| | |Progress Report # | 03 |
| | |Reporting Period: |02.08.2011 |to |08.08.2011 |
| | |Submittal Date : |August 09, 2011 |
| |RTE/UNDP/2011/NT-1 | | |
| | | | |
|Agreement No: | | | |
|Project Name: |Structured data & voice network cabling for Election Commission, BD |
|Contractor Name: |RANA Technologies |
|Submitted To: |Mr. Jawad Akram, Program Manager, UNDP, EC Strengthen Project |
| |Mohammad Mahbubur Rahaman | | |
|Project Manager: | | | |
| |Printed Name | |Signature |
Subject Line: Week-03 Progress Report on Election Commission Structured