PowerGen Europe, Cologne 12. – 14. June, 2012
Willibald J. Fischer Director, GT Product Management Siemens AG Energy Sector
© Siemens AG 2012 Energy Sector
Agenda
Introduction SGT5-8000H / Irsching 4 SGT6-8000H / Berlin Test Bed Update on Further Projects Conclusion
Page 2
PowerGen Europe 2012, Cologne
© Siemens AG 2012 Energy Sector
Large-scale Siemens Gas Turbine Portfolio for 50 and 60 Hz
SGT5-8000H SGT5-4000F SGT6-8000H SGT6-5000F SGT6-4000F SGT5-2000E SGT6-2000E SGT5-8000H 04/2007 113 MW SGT6-8000H 01/2011 292 MW 274 MW 206 MW 187 MW 168 MW 375 MW
Direct scale
(50 / 60 Hz)
Page 3
PowerGen Europe 2012, Cologne
© Siemens AG 2012 Energy Sector
SGT5/6-8000H Product Line Performance and Configuration Overview
50 Hz SGT-PAC 8000H 375 MW 40 % SCC-PAC 8000H 1S 570 MW > 60 % SCC-PAC 8000H 2x1 1.140 MW > 60 % SCC-PAC 8000H 3x1 t.b.d. t.b.d. net values at ISO conditions
60 Hz 274 MW 40 % 410 MW > 60 % 820 MW > 60 % 1.230MW > 60 %
SCC5/6-8000H 2x1 SGT5/6-8000H
SCC5/6-8000H 1S
Page 4
PowerGen Europe 2012, Cologne
© Siemens AG 2012 Energy Sector
Agenda
Introduction SGT5-8000H / Irsching 4 SGT6-8000H / Berlin Test Bed Update on Further Projects Conclusion
Page 5
PowerGen Europe 2012, Cologne
© Siemens AG 2012 Energy Sector
Irsching Units 1 – 5 owned by E.ON Kraftwerke
Unit 4
SCC5-8000H 1S KW Ulrich Hartmann
Unit 1 – 3 convent. Gas Fired Units
Unit 5
SCC5-4000F 2x1
Page 6
PowerGen Europe 2012, Cologne
© Siemens AG 2012 Energy Sector
Irsching 4, Project Overview
2005
Q1 Q2 Q3 Q4
2006
Q1 Q2 Q3 Q4
2007
Q1 Q2 Q3 Q4 Q1
2008
Q2 Q3 Q4 Q1
2009
Q2 Q3 Q4
2010
Q1 Q2 Q3 Q4 Q1
2011
Q2 Q3 Q4
Phase 1 SGT5-8000H open cycle Field Validation SGT5-8000H 18 months Phase 2 Combined Cycle extension Reference Plant SCC5-8000H 1S
Open Cycle
Commercial Operation 22. July 2011
Validation 8000H
Combined Cycle