Ouzts Corporation is considering two alternatives: A and B. Costs associated with the alternatives are listed below:
Alternative A
Alternative B
Materials costs
$40,000
$56,000
Processing costs
$37,000
$37,000
Equipment rental
$13,000
$13,000
Occupancy costs
$15,000
$22,000
71. Are the materials costs and processing costs relevant in the choice between alternatives A and B? (Ignore the equipment rental and occupancy costs in this question.) A) Both materials costs and processing costs are relevant B) Neither materials costs nor processing costs are relevant C) Only processing costs are relevant D) Only materials costs are relevant Ans: D AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Decision Making; Reporting LO: 1 Level: Easy
72. What is the differential cost of Alternative B over Alternative A, including all of the relevant costs? A) $105,000 B) $23,000 C) $128,000 D) $116,500 Ans: B AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Decision Making; Reporting LO: 1 Level: Easy
Solution:
Alternative A
Alternative B
Differential
Costs
Materials costs
$40,000
$56,000
$16,000
Occupancy costs
$15,000
$22,000 7,000
Differential cost
$23,000
Use the following to answer questions 73-74:
Two alternatives, code-named X and Y, are under consideration at Guyer Corporation. Costs associated with the alternatives are listed below.
Alternative X
Alternative Y
Materials costs
$41,000
$59,000
Processing costs
$45,000
$45,000
Equipment rental
$17,000
$17,000
Occupancy costs
$16,000
$24,000
73. Are the materials costs and processing costs relevant in the choice between alternatives X and Y? (Ignore the equipment rental and occupancy costs in this question.) A) Neither materials costs nor processing costs are relevant B) Only processing costs are relevant C) Only materials costs are relevant D) Both