • 2325 Words
    • 10 Pages
    Powerful Essays
  • Good Essays

    Risk Management Plan Devry

    • 1424 Words
    • 6 Pages

    2. Delay in caging material and other needed materials for project completion. This is lack of needed items to re-build shelter cages inside and outside.…

    • 1424 Words
    • 6 Pages
    Good Essays
  • Powerful Essays

    Back Yard Deck Project

    • 8397 Words
    • 34 Pages

    Project Management Institute. (2008). A guide to the project management body of knowledge (PMBOK guide) (4th ed.). Newtown Square, PA: Project Management Institute, Inc.…

    • 8397 Words
    • 34 Pages
    Powerful Essays
  • Satisfactory Essays

    Review the list of reasons why plans fail as described in Ch. 11 of Project Management. Which of these reasons applies to defining and sequencing activities? As a project manager, what steps may you take to prevent your plan from failing?…

    • 335 Words
    • 2 Pages
    Satisfactory Essays
  • Best Essays

    Project Management Plan

    • 2196 Words
    • 8 Pages

    the International Institute for Learning, New York, New York. — Eleventh edition. retrieved on October 12, 2014 from University of Phoenix…

    • 2196 Words
    • 8 Pages
    Best Essays
  • Good Essays

    Project Plan Outline

    • 5445 Words
    • 22 Pages

    This document is an annotated outline for a Project Management Plan, adapted from the PMI Project Management Body of Knowledge (PMBOK) and IEEE Standard for Project Management Plans. The Project Management Plan is considered to be a “Best Practice” template by the ETS Enterprise Program Management Office (EPMO).…

    • 5445 Words
    • 22 Pages
    Good Essays
  • Good Essays

    Storage facilities the size of 80,000 Square feet costing £30,000 pa, which will allow suitable storage for vehicles and products.…

    • 819 Words
    • 4 Pages
    Good Essays
  • Powerful Essays

    Project management

    • 1280 Words
    • 7 Pages

    Provide evidence for grading criterion P1. (identify the various stages of the construction process for a low-rise domestic or commercial building)…

    • 1280 Words
    • 7 Pages
    Powerful Essays
  • Satisfactory Essays

    Project Management

    • 289 Words
    • 2 Pages

    You are the project manager for the project you selected and identified in the prior assignments. Using your Microsoft Project software, sketch out your action plan. Use the action plan to develop the work breakdown schedule (WBS) as follows:…

    • 289 Words
    • 2 Pages
    Satisfactory Essays
  • Satisfactory Essays

    The purpose of this document is to provide an analysis on the case study presented to us in this Project, and outline the deliverables that are required. Project Title Team Name Team Members Hsiang-Han Chao Kerry Lau Omear Saeed Qiao Zhou Ting Chan Yihang Deng Supervisor Lars Moller International Capital, Inc. - Part A Group 30…

    • 641 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Project Management

    • 2439 Words
    • 10 Pages

    b) What phase is the Project Scope produced? What are some of the items contained in this document?…

    • 2439 Words
    • 10 Pages
    Powerful Essays
  • Satisfactory Essays

    Cont’d: Manage the evaluation & selection of construction methods Available contract data is analysed in detail & summarised to enable decisions to be made on methods of construction & installation Contract data e.g. method statement; contract documents; health, safety & environmental plans In instances where available contract data is insufficient additional relevant information is obtained Additional sources of information: customer/customer's representative; contractors; sub-contractors; suppliers; statutory authorities; technical/trade literature…

    • 739 Words
    • 3 Pages
    Satisfactory Essays
  • Good Essays

    Project Management

    • 3681 Words
    • 15 Pages

    Project constraints delay the start of project activities. Three project constraint need to be considered in scheduling.…

    • 3681 Words
    • 15 Pages
    Good Essays
  • Satisfactory Essays

    Identify the problem: the problem is the difference between the current sales and the goal for sale that Modern Shed has set for itself…

    • 547 Words
    • 3 Pages
    Satisfactory Essays
  • Powerful Essays

    Decision Model Theory

    • 1245 Words
    • 5 Pages

    * The criteria for action are established at this time. According to Thompson there are two possible outcomes: the market for the storage sheds could be favorable means there is a high demand of the product or it could be unfavorable means that there is low demand of the product.…

    • 1245 Words
    • 5 Pages
    Powerful Essays

Related Topics