SAP Implementation Process
What is ASAP Methodology
ASAP: Accelerated Systems Application and Products in Data Processing
All implementation projects have the following phases:
Scoping - What is to be implemented i.e. which submodules are to be implemented some clients may not require credit management for example. Look at the project scope document carefully it will tell you what SAP sub-modules in SAP you should be prepared for. Usually the sales people along with project manager do it.
As is - Here you understand the existing business processes of the client . Your BPOcollect all the ISO-documentation (if client is ISO certified), reports and forms at this stage and you analyse how and when the reports/forms are generated, where the data is coming from. You also do a Level -2 training for your BPO so he is made aware of all the required transactions in SAP.
Once this is over BPO can start learning with the consultants help more about SAP. This is crucial because if you miss out any transactions the BPO may forget about some of his Business processes which may come up later. It is a good practice to ask the BPO to make flow charts to explain business processes.
To-Be - Parallely you map these processes to SAP. Processes that you are not sure of as to whether they are present in SAP or not you try to do a configuration of those processes, and along with the BPO(Business process owner he is the clients employee who knows about the clients business processes probably a middle management guy, ther can more than one), BPO involvement is required as he may be able to tell you his requirements better. Once you do the business modeling you will also be made aware of the gaps between as-is and to-be , here decisons have to be made as to whether a ABAP development/system modification is required or not and so on. Involve the BPO as much as possible and document everything